Formwork Inspection Checklist

A field record focused on installed formwork and temporary works: document status, supports, geometry, joints, restraint, safe access and placement-stage change control.

Excel provides separate project setup, field record and issue/handover sheets, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Installed formwork and associated falsework for ordinary cast-in-place slabs, pad footings and strip footings, before loading/concrete placement against project temporary-works documents.

Outside this record: Temporary-works design/capacity calculations, independent design certification, complex suspended falsework, bridges/highways special provisions, jump/slip/travelling forms, major lift design, prestressing, demolition/stripping/load release and whole-pour release.

Blank field checklist for project adaptation. Use actual approved documents and project acceptance criteria. Record only observations made. This is not design approval, a temporary-works certificate, contractual Hold/Witness Point release, or permission to place, strip or load.

Collect these project inputs first

Element, formwork zone, pour/lot and system identifier
Makes the inspected assembly/configuration traceable.
Approved temporary-works drawings, system details and revision
Defines installed arrangement and inspection basis.
Design assumptions, support evidence and required independent check records
Allows checking that documents match visible conditions without recalculating capacity.
Structural/formwork geometry and project dimensional criteria
Provides project dimensions and tolerances for measurements.
Current pour method, access/SWMS and change-control procedure
Connects inspection to placement, loads, safe access and field-change escalation.

How to use the checklist

  1. Define assembly boundary and gather controlled drawings, system instructions, structural interfaces, pour method and safety plan.
  2. Inspect installed configuration and interfaces at work location; record component IDs and measurements against cited documents.
  3. Keep design/check evidence separate from observations; do not infer capacity visually.
  4. If system, support, loading, geometry or access differs from documents, identify change and refer under project change control.
  5. Transfer any release decision to assigned authority and contractual ITP; this checklist does not authorize stripping.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

FW-01 · Work package documents and design-check status

Identify element/boundary, current temporary-works drawings, design revision, erection sequence and required independent check/submission records.

How to check
Compare work area with controlled document register; verify status and that check records apply to actual system/configuration.
What defines acceptance
Use project temporary-works procedure, approved drawings, specification and contract points; cite design/check status without treating field inspection as design approval.
Project document to cite
Controlled temporary-works register, approved drawings, project procedure and required design/check records.

If a discrepancy is found: Do not accept unverified/changed arrangement; refer to assigned coordinator/designer/checker and obtain project-required written record.

Topic references: Cavoren cast-in-place concrete baseline; Queensland TMR MRTS70 Concrete, July 2022; Safe Work Australia, Guide to formwork, July 2014.

Blank record fields
  • element / formwork zone
  • drawing / rev
  • design-check record ref
  • open query / response
  • Result, inspector and date; issue and recheck reference

FW-02 · System components and visible condition

Observe form face/framing, proprietary components, ties/connectors and reused parts for damage, deformation, corrosion, omissions or unapproved mixed systems.

How to check
Walk accessible faces and compare system identifiers/components with approved drawings, supplier details and inspection points.
What defines acceptance
Use approved project system/component schedule; damaged/reused component criteria come from project designer/manufacturer.
Project document to cite
Approved system/component schedule, manufacturer instructions and project condition/disposition criteria.

If a discrepancy is found: Isolate suspect components and prevent loading; obtain competent-person assessment and documented repair/replacement direction.

Topic references: Safe Work Australia, Guide to formwork, July 2014; Queensland TMR MRTS70 Concrete, July 2022.

Blank record fields
  • system / component ID
  • location / condition
  • detail / drawing ref
  • photo / disposition ref
  • Result, inspector and date; issue and recheck reference

FW-03 · Bearing, support and founding interface

Observe base plates, sole plates, bearers, props and actual ground/slab contact, including settlement, voids, disturbance or unplanned load transfer.

How to check
Inspect support points against approved details and project ground/floor information; record location and movement signs.
What defines acceptance
Use project design assumptions, approved support/founding detail and required ground/slab verification; no bearing capacity or prop load is set.
Project document to cite
Approved support/founding details, design assumptions and project ground/slab verification.

If a discrepancy is found: Keep affected area unloaded/controlled as procedure requires; refer changed condition to temporary-works designer and record resolution.

Topic references: Queensland TMR MRTS70 Concrete, July 2022; Safe Work Australia, Guide to formwork, July 2014.

Blank record fields
  • support ID / location
  • bearing detail ref
  • contact / movement
  • verification / direction ref
  • Result, inspector and date; issue and recheck reference

FW-04 · Line, level, dimensions and formed profile

Check installed form surface/edges against element geometry and setting-out information, including openings/steps in this package.

How to check
Measure project-designated points with identified instruments; record readings, grid/offset and drawing/detail.
What defines acceptance
Use approved structural/formwork drawings and project tolerances; do not use generic dimensional limits.
Project document to cite
Approved structural and formwork drawings and project dimensional criteria.

If a discrepancy is found: Mark affected points, correct under documented direction and repeat same measurements; retain initial and recheck readings.

Topic references: Queensland TMR MRTS70 Concrete, July 2022; Safe Work Australia, Guide to formwork, July 2014.

Blank record fields
  • grid / point
  • criterion / drawing ref
  • instrument / method
  • actual / unit / recheck
  • Result, inspector and date; issue and recheck reference

FW-05 · Joints, sealing and concrete-loss paths

Inspect panel joints, corners, stop-ends, kickers, penetrations and closures for gaps, movement paths and sealing per approved detail/method.

How to check
Visually inspect joints and compare materials/detail with temporary-works drawings and pour method; photograph suspected leakage paths.
What defines acceptance
Use approved project joint/sealing detail and placement method; no generic gap limit or sealant prescription applies.
Project document to cite
Approved joint/sealing details and concrete placement method.

