FTG · Scoped work package

Concrete Footings Construction ITP Template

Reusable editable baseline for cast-in-place building pad, strip and ground-beam footings within a defined package. Covers approved foundation/design basis, excavation handover, set-out, reinforcement/starters, formwork/embeds, pre-pour authorization, concrete delivery/testing, placement, curing, stripping/loading controls and closeout. Excludes piles, bored piers, underpinning, retaining structures, precast footings and ground improvement unless separately specified. No geotechnical acceptance, design values, excavation safety method, tolerances, test rates or release authority is supplied.

What this plan covers

Reusable editable baseline for cast-in-place building pad, strip and ground-beam footings within a defined package. Covers approved foundation/design basis, excavation handover, set-out, reinforcement/starters, formwork/embeds, pre-pour authorization, concrete delivery/testing, placement, curing, stripping/loading controls and closeout. Excludes piles, bored piers, underpinning, retaining structures, precast footings and ground improvement unless separately specified. No geotechnical acceptance, design values, excavation safety method, tolerances, test rates or release authority is supplied.

Topic-guidance baseline only. Its rows are proposed checks, not project requirements. Confirm the actual contract, adopted jurisdictional provisions, current approved design and project quality plan. Complete every row with source-backed criteria, project-defined inspection coverage, actual roles and release authority. No engineering values, test rates, statutory or contractual Hold/Witness points, or signatures are supplied.

Project-specific ITP drafting for this package

A project-specific footing ITP can map excavation and founding release, set-out, reinforcement and embeds, pre-pour review, concrete supply and placement, curing, stripping and closeout to the actual footing types and pour lots. Criteria, test rates and release authority are taken from supplied controlled documents.

Useful files to provide

Example of an input still needed

For example: “Please send the approved footing schedule revision and geotechnical founding-release process; the current upload shows grids but no bearing acceptance or release owner.”

A project-specific concrete footings ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.

How the plan and blank records fit together

The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as Footing / grid, Observed founding condition, Bar / schedule mark provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.

Define the package before tailoring it

Included elements and pour lots
List element types, limits, pours and excluded work.
Foundation design and ground basis
Identify approved foundation design, geotechnical/ground classification, bearing criteria and excavation release responsibility.
Footing schedule and interfaces
Identify footing type, grid/levels, starters, columns/walls supported, adjacent services and pour segmentation.
Excavation and formation release
Identify required excavation inspection, geotechnical/design review, authority notification and evidence before concrete.

Inspection sequence and project requirements

This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

FND-01 · Package design and footing schedule

Work stage
Package design and footing schedule
Inspection / test
Confirm each footing type, location, support condition, drawings, mix and test requirements before excavation or procurement.
Method
Reconcile footing schedule, structural details, ground report, service conflicts, concrete mix and project-specific inspections; escalate conflicting or incomplete design inputs.
Acceptance condition
For [Fill: Element / pour / lot], current [Fill: Approved drawings and revisions], [Fill: Foundation design and ground basis] and [Fill: Footing schedule and interfaces] control the footing geometry and ground basis; approved mix [Fill: Approved concrete mix and supplier submission] and tests [Fill: Project test plan and acceptance] are identified.
Timing / coverage
Proposed: Before excavation and whenever controlling design documents change.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing schedule and design coordination register
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Element / pour / lot; Approved drawings and revisions; Foundation design and ground basis; Footing schedule and interfaces; Approved concrete mix and supplier submission; Project test plan and acceptance; Person/role performing this check; Person/role reviewing this check; Notice and release authority
Blank record fields
Footing type / ID; Grid / level; Drawing / revision; Geotechnical/design basis ref; Conflict / RFI ref

FND-02 · Excavation and founding surface handover

Work stage
Excavation and founding surface handover
Inspection / test
Record actual excavation limits and the assigned inspection/release of the founding condition before blinding, reinforcement or concrete conceals it.
Method
Identify each footing excavation; compare location and depth to approved details; arrange project-required geotechnical/designer inspection; record water, disturbed ground, unsuitable material and instructions.
Acceptance condition
Excavation is accepted only against [Fill: Excavation and formation release] and the assigned geotechnical/design authority; visual observation alone does not establish bearing capacity or soil classification.
Timing / coverage
Proposed: Each footing or agreed inspection lot before concealment, subject to project notice and coverage requirements.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing excavation and founding release record
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Excavation and formation release; Foundation design and ground basis; Approved drawings and revisions; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / excavation ID; Grid / level; Measured dimensions / depth; Observed founding condition; Geotechnical/design inspection ref; Role / date / release ref

FND-03 · Set-out, footing geometry and adjacent services

Work stage
Set-out, footing geometry and adjacent services
Inspection / test
Check footing location, orientation, level, steps, offsets and clearance from adjacent works against current approved drawings.
Method
Record actual measurements and method; coordinate service crossings, easements, property interfaces and adjacent footing sequence with relevant package records.
Acceptance condition
Measured location and geometry match [Fill: Footing schedule and interfaces] and [Fill: Approved drawings and revisions]; deviations and service conflicts have written design disposition before pour.
Timing / coverage
Proposed: Each defined footing lot before reinforcement limits access.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing set-out and interface check
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Footing schedule and interfaces; Approved drawings and revisions; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing ID / grid; Actual location / level; Measure method / equipment; Service/interface ref; Deviation / disposition ref

