What this plan covers
Original editable baseline for ordinary building cold-water, heated-water and non-drinking water service pipework where selected. Covers product evidence, service routing, jointing, project-specified testing, conditional flushing/disinfection, operational checks and handover. Excludes fire-fighting, gas, process/high-pressure, HVAC, pools, off-site utility mains and specialist treatment plant. System selection and all numeric criteria must come from applicable authority, approved design and contract.
Define the package before tailoring it
- Included water services
- Select cold, heated, non-drinking/rainwater and exact system boundaries; fire-fighting water is excluded.
- Jurisdiction and adoption
- Identify state/territory authority, code adoption and project compliance pathway.
- Products and evidence
- List approved pipes, fittings, valves, devices and required product evidence.
- Testing and commissioning
- Confirm test sections, methods, limits, flushing/disinfection, sampling and records from controlled sources.
- Roles and handover
- Confirm licensed roles, authority notices/inspections, releases and records.
Inspection sequence and project requirements
This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.
WTR-01 · Service boundary and design release
- Work stage
- Service boundary and design release
- Inspection / test
- Confirm the included cold, heated and non-drinking water systems, tie-in points and work boundaries before installation.
- Method
- Compare approved service drawings, schedules, scope and interface register; distinguish potable/non-potable, cold/heated services, utility work and excluded fire/process systems.
- Acceptance condition
- Only identified services and current approved drawings are released; unresolved design, cross-connection or point-of-connection decisions are recorded for the responsible designer/authority. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Service boundaries and connection interfaces]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service scope and interface register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Jurisdiction and authority basis; Approved service drawings and revisions; Service boundaries and connection interfaces; Licensed roles, inspections and release authority
- Blank record fields
- Service/system ID; Drawing and revision; Tie-in / work boundary; Open decision reference
WTR-02 · Product approval and delivery check
- Work stage
- Product approval and delivery check
- Inspection / test
- Check pipe, fittings, valves and devices against the approved service schedule and applicable evidence-of-suitability requirements.
- Method
- Match product identity, size/material, pressure/service designation and required certification/document references to approved submittals; segregate mismatched or damaged products.
- Acceptance condition
- Products match approved project schedule and required evidence is available for the intended service and jurisdiction. No product approval is inferred from this template. Project basis: [Fill: Approved product and material schedule]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water product receipt and approval register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved product and material schedule; Project specification and adopted standards; Jurisdiction and authority basis; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Product / component; Service and location; Approval / certification reference; Condition / disposition
WTR-03 · Set-out, support and service separation
- Work stage
- Set-out, support and service separation
- Inspection / test
- Verify installed route, identification and supports against approved drawings and service coordination before concealment.
- Method
- Walk the installed section; compare route, levels/clearances, support details, sleeves and service identification to controlled drawings and coordination requirements; record deviations.
- Acceptance condition
- Installed route and support/interface details agree with approved documents; separation, access and identification requirements are resolved from project sources. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service installation and pre-cover record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved service drawings and revisions; Project specification and adopted standards; Concealment, cover and access requirements; Licensed roles, inspections and release authority
- Blank record fields
- Section / location; Drawing and revision; Support / restraint reference; Deviation / RFI reference
WTR-04 · Jointing and concealed workmanship
- Work stage
- Jointing and concealed workmanship
- Inspection / test
- Inspect completed joints and fittings while accessible, before insulation or enclosure.
- Method
- Verify joint type and installer/process evidence against manufacturer instructions and approved method; visually inspect accessible joints and record defects and repair references.
- Acceptance condition
- Jointing method and workmanship meet approved product instructions and project criteria; all identified defects are dispositioned before concealment. Project basis: [Fill: Approved product and material schedule]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water joint and pre-concealment inspection log
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved product and material schedule; Project specification and adopted standards; Concealment, cover and access requirements; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Section / location; Joint type / installer; Observation / defect; Repair / reinspection reference
WTR-05 · Pressure test readiness and isolation
- Work stage
- Pressure test readiness and isolation
- Inspection / test
- Confirm each test section, boundaries, compatible test setup and protection of connected components before testing.
- Method
- Review approved test procedure; verify section limits, gauge/instrument identification and calibration status if required, isolated appliances, test medium and safety controls.
- Acceptance condition
- Test section and procedure match project-approved test plan and applicable service requirements; vulnerable components are protected and setup is recorded before pressurisation. Project basis: [Fill: Project-specific test method and acceptance]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water pressure test setup record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Project-specific test method and acceptance; Project specification and adopted standards; Licensed roles, inspections and release authority; Project records and handover requirements
- Blank record fields
- Test section; Procedure / revision; Gauge ID / calibration reference; Isolation and protection check
WTR-06 · Pressure test and defect closeout
- Work stage
- Pressure test and defect closeout
- Inspection / test
- Record the specified water-service test result and verify repair/retest evidence where required.
- Method
- Perform the approved test for the defined section; record actual medium, set conditions, start/end readings, times, observed leakage and test instrument; repair and repeat per approved procedure.
