SWD · Scoped work package

Stormwater Drainage Installation ITP Template

Site stormwater pipes, pits, levels, approved outlet interfaces, pre-cover checks and completion records.

What this plan covers

Original editable baseline for ordinary building stormwater pipework, pits, inlets and approved discharge connections. Covers approved hydraulic design boundaries, products, trench support, measured pipe profile, pit outlet levels, joints/separation, pre-cover records, specified functional checks and outlet handover. Excludes roof-gutter fabrication, public stormwater network construction, flood modelling/design, pumps/tanks and specialist civil stormwater treatment unless separately scoped. Hydraulic criteria, pit/outfall levels and discharge approvals must come from approved design, contract and local authority.

Define the package before tailoring it

Approved hydraulic design
Identify drawings/calculations, catchments, gradients, inverts, pits, outlets and approved discharge point.
Work and authority boundary
Identify building/site interfaces, utility connections, easements and excluded public-network works.
Jurisdiction and approvals
Confirm state/local authority requirements and project approval conditions.
Products and loading schedule
List approved pipe, pit, grate and cover selections with use/loading conditions.
Inspection and records
Confirm pre-cover survey, functional checks, release roles, as-builts and approvals.

Inspection sequence and project requirements

This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

STR-01 · Approved stormwater design and discharge boundary

Work stage
Approved stormwater design and discharge boundary
Inspection / test
Confirm catchment/system boundary, design source, point of discharge and approvals before setting out.
Method
Review drainage plans, hydraulic calculations/schedules, easements, authority conditions and outfall/connection details; identify roof, surface and subsurface elements and interfaces with civil works.
Acceptance condition
Installation scope maps to the approved design and authorized discharge point; capacity, catchment assumptions and outlet conditions are not devised by this template. Project basis: [Fill: Approved stormwater design and discharge basis]; [Fill: Jurisdiction and authority basis].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater scope, design and approval register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved stormwater design and discharge basis; Jurisdiction and authority basis; Approved service drawings and revisions; Service boundaries and connection interfaces; Licensed roles, inspections and release authority
Blank record fields
Catchment / system ID; Design drawing / revision; Approved point of discharge; Authority / condition reference

STR-02 · Incoming stormwater products and pit components

Work stage
Incoming stormwater products and pit components
Inspection / test
Check pipe, fittings, pits, grates and access components against the approved schedule.
Method
Match material/class, dimensions, connection type, grate/cover and required evidence to approved submittals; inspect product condition and hold substitutions for design approval.
Acceptance condition
Products and components suit the approved schedule and location/loading/design conditions; no generic class or product selection is supplied. Project basis: [Fill: Approved product and material schedule]; [Fill: Project specification and adopted standards].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater products and pit delivery register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved product and material schedule; Project specification and adopted standards; Approved stormwater design and discharge basis; Project records and handover requirements; Licensed roles, inspections and release authority
Blank record fields
Pipe / pit / component; Location / catchment; Submittal / approval ref.; Condition / disposition

STR-03 · Trench, formation and pipe support

Work stage
Trench, formation and pipe support
Inspection / test
Inspect formation, bedding and support before placing stormwater pipework.
Method
Compare excavation and support conditions with approved civil/drainage details; document groundwater, unsuitable formation, clashes or changed cover for designer disposition.
Acceptance condition
Prepared support and route reflect approved project details and site constraints; unresolved ground and loading issues are dispositioned before installation. Project basis: [Fill: Approved service drawings and revisions]; [Fill: Project specification and adopted standards].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater trench and support inspection
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved service drawings and revisions; Project specification and adopted standards; Design levels, gradients and hydraulic criteria; Concealment, cover and access requirements; Licensed roles, inspections and release authority
Blank record fields
Section / chainage; Formation / groundwater; Approved bedding / support detail; Instruction / disposition ref.

STR-04 · Pipe line, invert levels and hydraulic profile

Work stage
Pipe line, invert levels and hydraulic profile
Inspection / test
Verify actual pipe route, inverts and gradients against the approved hydraulic layout.
Method
Survey each defined section and compare measured locations, invert levels, gradients, cover and transitions to the approved drawings and stated project tolerance.
Acceptance condition
Measured profile matches the approved design values and tolerance references; do not substitute generic fall, cover or hydraulic capacity assumptions. Project basis: [Fill: Design levels, gradients and hydraulic criteria]; [Fill: Approved stormwater design and discharge basis].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater as-laid level and profile survey
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Design levels, gradients and hydraulic criteria; Approved stormwater design and discharge basis; Approved service drawings and revisions; Concealment, cover and access requirements; Licensed roles, inspections and release authority
Blank record fields
Section / chainage; Measured upstream/downstream inverts; Measured gradient / method; Drawing / design tolerance

