CON · Free editable resource

Concrete ITP template and inspection checklist

From pre-pour checks and concrete delivery to curing, strength reports and final inspection.

Scope and limitations

Concrete placement work may include formwork, reinforcement, pre-pour release, delivery checks, placement, curing and test records. Select only activities included in your package.

Use the project drawings, specification, approved mix information and inspection/test requirements to complete project-specific fields. Do not use example prompts as engineering acceptance limits.

Inspection steps in this starting template

  • Planning and submittals — Confirm scope, concrete element, drawings, specifications, approved mix and test plan are identified.

    Review current approved document register and pour schedule.

    Project reference to complete: Contract specification, approved structural drawings, mix submission and project test plan — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 1379 (supply) and AS 3600 (structural scope), where adopted by the project. Confirm applicability, project-adopted edition and amendments.

  • Set-out — Check element location, levels, dimensions and reference marks before formwork close-up.

    Survey or measure against approved drawings and established control marks.

    Project reference to complete: Approved set-out drawing, survey datum and specified tolerances — enter document number, revision/edition and clause/detail.

  • Founding / substrate — Check exposed founding surface or substrate is the specified type, level and condition before placing concrete.

    Visual inspection; compare geotechnical/design release and drawing; request geotechnical or design review where specified.

    Project reference to complete: Geotechnical/design instructions, founding approval and approved structural drawing — enter document number, revision/edition and clause/detail.

  • Formwork and falsework — Inspect formwork dimensions, line, level, support, cleanliness, tightness, release agent and access.

    Visual and dimensional inspection against drawings and approved temporary-works design/checks.

    Project reference to complete: Approved formwork/falsework design, structural drawing and project method — enter document number, revision/edition and clause/detail.

  • Reinforcement materials — Verify reinforcement product identification, grade, size and traceability before fixing.

    Check tags, delivery documents and material certificates against bar schedule and approved drawings.

    Project reference to complete: Reinforcement schedule, material specification and project-adopted reinforcement standard — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The reinforcement standard named in the project specification; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Reinforcement installation — Check bar position, spacing, laps, anchorage, cover supports and congestion against structural details.

    Visual inspection and measurement before concrete placement.

    Project reference to complete: Approved structural drawing, reinforcement detail and project specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 3600 where adopted; use the approved reinforcement design for actual cover/lap criteria. Confirm applicability, project-adopted edition and amendments.

  • Cast-in items and joints — Check cast-in plates, bolts, sleeves, conduits, waterstops, construction joints and isolation joints.

    Compare location, type and fixing against approved coordination/structural details; measure critical set-out.

    Project reference to complete: Approved cast-in, joint and waterstop details plus applicable product instructions — enter document number, revision/edition and clause/detail.

  • Pre-pour release — Confirm prerequisites are complete and the pour area is ready; record the actual release decision.

    Complete pre-pour checklist covering formwork, reinforcement, embeds, cleanliness, access, weather/contingency and required approvals.

    Project reference to complete: Approved pour checklist, project specification and contractual notice/release procedure — enter document number, revision/edition and clause/detail.

  • Concrete delivery and batch identity — Check each delivery docket and identify the supplied mix, batch, quantity and arrival/discharge times.

    Review docket at receipt and reconcile mix ID against approved order and pour location.

    Project reference to complete: Approved mix submission, supply specification and project-adopted concrete supply standard — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 1379; the catalogue lists AS 1379:2026, but confirm the project-adopted edition. Confirm applicability, project-adopted edition and amendments.

  • Fresh concrete checks — Perform specified fresh concrete tests and sampling and identify specimens to the relevant pour/batch.

    Use project-nominated test method, equipment and competent tester; label specimens with sample, batch and element IDs.

    Project reference to complete: Project test plan, nominated fresh-concrete test methods and acceptance specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The applicable AS 1012 parts nominated by the project test plan; AS 1379 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Placement and consolidation — Observe placement sequence, discharge location, continuity, segregation, consolidation and construction-joint treatment.

    Site observation during placement; note interruptions, method and corrective action.

    Project reference to complete: Approved placement/compaction method, mix instructions and project specification — enter document number, revision/edition and clause/detail.

  • Finishing and surface — Inspect finish, falls, edges, joints and surface condition against drawings and finish schedule.

    Visual and dimensional checks with straightedge/level or survey method stated by project.

    Project reference to complete: Approved finish schedule, drawing detail and project surface tolerance specification — enter document number, revision/edition and clause/detail.

