What this plan covers
Original editable baseline for ordinary building cold-water, heated-water and non-drinking water service pipework where selected. Covers product evidence, service routing, jointing, project-specified testing, conditional flushing/disinfection, operational checks and handover. Excludes fire-fighting, gas, process/high-pressure, HVAC, pools, off-site utility mains and specialist treatment plant. System selection and all numeric criteria must come from applicable authority, approved design and contract.
Project-specific ITP drafting for this package
A project ITP can trace water pipe identification, supports, joints, penetrations, cross-connection interfaces and project-specified tests by system section, then capture the required report and handover evidence. Test pressures, durations, notices and sign-off roles must be supplied or confirmed from governing project sources.
Useful files to provide
- Current water-services layouts, risers and connection / isolation boundaries
- Approved pipe, valve and fitting schedule with product submittals
- Adopted jurisdiction / authority process and required inspection or certificate pathway
- Project pressure / flushing / disinfection procedures, criteria and licensed roles
Example of an input still needed
For example: “The riser drawing is present, but the approved pressure-test procedure and authority inspection pathway are missing. Please provide those documents and the nominated licensed tester.”
A project-specific water services installation ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.
How the plan and blank records fit together
The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as Service/system ID, Test section, Procedure / revision provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.
Define the package before tailoring it
- Included water services
- Select cold, heated, non-drinking/rainwater and exact system boundaries; fire-fighting water is excluded.
- Jurisdiction and adoption
- Identify state/territory authority, code adoption and project compliance pathway.
- Products and evidence
- List approved pipes, fittings, valves, devices and required product evidence.
- Testing and commissioning
- Confirm test sections, methods, limits, flushing/disinfection, sampling and records from controlled sources.
- Roles and handover
- Confirm licensed roles, authority notices/inspections, releases and records.
Inspection sequence and project requirements
WTR-01 · Service boundary and design release
- Work stage
- Service boundary and design release
- Inspection / test
- Confirm the included cold, heated and non-drinking water systems, tie-in points and work boundaries before installation.
- Method
- Compare approved service drawings, schedules, scope and interface register; distinguish potable/non-potable, cold/heated services, utility work and excluded fire/process systems.
- Acceptance condition
- Only identified services and current approved drawings are released; unresolved design, cross-connection or point-of-connection decisions are recorded for the responsible designer/authority. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Service boundaries and connection interfaces]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service scope and interface register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Jurisdiction and authority basis; Approved service drawings and revisions; Service boundaries and connection interfaces; Licensed roles, inspections and release authority
- Blank record fields
- Service/system ID; Drawing and revision; Tie-in / work boundary; Open decision reference
WTR-02 · Product approval and delivery check
- Work stage
- Product approval and delivery check
- Inspection / test
- Check pipe, fittings, valves and devices against the approved service schedule and applicable evidence-of-suitability requirements.
- Method
- Match product identity, size/material, pressure/service designation and required certification/document references to approved submittals; segregate mismatched or damaged products.
- Acceptance condition
- Products match approved project schedule and required evidence is available for the intended service and jurisdiction. No product approval is inferred from this template. Project basis: [Fill: Approved product and material schedule]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water product receipt and approval register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved product and material schedule; Project specification and adopted standards; Jurisdiction and authority basis; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Product / component; Service and location; Approval / certification reference; Condition / disposition
WTR-03 · Set-out, support and service separation
- Work stage
- Set-out, support and service separation
- Inspection / test
- Verify installed route, identification and supports against approved drawings and service coordination before concealment.
- Method
- Walk the installed section; compare route, levels/clearances, support details, sleeves and service identification to controlled drawings and coordination requirements; record deviations.
- Acceptance condition
- Installed route and support/interface details agree with approved documents; separation, access and identification requirements are resolved from project sources. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service installation and pre-cover record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved service drawings and revisions; Project specification and adopted standards; Concealment, cover and access requirements; Licensed roles, inspections and release authority
- Blank record fields
- Section / location; Drawing and revision; Support / restraint reference; Deviation / RFI reference
WTR-04 · Jointing and concealed workmanship
- Work stage
- Jointing and concealed workmanship
- Inspection / test
- Inspect completed joints and fittings while accessible, before insulation or enclosure.
- Method
- Verify joint type and installer/process evidence against manufacturer instructions and approved method; visually inspect accessible joints and record defects and repair references.
- Acceptance condition
- Jointing method and workmanship meet approved product instructions and project criteria; all identified defects are dispositioned before concealment. Project basis: [Fill: Approved product and material schedule]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water joint and pre-concealment inspection log
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved product and material schedule; Project specification and adopted standards; Concealment, cover and access requirements; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Section / location; Joint type / installer; Observation / defect; Repair / reinspection reference
WTR-05 · Pressure test readiness and isolation
- Work stage
- Pressure test readiness and isolation
- Inspection / test
- Confirm each test section, boundaries, compatible test setup and protection of connected components before testing.
- Method
- Review approved test procedure; verify section limits, gauge/instrument identification and calibration status if required, isolated appliances, test medium and safety controls.
- Acceptance condition
- Test section and procedure match project-approved test plan and applicable service requirements; vulnerable components are protected and setup is recorded before pressurisation. Project basis: [Fill: Project-specific test method and acceptance]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water pressure test setup record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Project-specific test method and acceptance; Project specification and adopted standards; Licensed roles, inspections and release authority; Project records and handover requirements
- Blank record fields
- Test section; Procedure / revision; Gauge ID / calibration reference; Isolation and protection check
WTR-06 · Pressure test and defect closeout
- Work stage
- Pressure test and defect closeout
- Inspection / test
- Record the specified water-service test result and verify repair/retest evidence where required.
