Plumbing & drainage · Free field record

Building Stormwater Drainage Inspection Record

A blank field record for stormwater pits, levels, pipe connections, separation, designated outlet, conditional project tests, pre-cover checks and as-built evidence.

Excel provides separate project setup, field record and issue/handover sheets, plus a repeatable stormwater segment, pit and outlet log sheet, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Ordinary building surface/subsurface stormwater drainage within the project boundary, including identified lines, pits, inlets, connections and approved outlet interface.

Outside this record: Stormwater network design or sizing, universal levels/gradients/test requirements, public authority mains, major civil flood systems and on-site detention design; industrial/process, sanitary, gas or fire networks unless separately scoped and sourced.

Stormwater requirements and authority interfaces vary by jurisdiction and project. No default test is assumed: perform and record a test only where the approved project or authority documents require one. Capture actual surveyed levels with datum and the designated discharge destination.

Collect these project inputs first

Approved stormwater plans, pit schedules and outlet details
Define design nodes, levels, pits, flow route, destination and current revision.
Project survey/setout criteria and level datum
Allows actual levels to be recorded and compared on the correct datum and against stated tolerances.
Authority, consent and point-of-connection documents
Define approved network interface or on-site discharge arrangement where applicable.
Project test/inspection and pre-cover schedule
States whether functional testing, notice, witness or release is required; no generic requirement is assumed.
As-built and defect-closeout process
Defines required survey file, markup, photographs, repair records and handover evidence.

How to use the checklist

  1. Use the approved drainage drawing to identify line, pit, inlet, connection and terminal outlet. Keep design and actual surveyed data distinct.
  2. Record actual levels with unit and datum, linked to the survey/setout evidence and project acceptance source.
  3. Inspect pit/access and pipe interfaces while visible; record exact connection identity and check separation from sanitary drainage.
  4. Confirm and record the designated connection or approved disposal point from project/authority evidence.
  5. Record a test only where required. Link method and source; if none is specified, state the basis for N/A.
  6. Before cover or surface closure, link required inspection, photos, survey and as-built records and project-assigned disposition.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

Stormwater segment, pit and outlet log for repeat entries

Use one line per identified segment, pit, inspection or project-required test event. Record design and measured levels with their datum/source. A test is conditional on actual project/authority requirements; leave entries blank until observed.

Columns in the blank log
  • Date / stage
  • Line / pit / inlet ID
  • From–to / outlet
  • Drawing / revision
  • Design level / datum
  • Actual level / unit / survey ref
  • Connection / access observation
  • Test / defect / as-built evidence ref
  • Recorder / status

The files provide 8 blank entry rows. Continue on another blank copy as needed; the web page does not record site entries.

SW-01 · Stormwater network identity and design setout

Line, pit and inlet IDs, contributing area/reference where scheduled, drawing revision, flow direction, design levels and outlet destination.

How to check
Trace each installed line and pit to the current approved drainage plan, pit schedule and level details; record measured/as-installed values separately from design values.
What defines acceptance
Network elements and flow path are traceable to approved project drawings, with actual measurements compared only against project criteria and units.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Identify affected line/pit and resolve drawing, level or destination conflicts with the assigned project/design role.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems; Victoria Building and Plumbing Commission, DR 07 Bedding site stormwater drains.

Blank record fields
  • Line / pit / inlet ID
  • From–to node / outlet
  • Drawing / pit schedule revision
  • Design level / datum / source
  • Actual level / unit / survey ref
  • Result, inspector and date; issue and recheck reference

SW-BED · Exposed trench, bedding and pipe support

Record trench condition, installed bedding and pipe support before they are concealed, where below-ground work is included.

How to check
Compare exposed work with the approved trench, bedding and embedment detail and relevant product instructions. Identify unstable formation, voids, debris, pipe movement and civil-work interfaces for project disposition.
What defines acceptance
Observed trench support, bedding and embedment correspond to the approved project detail. Material, thickness, cover and compaction requirements come from the actual applicable sources; this record supplies no default value.
Project document to cite
Enter approved drawing/detail and revision, applicable civil or geotechnical specification, and product installation instruction.

If a discrepancy is found: Keep the affected location identifiable, document the discrepancy and obtain the project-assigned disposition and reinspection before covering.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems; Victoria Building and Plumbing Commission, DR 07 Bedding site stormwater drains.

Blank record fields
  • Drain run / inspection location
  • Drawing / bedding detail and revision
  • Formation condition / groundwater observation
  • Bedding material and evidence reference
  • Actual bedding / support observation or measurement and unit
  • Specified cover / surround criterion source
  • Civil interface / unresolved defect / reinspection reference
  • Result, inspector and date; issue and recheck reference

SW-02 · Pits, inlets, grates and access condition

Pit type/mark, installed position and orientation, inlet/grate condition, cover level reference, access for maintenance and visible workmanship.