  • Curing and protection — Start and maintain specified curing and protect concrete from weather, early loading, impact and contamination.

    Record curing method, start/end, interruptions and protection measures.

    Project reference to complete: Approved curing/protection method and project concrete specification — enter document number, revision/edition and clause/detail.

  • Strength specimen results — Track laboratory reports for specimens to their concrete batch, element, test age and specified strength.

    Review lab report identity, method, curing/custody details and results against project criteria; refer adverse or missing results.

    Project reference to complete: Project strength test plan, nominated specimen/test methods and acceptance specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The applicable AS 1012 specimen/strength-test parts nominated by the project; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Strip, survey, defects and closeout — Verify approved stripping/loading status, finished geometry and defect/repair disposition; compile records.

    Check release instructions, survey/measure against drawings, inspect defects and close out records/NCRs.

    Project reference to complete: Approved stripping/loading criteria, survey tolerances and authorised defect/repair instructions — enter document number, revision/edition and clause/detail.

How to complete the project fields

  1. Identify the actual work package and remove steps outside its scope.
  2. For each retained check, cite the current drawing, specification, product instruction or approved project document.
  3. Enter project acceptance requirements exactly from those sources and agree inspection responsibilities and release points.
  4. Keep measurements, observations, dates and signatures blank until checks are performed on site.

Source notes

The starting structure is a general planning aid. The links below explain topic context; they do not set universal project acceptance values.

  • NSW Government Quality Management Guidelines for Construction, Appendix D (ITP guidance)

    Limited methodology context only: the NSW public page identifies a construction ITP guideline/checklist resource and contract-level quality planning. The linked Appendix D document itself was not inspected, so no detailed template fields or technical acceptance rules are attributed to it.

  • Queensland TMR MRTS70 Concrete (July 2022)

    Inspected topic-specific technical example for Queensland transport/infrastructure concrete. In-situ topics are supported by Section 15; Section 17 is only relevant to its stated normal-class scope. Use numerical or procedural criteria only where the customer project adopts this edition and relevant annexures; not a general building requirement.

  • Hutchinson Builders, Construction ITPs and Reports suite (downloadable Word examples)

    Australian builder industry examples support high-level task sequencing, separate groundworks/concrete/steel process stages, records and lot/report fields only. Examples are explicitly marked EXAMPLE; they are not standards and provide no universal acceptance values or test rates. Original templates are not redistributed or copied.

  • Standards Australia catalogue — AS 1379:2026, Specification and supply of concrete (metadata only)

    AS 1379:2026; catalogue status Current; published 22 May 2026; metadata checked 7 October 2026. Edition-awareness pointer only; full standard text was not inspected. A new publication does not automatically amend a contract, adopted standard edition or MRTS70 July 2022. Confirm project adoption and applicable amendments before citing clauses or using acceptance values.

  • Standards Australia catalogue — AS 3600:2018, Concrete structures (metadata only)

    AS 3600:2018; catalogue status Pending Revision; metadata checked 7 October 2026. Optional structural-reference pointer only; full standard and amendment texts were not inspected. Confirm applicability, project-adopted edition and amendments. Catalogue metadata does not establish technical compliance or supply project acceptance criteria.

Continue with the related work

Choose the next resource for your task.

Prepare this plan

Keep the work package, inspection sequence and record under the same project references.

Define criteria and control points

Resolve the project requirement, notice and release arrangements before site checks.

Capture and close out the evidence

These blank records support the relevant work stages; complete actual results on site.

Browse guides by task · Browse field and quality records

Browser editor

Loading the editable Concrete plan… If the editor does not load, download a file above.

  • Planning and submittals — Confirm scope, concrete element, drawings, specifications, approved mix and test plan are identified.

    Review current approved document register and pour schedule.

    Project reference to complete: Contract specification, approved structural drawings, mix submission and project test plan — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 1379 (supply) and AS 3600 (structural scope), where adopted by the project. Confirm applicability, project-adopted edition and amendments.

  • Set-out — Check element location, levels, dimensions and reference marks before formwork close-up.

    Survey or measure against approved drawings and established control marks.

    Project reference to complete: Approved set-out drawing, survey datum and specified tolerances — enter document number, revision/edition and clause/detail.

  • Founding / substrate — Check exposed founding surface or substrate is the specified type, level and condition before placing concrete.

    Visual inspection; compare geotechnical/design release and drawing; request geotechnical or design review where specified.