STR-05 · Pits, grates and inlet capture interfaces

Work stage
Pits, grates and inlet capture interfaces
Inspection / test
Check pit location, orientation, inlet/outlet configuration and grate/cover arrangement against approved detail.
Method
Inspect pit dimensions/benching/outlet arrangement and connected inlets; compare cover/grate level and access with detail and finished surface/traffic/loading schedule.
Acceptance condition
Pit and inlet arrangement matches approved detail; outlet invert and surface level are recorded against project values, with access and loading requirements resolved by the design. Project basis: [Fill: Approved stormwater design and discharge basis]; [Fill: Design levels, gradients and hydraulic criteria]; [Fill: Project specification and adopted standards].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater pit and inlet inspection sheet
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved stormwater design and discharge basis; Design levels, gradients and hydraulic criteria; Project specification and adopted standards; Approved service drawings and revisions; Licensed roles, inspections and release authority
Blank record fields
Pit ID / location; Inlet configuration; Outlet invert / connection; Grate / cover level and type

STR-06 · Joints, connections and cross-system separation

Work stage
Joints, connections and cross-system separation
Inspection / test
Inspect joints and connections including roof leaders, surface inlets, pits and approved downstream tie-ins.
Method
Check joint preparation and assembly to product instructions; confirm connection direction, seals, cleanout/access and separation from sanitary drainage; record defects before cover.
Acceptance condition
Connections are continuous to the approved layout and remain distinct from sanitary drainage; joint defects and interface clashes are resolved before concealment. Project basis: [Fill: Approved product and material schedule]; [Fill: Approved service drawings and revisions].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater joint and connection record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved product and material schedule; Approved service drawings and revisions; Service boundaries and connection interfaces; Concealment, cover and access requirements; Licensed roles, inspections and release authority
Blank record fields
Section / connection; Joint / product type; Connected system / destination; Defect / repair reference

STR-07 · Pre-cover survey and inspection readiness

Work stage
Pre-cover survey and inspection readiness
Inspection / test
Confirm buried sections, pits and outlet connections are inspectable and test/inspection-ready before backfill.
Method
Reconcile installed line, survey points, test/flow check requirements, authority notice and open design deviations; verify photo/survey evidence is captured while visible.
Acceptance condition
Required inspection, survey and approvals are complete before concealment; unresolved levels, outlet approvals or defects remain open. Project control points are not created by this baseline. Project basis: [Fill: Concealment, cover and access requirements]; [Fill: Licensed roles, inspections and release authority].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater pre-cover survey and inspection record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Concealment, cover and access requirements; Licensed roles, inspections and release authority; Design levels, gradients and hydraulic criteria; Project records and handover requirements
Blank record fields
Section / location; Survey/photo record ref.; Inspection / notice ref.; Open item / release ref.

STR-08 · Specified flow, connection or functional check

Work stage
Specified flow, connection or functional check
Inspection / test
Complete only project-specified functional checks and verify discharge follows the approved path.
Method
Use the approved commissioning/check procedure; record source/volume or test condition where specified, observed inlet/pit/outfall behaviour, obstructions, leaks and corrective work.
Acceptance condition
Observed function and discharge path meet project-defined requirements; do not infer a design storm, flow rate, hydraulic capacity or acceptance threshold. Project basis: [Fill: Project-specific test method and acceptance]; [Fill: Approved stormwater design and discharge basis].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater functional check and defect log
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Project-specific test method and acceptance; Approved stormwater design and discharge basis; Licensed roles, inspections and release authority; Project records and handover requirements
Blank record fields
Catchment / test area; Approved procedure; Observed flow / outlet response; Defect / retest reference

STR-09 · Outlet protection, access and handover

Work stage
Outlet protection, access and handover
Inspection / test
Verify approved outlet connection, erosion/debris protection, maintenance access and closeout records.
Method
Inspect outfall and downstream tie-in against approval details; verify project-required protection and maintenance access; compile as-laid survey, test/check evidence and approvals.
Acceptance condition
Outlet is the approved destination and protection/access requirements are met; project and authority records are indexed with unresolved conditions disclosed. Project basis: [Fill: Approved stormwater design and discharge basis]; [Fill: Licensed roles, inspections and release authority]; [Fill: Project records and handover requirements].
Timing / coverage
Proposed: At the identified item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned licensed plumbing contractor performs and records; reviewer / regulator acts only within documented authority. Project role basis: [Fill: Licensed roles, inspections and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm contractual or regulatory Hold/Witness points, notice, evidence and release authority from the project; none is assigned here. Project basis: [Fill: Licensed roles, inspections and release authority]
Record
Stormwater outlet and handover dossier
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved stormwater design and discharge basis; Licensed roles, inspections and release authority; Project records and handover requirements; Jurisdiction and authority basis
Blank record fields
Outfall / authority reference; Protection detail / check; Maintenance access check; As-built / closeout record ref.

Source notes

Connect the plan to field evidence

How to write a plumbing and drainage ITP · Compare the broader plumbing & drainage scope

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Browser editor

Loading the editable stormwater drainage plan. Download a file above if the editor is unavailable.