FND-04 · Reinforcement, starters and cast-in items

Work stage
Reinforcement, starters and cast-in items
Inspection / test
Check scheduled bars, anchorage/lap locations, starter bars, column/wall interfaces, cover supports and cast-in items against approved details.
Method
Verify identifiers and placement from approved bar schedule; record locations and specified measurement method; reconcile starter projections, waterstops or embeds where designed.
Acceptance condition
Reinforcement, starters and embeds match [Fill: Approved drawings and revisions] and [Fill: Project specification and adopted standards]; all dimensional/cover criteria are taken from those approved documents, not generic values.
Timing / coverage
Proposed: Before concrete placement for each designated footing area, with coverage set by project ITP.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing reinforcement and embed pre-pour record
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Approved drawings and revisions; Project specification and adopted standards; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / grid; Bar / schedule mark; Starter / supported element ID; Measured cover / method; Embed / waterstop ref; Issue / disposition ref

FND-05 · Formwork and pre-pour readiness

Work stage
Formwork and pre-pour readiness
Inspection / test
Inspect any footing forms, construction joints, interfaces, access and final cleanliness; document the project-assigned pre-pour review and release.
Method
Walk each defined pour area; compare geometry, stability evidence, base condition, reinforcement/embeds and approved method with the pour checklist and actual ITP notice.
Acceptance condition
Pre-pour status is recorded against [Fill: Approved drawings and revisions], [Fill: Project specification and adopted standards] and [Fill: Notice and release authority]; only the identified authority can record formal release or contractual acceptance.
Timing / coverage
Proposed: Before each defined pour and before concrete placement begins.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing pre-pour and release register
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Approved drawings and revisions; Project specification and adopted standards; Notice and release authority; Project evidence and closeout requirements; Person/role performing this check; Person/role reviewing this check
Blank record fields
Pour / footing IDs; Formwork / method ref; Base / cleanliness observation; Open item / action; Installer / role / date; Release person / role / date / ref

FND-06 · Concrete delivery and specified fresh tests

Work stage
Concrete delivery and specified fresh tests
Inspection / test
Verify concrete docket/mix traceability and capture only project-required tests and samples.
Method
Compare load identity and delivery records to approved mix; record actual addition/rejection; tag fresh tests and specimens to footing, batch, location and named tester.
Acceptance condition
Delivery and results are judged against [Fill: Approved concrete mix and supplier submission] and [Fill: Project test plan and acceptance]; strength, workability, temperature, sampling frequency and rejection rules are not filled in by this baseline.
Timing / coverage
Proposed: For each load/test/sample required by the project test plan.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing delivery and fresh test register
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Approved concrete mix and supplier submission; Project test plan and acceptance; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / pour ID; Batch / docket; Mix ID; Sample / test ID; Actual result / units; Tester / role / report ref

FND-07 · Placement and consolidation around bars / starters

Work stage
Placement and consolidation around bars / starters
Inspection / test
Observe discharge, lift/sequence, consolidation around congested reinforcement, starter bars, forms and embedded items.
Method
Record observed zone and sequence; compare placement equipment and procedure with approved method; note interruptions, movement, leakage, segregation or corrective action.
Acceptance condition
Placement follows approved [Fill: Project specification and adopted standards] and method; movement, void risk, unplanned joints or other departures are documented and dispositioned before dependent construction.
Timing / coverage
Proposed: During each pour at the project-defined observation coverage.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing placement log
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Approved drawings and revisions; Project specification and adopted standards; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / placement zone; Placement time; Sequence / lift; Starter / embed observation; Interruption / issue / action ref

FND-08 · Curing, stripping and loading control

Work stage
Curing, stripping and loading control
Inspection / test
Record the specified curing/protection and any project-controlled form removal, backfill, column start or loading release.
Method
Compare actual timing, method and conditions to approved concrete/design instructions; record any engineer/project authorization for stripping or loading.
Acceptance condition
Curing and subsequent work comply with [Fill: Project specification and adopted standards] and documented [Fill: Stripping / loading release requirements]; no stripping time, strength threshold, backfill permission or load allowance is presumed.
Timing / coverage
Proposed: Monitor from placement through each specified release milestone.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing curing and early-work release record
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Project specification and adopted standards; Stripping / loading release requirements; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / pour ID; Curing / protection method; Start date/time; Strip / backfill date and authority ref; Loading / next-stage release ref

FND-09 · Strength reports, defects and final handover

Work stage
Strength reports, defects and final handover
Inspection / test
Link specified concrete test results, survey, visible defects/repairs and footing records to the supported structure.
Method
Compare laboratory reports and as-built records against project criteria; refer adverse results, honeycombing or geometry issues for responsible design disposition and verify closure.
Acceptance condition
Results and geometry satisfy [Fill: Project test plan and acceptance] and [Fill: Project specification and adopted standards] or are formally dispositioned; files and outstanding items reconcile with [Fill: Project evidence and closeout requirements].
Timing / coverage
Proposed: On receipt of required reports, before dependent loading where specified, and at package closeout.
Responsible role
Proposed: [Fill: Person/role performing this check] performs and records; [Fill: Person/role reviewing this check] reviews only where assigned by project documents.
Control / release arrangement
Proposed record point only. Confirm any contractual or regulatory Hold/Witness point, notice period, release authority and evidence from the project documents; none is assigned by this baseline. [Fill: Notice and release authority]
Record
Footing results and closeout register
Project document reference
Approved project drawings, specification, mix, inspection/test plan and written dispositions — enter exact document number, revision and clause/detail.
Project inputs to resolve
Project test plan and acceptance; Project specification and adopted standards; Project evidence and closeout requirements; Notice and release authority; Person/role performing this check; Person/role reviewing this check
Blank record fields
Footing / supported element; Sample / batch ID; Lab / survey report ref; Actual result / units; Defect / repair / disposition ref; Handover record ref

Source notes

Connect the plan to field evidence

How to write a concrete ITP · Compare the broader concrete scope

Need your concrete footings ITP prepared for this project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.

Browser editor

Loading the editable concrete footings plan. Download a file above if the editor is unavailable.