- Method
- Perform the approved test for the defined section; record actual medium, set conditions, start/end readings, times, observed leakage and test instrument; repair and repeat per approved procedure.
- Acceptance condition
- Actual results satisfy only the project-approved acceptance criteria and authority pathway; failed tests remain open until documented repair and accepted retest. Do not apply WA example values unless expressly adopted. Project basis: [Fill: Project-specific test method and acceptance]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service test and retest certificate
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Project-specific test method and acceptance; Jurisdiction and authority basis; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Test section; Actual readings / result; Actual start/end time; Defect / repair / retest ref.
WTR-07 · Flushing and disinfection, where required
- Work stage
- Flushing and disinfection, where required
- Inspection / test
- Determine and complete project-required flushing, disinfection and water-quality checks before service use.
- Method
- Confirm system type, scope and written procedure; flush/disinfect only where required and by approved method; record water quality samples/results, disposal and clearance where specified.
- Acceptance condition
- Applicable flushing/disinfection and water-quality evidence meets authority and project requirements; where not required, the basis is recorded. No universal disinfection trigger, dose or residual is supplied. Project basis: [Fill: Flushing, disinfection and water quality requirements]; [Fill: Jurisdiction and authority basis].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water flushing, disinfection and sampling record
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Flushing, disinfection and water quality requirements; Jurisdiction and authority basis; Project specification and adopted standards; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- System / section; Approved procedure reference; Sample point / lab result; Clearance / disposition
WTR-08 · Operational checks and service identification
- Work stage
- Operational checks and service identification
- Inspection / test
- Check completed valves, outlets, controls, labels and access against approved schedules and operation requirements.
- Method
- Operate each scheduled item; verify intended service identification, access/isolation, flow direction and documented function; record exceptions and closeout actions.
- Acceptance condition
- Installed items match approved schedule and perform as specified; access and service identification are maintained and defects are closed. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Project specification and adopted standards].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water service functional check and asset register
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Approved service drawings and revisions; Project specification and adopted standards; Project records and handover requirements; Licensed roles, inspections and release authority
- Blank record fields
- Valve / outlet / control ID; Location / service; Observed function; Defect / closeout reference
WTR-09 · Regulatory inspection and handover
- Work stage
- Regulatory inspection and handover
- Inspection / test
- Confirm required authority notifications, inspection outcomes and service records are complete for handover.
- Method
- Reconcile regulator/utility approvals, certificates, approved deviations, test/flush results, marked-up drawings and operation information against the project dossier index.
- Acceptance condition
- All required project and jurisdiction records are indexed; outstanding authority conditions, defects or exclusions are visible and not represented as accepted. Project basis: [Fill: Licensed roles, inspections and release authority]; [Fill: Project records and handover requirements].
- Timing / coverage
- Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
- Responsible role
- Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
- Control / release arrangement
- Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
- Record
- Water services commissioning and handover dossier index
- Project document reference
- Enter the governing document, revision and clause, drawing detail or register entry for this check.
- Project inputs to resolve
- Jurisdiction and authority basis; Licensed roles, inspections and release authority; Project records and handover requirements; Service boundaries and connection interfaces
- Blank record fields
- Record / certificate; Document number / revision; Status / authority; Open condition / owner
Source notes
- Australian Building Codes Board, NCC 2022 Volume Three — Plumbing Code of Australia
Official national framework and source locator. State adoption, variations, application and project compliance pathway must be confirmed; NCC edition is not assumed to be the contract edition.
Accessed 2026-10-07; Volume Three index: Section B Water services, Section C Sanitary plumbing and drainage systems, state/territory schedules and Schedule 2 referenced documents.
- Australian Building Codes Board, NCC 2022 Volume Three — Schedule 2 Referenced documents
Confirms NCC 2022 referenced-document editions and provision cross-references only. Verify the edition actually adopted by the project jurisdiction and contract; full standards text was not used.
Accessed 2026-10-07; entries AS/NZS 3500 Part 1:2021 (B1D3 etc.), Part 2:2021 (C1/C2 provisions) and Part 3:2021 (F1D3, H2D2/H2D6 and 7.4.3).
- Australian Building Codes Board, NCC 2022 Volume Three — Section B Water services
Defines service group coverage and compliance topic routing; it does not set project-specific test methods, design values, hold points or blanket disinfection requirements.
Accessed 2026-10-07; index entries Part B1 Cold water services, B2 Heated water services, B3 Non-drinking water services, B5 Cross-connection control, B6 Rainwater services and B7 Rainwater storage.
- WA Plumbers Licensing Board, Pipe sizing and commissioning
WA-specific technical example only. Its stated pressure/time and disinfection triggers are intentionally not reproduced as generic criteria; use only if confirmed applicable by jurisdiction, contract and service design.
Version 4, May 2023: page 4 Testing and commissioning of water services flowchart; page 5 WA scope and adopted-code notes. Checked 7 October 2026.
- ABCB WaterMark, What requires WaterMark?
Topic support for checking certification applicability and product identity; not every plumbing product requires WaterMark. No individual product or installation is certified by this template.
Transcript: schedules of products/excluded products and matching certificate/product identity. Checked 7 October 2026.
Connect the plan to field evidence
- Construction Nonconformance Report and Corrective Action Record
- Construction ITP Inspection and Quality Records Register
- Water services pressure test record
- Sanitary drainage pre-cover inspection
- Stormwater drainage inspection
How to write a plumbing and drainage ITP · Compare the broader plumbing & drainage scope
Need your water services installation ITP prepared for this project?
Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.
USD 99 per defined work package · First delivery within 24 hours after payment and receipt of complete required project files. Weekends and public holidays included. Need it sooner? Contact us before ordering to confirm availability.
2 free revision rounds within 14 days of first delivery. Our errors are corrected free without using a round. Delivery, revisions and refunds.