If a discrepancy is found: Repair only using accepted method; recheck before placement and record evidence or unresolved risk.

Topic references: Safe Work Australia, Guide to formwork, July 2014; Queensland TMR MRTS70 Concrete, July 2022.

Blank record fields
  • joint / location
  • detail / material ref
  • seal condition
  • repair / recheck ref
  • Result, inspector and date; issue and recheck reference

FW-06 · Bracing, ties, connections and restraint fit

Observe braces, ties, wedges, pins, clamps and connections for presence, orientation/engagement and visible damage against approved arrangement.

How to check
Inspect drawing-identified points; compare component and installation with system instructions/project erection details.
What defines acceptance
Use approved temporary-works design and manufacturer/project details; do not infer spacing, torque, capacity or allowable deflection.
Project document to cite
Approved bracing/tie/connection details and applicable system installation instructions.

If a discrepancy is found: Do not improvise braces, remove ties or alter system; secure per procedure and obtain designer/competent-person instruction.

Topic references: Safe Work Australia, Guide to formwork, July 2014; Queensland TMR MRTS70 Concrete, July 2022.

Blank record fields
  • connection / location
  • system detail ref
  • engagement / defect
  • direction / recheck ref
  • Result, inspector and date; issue and recheck reference

FW-07 · Cast-in openings and interface coordination

Check voids, block-outs, stop-ends or form interfaces shown on coordinated project drawings and within formwork package.

How to check
Compare with current structural/coordination details; verify secure fixing and no unapproved cuts/alterations to system.
What defines acceptance
Use approved coordinated drawings and temporary-works details; field-cut penetrations require approvals set by project design process.
Project document to cite
Approved coordination/opening drawings and temporary-works alteration details.

If a discrepancy is found: Stop affected alteration/concealment; refer clash/unshown opening to designer/coordinator and record response/revised drawing.

Topic references: Safe Work Australia, Guide to formwork, July 2014; Queensland TMR MRTS70 Concrete, July 2022.

Blank record fields
  • opening / grid
  • coordination drawing ref
  • position / dimensions
  • response / recheck ref
  • Result, inspector and date; issue and recheck reference

FW-08 · Access, edge protection and work-stage safety interface

Observe access route, working platform, edge/opening protection and safe arrangement relevant to inspecting/placing concrete.

How to check
Compare visible access/protection with project SWMS, work-at-height and temporary-works plans; refer hazards to site safety process.
What defines acceptance
Apply site safety plan and jurisdictional WHS requirements; checklist does not certify a platform, edge protection or SWMS.
Project document to cite
Site SWMS, access/work-at-height plans and applicable jurisdictional WHS requirements.

If a discrepancy is found: Stop/report unsafe access under site procedures; obtain responsible safety/temporary-works role correction and verification before task resumes.

Topic references: Safe Work Australia, Guide to formwork, July 2014.

Blank record fields
  • zone / access point
  • SWMS / plan ref
  • hazard / reported role
  • correction evidence
  • Result, inspector and date; issue and recheck reference

FW-09 · Placement-stage loads, access and change control

Confirm planned placement sequence, access and equipment are covered by current approved temporary-works/method documents; identify field changes.

How to check
Review method with responsible site role and compare planned sequence/equipment/configuration to documented design assumptions.
What defines acceptance
Use approved sequence and assumptions; no allowable load, pour rate, concrete pressure or vibration criterion is supplied.
Project document to cite
Approved placement method, temporary-works assumptions and written change review.

If a discrepancy is found: Do not proceed with changed loading/undocumented configuration; obtain written reassessment by assigned designer/checker and update records.

Topic references: Safe Work Australia, Guide to formwork, July 2014; Queensland TMR MRTS70 Concrete, July 2022.

Blank record fields
  • method revision
  • design assumption ref
  • equipment / sequence
  • change approval ref
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
Props, ties, braces, components or supports differ from approved drawings.Record location and difference, prevent unassessed loading under site procedure and obtain written reassessment.
Ground, slab, bearing or movement differs from documented assumptions.Record support/location/condition and refer to temporary-works designer with actual ground/slab evidence.
Pour sequence, equipment, access, vibration or loads have changed.Request documented review against design assumptions and update controlled method/design records before proceeding.
Unsafe access or edge protection is found.Control/report through site WHS process and SWMS; this checklist does not certify safety systems.
Formwork removal or load release is requested.Use separate project/design release procedure and actual criteria/authority/evidence; this form covers pre-placement checks only.

Formwork inspection handover

This records the field inspection handover only. It is not design certification, authorization to pour, a Hold Point release, or permission to strip/load. Transfer the completed inspection and outstanding issues to the project-assigned temporary-works/project release process.

Field inspection handover status options in the blank record:

Record the assigned roles: Field inspector name / role / date; Receiving temporary-works or project role / date; Open design query, NCR or change approval reference.

Fictional document-mapping example — not a project requirement

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

A sample register lists temporary-works drawing TW-F-012 Rev B and formwork system layout SK-F-012 Rev 2 for a strip footing. These identifiers are fictional teaching placeholders only.

Requirement to carry into the record
Confirm the installed arrangement and components match the current approved temporary-works documents, and verify that required design/check records apply to this actual configuration. A field walkdown does not calculate or certify capacity.
Illustrative reference
Fictional TW-F-012 Rev B / SK-F-012 Rev 2; replace with actual project references.
What the site record should capture
Record formwork zone, installed system/configuration, drawing revisions consulted, observed support/connection condition, any mismatch and written reassessment reference. Leave observations/results blank until inspected.

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.