- Acceptance condition
- Actual results satisfy only the project-approved acceptance criteria and authority pathway; failed tests remain open until documented repair and accepted retest. Do not apply WA example values unless expressly adopted. Project basis: [Fill: Project-specific test method and acceptance]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service test and retest certificate
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Project-specific test method and acceptance; Jurisdiction and authority basis; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Test section; Actual readings / result; Actual start/end time; Defect / repair / retest ref.
WTR-07 · Flushing and disinfection, where required
- Work stage
- Flushing and disinfection, where required
- Inspection / test
- Determine and complete project-required flushing, disinfection and water-quality checks before service use.
- Method
- Confirm system type, scope and written procedure; flush/disinfect only where required and by approved method; record water quality samples/results, disposal and clearance where specified.
- Acceptance condition
- Applicable flushing/disinfection and water-quality evidence meets authority and project requirements; where not required, the basis is recorded. No universal disinfection trigger, dose or residual is supplied. Project basis: [Fill: Flushing, disinfection and water quality requirements]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water flushing, disinfection and sampling record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Flushing, disinfection and water quality requirements; Jurisdiction and authority basis; Project specification and adopted standards; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- System / section; Approved procedure reference; Sample point / lab result; Clearance / disposition
WTR-08 · Operational checks and service identification
- Work stage
- Operational checks and service identification
- Inspection / test
- Check completed valves, outlets, controls, labels and access against approved schedules and operation requirements.
- Method
- Operate each scheduled item; verify intended service identification, access/isolation, flow direction and documented function; record exceptions and closeout actions.
- Acceptance condition
- Installed items match approved schedule and perform as specified; access and service identification are maintained and defects are closed. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service functional check and asset register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved service drawings and revisions; Project specification and adopted standards; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Valve / outlet / control ID; Location / service; Observed function; Defect / closeout reference
WTR-09 · Regulatory inspection and handover
- Work stage
- Regulatory inspection and handover
- Inspection / test
- Confirm required authority notifications, inspection outcomes and service records are complete for handover.
- Method
- Reconcile regulator/utility approvals, certificates, approved deviations, test/flush results, marked-up drawings and operation information against the project dossier index.
- Acceptance condition
- All required project and jurisdiction records are indexed; outstanding authority conditions, defects or exclusions are visible and not represented as accepted. Project basis: [Fill: Licensed roles, inspections and release authority]; [Fill: Project records and handover requirements].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water services commissioning and handover dossier index
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Jurisdiction and authority basis; Licensed roles, inspections and release authority; Project records and handover requirements; Service boundaries and connection interfaces
- Blank record fields
- Record / certificate; Document number / revision; Status / authority; Open condition / owner
Source notes
- Australian Building Codes Board, NCC 2022 Volume Three — Plumbing Code of Australia
Official national framework and source locator. State adoption, variations, application and project compliance pathway must be confirmed; NCC edition is not assumed to be the contract edition.
Accessed 2026-10-07; Volume Three index: Section B Water services, Section C Sanitary plumbing and drainage systems, state/territory schedules and Schedule 2 referenced documents.
- Australian Building Codes Board, NCC 2022 Volume Three — Schedule 2 Referenced documents
Confirms NCC 2022 referenced-document editions and provision cross-references only. Verify the edition actually adopted by the project jurisdiction and contract; full standards text was not used.
Accessed 2026-10-07; entries AS/NZS 3500 Part 1:2021 (B1D3 etc.), Part 2:2021 (C1/C2 provisions) and Part 3:2021 (F1D3, H2D2/H2D6 and 7.4.3).
- Australian Building Codes Board, NCC 2022 Volume Three — Section B Water services
Defines service group coverage and compliance topic routing; it does not set project-specific test methods, design values, hold points or blanket disinfection requirements.
Accessed 2026-10-07; index entries Part B1 Cold water services, B2 Heated water services, B3 Non-drinking water services, B5 Cross-connection control, B6 Rainwater services and B7 Rainwater storage.
- WA Plumbers Licensing Board, Pipe sizing and commissioning
WA-specific technical example only. Its stated pressure/time and disinfection triggers are intentionally not reproduced as generic criteria; use only if confirmed applicable by jurisdiction, contract and service design.
Version 4, May 2023: page 4 Testing and commissioning of water services flowchart; page 5 WA scope and adopted-code notes. Checked 7 October 2026.
- ABCB WaterMark, What requires WaterMark?
Topic support for checking certification applicability and product identity; not every plumbing product requires WaterMark. No individual product or installation is certified by this template.
Transcript: schedules of products/excluded products and matching certificate/product identity. Checked 7 October 2026.
Connect the plan to field evidence
- Water services pressure test record
- Sanitary drainage pre-cover inspection
- Stormwater drainage inspection
How to write a plumbing and drainage ITP · Compare the broader plumbing & drainage scope
Need an ITP prepared for your project?
Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.
USD 99 per defined work package · Within 24 hours after the required project files are complete.