Concrete · Free field record

Pre-Pour Inspection Checklist

A printable site record for checking ordinary cast-in-place slabs and footings before concrete placement.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Pre-placement checks for ordinary cast-in-place concrete slabs, pad footings and strip footings: document readiness, set-out and founding, formwork, reinforcement, cast-in items and joints, cleanliness/access, and recording the project release decision.

Outside this record: Does not cover concrete delivery or testing, placement, compaction, finishing, curing, post-pour inspection, precast, prestressing, shotcrete, piles, specialist repair, or project-specific design/engineering approval. Add separate records where those scopes apply.

Blank generic record for project adaptation. Complete each acceptance requirement and reference from current approved project documents before use. No standard engineering values, inspection results, release, certification or approval are supplied. A checklist entry is not a contractual Hold or Witness Point unless the project assigns it.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

PP-01 · Project documents and pour identification

Confirm this checklist identifies the correct project, element and pour; check current approved drawings, specification, mix approval and required test arrangements are available.

How to check
Review the project document register and pour schedule; record the applicable document numbers and revisions.
What defines acceptance
Applicable approved documents and project acceptance requirements are identified. Record unresolved conflicts or missing approvals for resolution before the pour.
Project document to cite
Project document register, approved drawings, specification, mix submittal and test plan (enter numbers/revisions below).
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-02 · Set-out and dimensions

Check element location, grid references, dimensions and levels against the approved drawings.

How to check
Survey or measure the identified points and record actual observations; compare only with project criteria.
What defines acceptance
Matches the cited approved drawing and project dimensional criteria; deviations have a documented disposition.
Project document to cite
Approved set-out / structural drawings and project dimensional criteria.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-03 · Founding or substrate

Check exposed founding surface or substrate type, level and condition; confirm any required geotechnical or design release is recorded.

How to check
Visual inspection and comparison with the approved design documents; record release reference where required.
What defines acceptance
Matches project founding/substrate requirements and any required release is documented. Refer changed or unsuitable conditions for instruction.
Project document to cite
Approved structural/geotechnical documents and project release record, where applicable.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-04 · Formwork and temporary works

Check formwork line, level, dimensions, support/bracing, tightness, cleanliness, release-agent condition and access for placement.

How to check
Visual and dimensional check against approved drawings and temporary-works documents; record any required temporary-works release.
What defines acceptance
Matches cited project formwork and temporary-works criteria; required design/check records are available; forms are clean and do not obstruct reinforcement or cast-in items.
Project document to cite
Approved formwork drawings, temporary-works design/checks and project specification.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-05 · Reinforcement identification and traceability

Check reinforcement type, size and identification against the approved bar schedule; confirm project-required certificates or traceability records are available.

How to check
Inspect tags and delivery documents; compare marks and sizes with approved drawings/schedules.
What defines acceptance
Items are identifiable and match the cited project schedule; required traceability records are recorded.
Project document to cite
Approved structural drawings, bar schedule, reinforcement submittal and project traceability requirements.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-06 · Reinforcement placement and cover

Check bar arrangement, spacing, laps, anchorage, supports, specified cover and congestion against structural details.

How to check
Visual inspection and measurement before placement; record actual values where project criteria require measurement.
What defines acceptance
Matches cited bar arrangement and cover criteria. Resolve clashes or deviations through documented project instruction before the pour.
Project document to cite
Approved structural drawings, bar schedule and project cover criteria.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-07 · Cast-in items, services and joints

Check applicable cast-in plates, bolts, sleeves, conduits, waterstops, construction/isolation joints and other embedded items for type, location, level and secure fixing.

How to check
Compare with approved structural/coordination details; measure and record critical set-out or projection required by the project.
What defines acceptance
Applicable items and joint preparation match cited project details, are secured, and remain clear for concrete placement.
Project document to cite
Approved structural and coordination drawings, embed schedules, services drawings and joint details.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

PP-08 · Pre-pour area readiness and release

Confirm preceding checks are complete, debris and standing water are addressed as required by project documents, access is ready, open issues are dispositioned, and the required project release decision is recorded.

How to check
Walk the pour area with the applicable checklist and closeout records; record the actual release status, responsible role and any required client notice/release reference.
What defines acceptance
Record the actual decision and any outstanding conditions. Proceed only when the project-assigned release conditions and contractual notice/hold requirements are satisfied.
Project document to cite
Project ITP, contract notice/release requirements, approved method and closed issue records.
Blank record fields
  • Observed condition / measurement
  • Evidence reference
  • Result, inspector and date; issue and recheck reference

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.