Scope and limitations
Concrete placement work may include formwork, reinforcement, pre-pour release, delivery checks, placement, curing and test records. Select only activities included in your package.
Use the project drawings, specification, approved mix information and inspection/test requirements to complete project-specific fields. Do not use example prompts as engineering acceptance limits.
Inspection steps in this starting template
- Planning and submittals — Confirm scope, concrete element, drawings, specifications, approved mix and test plan are identified.
Review current approved document register and pour schedule.
Project reference to complete: Contract specification, approved structural drawings, mix submission and project test plan — enter document number, revision/edition and clause/detail.
Optional reference candidates: AS 1379 (supply) and AS 3600 (structural scope), where adopted by the project. Confirm applicability, project-adopted edition and amendments.
- Set-out — Check element location, levels, dimensions and reference marks before formwork close-up.
Survey or measure against approved drawings and established control marks.
Project reference to complete: Approved set-out drawing, survey datum and specified tolerances — enter document number, revision/edition and clause/detail.
- Founding / substrate — Check exposed founding surface or substrate is the specified type, level and condition before placing concrete.
Visual inspection; compare geotechnical/design release and drawing; request geotechnical or design review where specified.
Project reference to complete: Geotechnical/design instructions, founding approval and approved structural drawing — enter document number, revision/edition and clause/detail.
- Formwork and falsework — Inspect formwork dimensions, line, level, support, cleanliness, tightness, release agent and access.
Visual and dimensional inspection against drawings and approved temporary-works design/checks.
Project reference to complete: Approved formwork/falsework design, structural drawing and project method — enter document number, revision/edition and clause/detail.
- Reinforcement materials — Verify reinforcement product identification, grade, size and traceability before fixing.
Check tags, delivery documents and material certificates against bar schedule and approved drawings.
Project reference to complete: Reinforcement schedule, material specification and project-adopted reinforcement standard — enter document number, revision/edition and clause/detail.
Optional reference candidates: The reinforcement standard named in the project specification; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.
- Reinforcement installation — Check bar position, spacing, laps, anchorage, cover supports and congestion against structural details.
Visual inspection and measurement before concrete placement.
Project reference to complete: Approved structural drawing, reinforcement detail and project specification — enter document number, revision/edition and clause/detail.
Optional reference candidates: AS 3600 where adopted; use the approved reinforcement design for actual cover/lap criteria. Confirm applicability, project-adopted edition and amendments.
- Cast-in items and joints — Check cast-in plates, bolts, sleeves, conduits, waterstops, construction joints and isolation joints.
Compare location, type and fixing against approved coordination/structural details; measure critical set-out.
Project reference to complete: Approved cast-in, joint and waterstop details plus applicable product instructions — enter document number, revision/edition and clause/detail.
- Pre-pour release — Confirm prerequisites are complete and the pour area is ready; record the actual release decision.
Complete pre-pour checklist covering formwork, reinforcement, embeds, cleanliness, access, weather/contingency and required approvals.
Project reference to complete: Approved pour checklist, project specification and contractual notice/release procedure — enter document number, revision/edition and clause/detail.
- Concrete delivery and batch identity — Check each delivery docket and identify the supplied mix, batch, quantity and arrival/discharge times.
Review docket at receipt and reconcile mix ID against approved order and pour location.
Project reference to complete: Approved mix submission, supply specification and project-adopted concrete supply standard — enter document number, revision/edition and clause/detail.
Optional reference candidates: AS 1379; the catalogue lists AS 1379:2026, but confirm the project-adopted edition. Confirm applicability, project-adopted edition and amendments.
- Fresh concrete checks — Perform specified fresh concrete tests and sampling and identify specimens to the relevant pour/batch.
Use project-nominated test method, equipment and competent tester; label specimens with sample, batch and element IDs.
Project reference to complete: Project test plan, nominated fresh-concrete test methods and acceptance specification — enter document number, revision/edition and clause/detail.