    Project reference to complete: Geotechnical/design instructions, founding approval and approved structural drawing — enter document number, revision/edition and clause/detail.

  • Formwork and falsework — Inspect formwork dimensions, line, level, support, cleanliness, tightness, release agent and access.

    Visual and dimensional inspection against drawings and approved temporary-works design/checks.

    Project reference to complete: Approved formwork/falsework design, structural drawing and project method — enter document number, revision/edition and clause/detail.

  • Reinforcement materials — Verify reinforcement product identification, grade, size and traceability before fixing.

    Check tags, delivery documents and material certificates against bar schedule and approved drawings.

    Project reference to complete: Reinforcement schedule, material specification and project-adopted reinforcement standard — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The reinforcement standard named in the project specification; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Reinforcement installation — Check bar position, spacing, laps, anchorage, cover supports and congestion against structural details.

    Visual inspection and measurement before concrete placement.

    Project reference to complete: Approved structural drawing, reinforcement detail and project specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 3600 where adopted; use the approved reinforcement design for actual cover/lap criteria. Confirm applicability, project-adopted edition and amendments.

  • Cast-in items and joints — Check cast-in plates, bolts, sleeves, conduits, waterstops, construction joints and isolation joints.

    Compare location, type and fixing against approved coordination/structural details; measure critical set-out.

    Project reference to complete: Approved cast-in, joint and waterstop details plus applicable product instructions — enter document number, revision/edition and clause/detail.

  • Pre-pour release — Confirm prerequisites are complete and the pour area is ready; record the actual release decision.

    Complete pre-pour checklist covering formwork, reinforcement, embeds, cleanliness, access, weather/contingency and required approvals.

    Project reference to complete: Approved pour checklist, project specification and contractual notice/release procedure — enter document number, revision/edition and clause/detail.

  • Concrete delivery and batch identity — Check each delivery docket and identify the supplied mix, batch, quantity and arrival/discharge times.

    Review docket at receipt and reconcile mix ID against approved order and pour location.

    Project reference to complete: Approved mix submission, supply specification and project-adopted concrete supply standard — enter document number, revision/edition and clause/detail.

    Optional reference candidates: AS 1379; the catalogue lists AS 1379:2026, but confirm the project-adopted edition. Confirm applicability, project-adopted edition and amendments.

  • Fresh concrete checks — Perform specified fresh concrete tests and sampling and identify specimens to the relevant pour/batch.

    Use project-nominated test method, equipment and competent tester; label specimens with sample, batch and element IDs.

    Project reference to complete: Project test plan, nominated fresh-concrete test methods and acceptance specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The applicable AS 1012 parts nominated by the project test plan; AS 1379 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Placement and consolidation — Observe placement sequence, discharge location, continuity, segregation, consolidation and construction-joint treatment.

    Site observation during placement; note interruptions, method and corrective action.

    Project reference to complete: Approved placement/compaction method, mix instructions and project specification — enter document number, revision/edition and clause/detail.

  • Finishing and surface — Inspect finish, falls, edges, joints and surface condition against drawings and finish schedule.

    Visual and dimensional checks with straightedge/level or survey method stated by project.

    Project reference to complete: Approved finish schedule, drawing detail and project surface tolerance specification — enter document number, revision/edition and clause/detail.

  • Curing and protection — Start and maintain specified curing and protect concrete from weather, early loading, impact and contamination.

    Record curing method, start/end, interruptions and protection measures.

    Project reference to complete: Approved curing/protection method and project concrete specification — enter document number, revision/edition and clause/detail.

  • Strength specimen results — Track laboratory reports for specimens to their concrete batch, element, test age and specified strength.

    Review lab report identity, method, curing/custody details and results against project criteria; refer adverse or missing results.

    Project reference to complete: Project strength test plan, nominated specimen/test methods and acceptance specification — enter document number, revision/edition and clause/detail.

    Optional reference candidates: The applicable AS 1012 specimen/strength-test parts nominated by the project; AS 3600 where adopted. Confirm applicability, project-adopted edition and amendments.

  • Strip, survey, defects and closeout — Verify approved stripping/loading status, finished geometry and defect/repair disposition; compile records.

    Check release instructions, survey/measure against drawings, inspect defects and close out records/NCRs.

    Project reference to complete: Approved stripping/loading criteria, survey tolerances and authorised defect/repair instructions — enter document number, revision/edition and clause/detail.