Optional reference candidates: The applicable AS 1012 parts nominated by the project test plan; AS 1379 where adopted. Confirm applicability, project-adopted edition and amendments.
- Placement and consolidation — Observe placement sequence, discharge location, continuity, segregation, consolidation and construction-joint treatment.
Site observation during placement; note interruptions, method and corrective action.
Project reference to complete: Approved placement/compaction method, mix instructions and project specification — enter document number, revision/edition and clause/detail.
- Finishing and surface — Inspect finish, falls, edges, joints and surface condition against drawings and finish schedule.
Visual and dimensional checks with straightedge/level or survey method stated by project.
Project reference to complete: Approved finish schedule, drawing detail and project surface tolerance specification — enter document number, revision/edition and clause/detail.
- Curing and protection — Start and maintain specified curing and protect concrete from weather, early loading, impact and contamination.
Record curing method, start/end, interruptions and protection measures.
Project reference to complete: Approved curing/protection method and project concrete specification — enter document number, revision/edition and clause/detail.
- Strength specimen results — Track laboratory reports for specimens to their concrete batch, element, test age and specified strength.
Review lab report identity, method, curing/custody details and results against project criteria; refer adverse or missing results.
Project reference to complete: Project strength test plan, nominated specimen/test methods and acceptance specification — enter document number, revision/edition and clause/detail.
Optional reference candidates: The applicable AS 1012 specimen/strength-test parts nominated by the project; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.
- Strip, survey, defects and closeout — Verify approved stripping/loading status, finished geometry and defect/repair disposition; compile records.
Check release instructions, survey/measure against drawings, inspect defects and close out records/NCRs.
Project reference to complete: Approved stripping/loading criteria, survey tolerances and authorised defect/repair instructions — enter document number, revision/edition and clause/detail.
How to complete the project fields
- Identify the actual work package and remove steps outside its scope.
- For each retained check, cite the current drawing, specification, product instruction or approved project document.
- Enter project acceptance requirements exactly from those sources and agree inspection responsibilities and release points.
- Keep measurements, observations, dates and signatures blank until checks are performed on site.
Source notes
The starting structure is a general planning aid. The links below explain topic context; they do not set universal project acceptance values.
- NSW Government Quality Management Guidelines for Construction, Appendix D (ITP guidance)
Limited methodology context only: the NSW public page identifies a construction ITP guideline/checklist resource and contract-level quality planning. The linked Appendix D document itself was not inspected, so no detailed template fields or technical acceptance rules are attributed to it.
- Queensland TMR MRTS70 Concrete (July 2022)
Inspected topic-specific technical example for Queensland transport/infrastructure concrete. In-situ topics are supported by Section 15; Section 17 is only relevant to its stated normal-class scope. Use numerical or procedural criteria only where the customer project adopts this edition and relevant annexures; not a general building requirement.
- Hutchinson Builders, Construction ITPs and Reports suite (downloadable Word examples)
Australian builder industry examples support high-level task sequencing, separate groundworks/concrete/steel process stages, records and lot/report fields only. Examples are explicitly marked EXAMPLE; they are not standards and provide no universal acceptance values or test rates. Original templates are not redistributed or copied.
- Standards Australia catalogue — AS 1379:2026, Specification and supply of concrete (metadata only)
AS 1379:2026; catalogue status Current; published 22 May 2026; metadata checked 7 October 2026. Edition-awareness pointer only; full standard text was not inspected. A new publication does not automatically amend a contract, adopted standard edition or MRTS70 July 2022. Confirm project adoption and applicable amendments before citing clauses or using acceptance values.
- Standards Australia catalogue — AS 3600:2018, Concrete structures (metadata only)
AS 3600:2018; catalogue status Pending Revision; metadata checked 7 October 2026. Optional structural-reference pointer only; full standard and amendment texts were not inspected. Confirm applicability, project-adopted edition and amendments. Catalogue metadata does not establish technical compliance or supply project acceptance criteria.