How to check
Compare installed pit and access arrangement with approved pit detail/schedule; record photo and level/survey references where required.
What defines acceptance
Pits, inlets and maintenance access match project-approved details; no size, level tolerance or grate load class is assumed by this record.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Record exact pit/location and affected detail, then seek project disposition before concealment or paving over access.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems.

Blank record fields
  • Pit / inlet mark
  • Approved pit detail / revision
  • Grate / cover identity
  • Access and clearance observation
  • Photo / level survey ref
  • Result, inspector and date; issue and recheck reference

SW-03 · Pipe connections, transitions and separation

Pipe material/joint identity, pit entry/exit, connection seating, changes of direction/level, sealed interfaces and separation from sanitary drainage.

How to check
Inspect accessible interfaces and compare to approved connection details and service coordination drawings; trace suspected cross-connections to source and destination before disposition.
What defines acceptance
Connections and transitions follow approved project details; keep stormwater and sanitary systems separate; any proposed cross-system connection needs verified design and applicable authority approval.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Identify the actual connection and affected systems, prevent concealment where practicable, and seek written project/design direction for defects or cross-connections.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems.

Blank record fields
  • Pipe / joint system
  • Pit entry / exit / connection IDs
  • Transition / detail reference
  • Sanitary separation observation
  • Issue / photo / instruction ref
  • Result, inspector and date; issue and recheck reference

SW-04 · Designated point of connection or on-site outlet

Approved network connection, lawful/designated discharge point or approved on-site disposal arrangement, destination ID and any authority interface.

How to check
Trace installed discharge route to the approved project outlet and relevant consent/authority detail; record the actual terminal point, not an assumed discharge path.
What defines acceptance
The constructed route terminates at the project-designated point of connection or approved disposal system and required interface evidence is linked.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Keep outlet disposition open and obtain written direction/authority evidence when terminal point, permission or destination is unclear.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems.

Blank record fields
  • Outlet / point-of-connection ID
  • Approved outlet drawing / consent ref
  • Actual destination / receiving system
  • Authority interface record if applicable
  • Open issue / decision ref
  • Result, inspector and date; issue and recheck reference

SW-05 · Specified test or functional evidence, conditional

Whether a test/functional demonstration is required, its project source, defined extent, actual method and result; visible obstruction, defect, repair or retest if encountered.

How to check
Only where specified, follow the current approved project/authority method and retain actual test evidence. If no test is specified, record N/A with the controlling scope basis rather than inventing one.
What defines acceptance
Any required test is assessed against its stated project criteria and linked to actual segment/pit results; no universal stormwater test or acceptance value is imposed.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Document the missing criterion, defect or failed result and refer for project disposition; retain the original result with any retest.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems.

Blank record fields
  • Test required? / source
  • Test extent / method / revision
  • Actual observation / result and unit
  • Defect / blockage / repair ref
  • Retest / disposition record
  • Result, inspector and date; issue and recheck reference

SW-06 · Pre-cover, levels and as-built closeout

Required exposed inspection, surveyed actual inverts/cover levels where required, pit and connection coordinates, photos, as-built markups, outstanding defects and release evidence.

How to check
Compare actual survey and installed network to current approved requirements; link inspection notice and project release decision before trench fill or surface closure where required.
What defines acceptance
Project-required pre-cover inspection, level records and as-built evidence are complete and traceable; this form does not create a universal hold point or level tolerance.
Project document to cite
Current approved project drawings, specification, adopted service standard and inspection/test plan; record exact document, revision, clause/detail and affected segment.

If a discrepancy is found: Identify covered/uninspected extent and missing survey/as-built evidence; notify the assigned project role and leave status open.

Topic references: ABCB, NCC 2022 Volume Three — Plumbing Code of Australia; ABCB, NCC 2022 Volume Three Schedule 2 — Referenced documents; ABCB, NCC 2022 Volume Three — Victoria Part E4 Stormwater, Surface and Sub-surface Drainage Systems; Victoria Building and Plumbing Commission, DR 07 Bedding site stormwater drains.

Blank record fields
  • Pre-cover inspection / notice ref
  • Actual invert / cover levels and datum
  • Survey / setout file ref
  • As-built markup / photo refs
  • Release / outstanding disposition ref
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
Outlet destination or approval is unclearTrace the actual terminal line and obtain the project/authority record defining the permitted connection or disposal point.
Design and measured levels differ or use unclear datumsPreserve measured values and survey source; request written review against the project design and datum.
Stormwater/sanitary interface is uncertainRecord both line identities and actual connection evidence; request project direction before closing the issue.
No test requirement is foundRecord the documents checked and request confirmation if the project scope remains ambiguous; do not invent a test.
Pre-cover or as-built evidence is missingIdentify affected extent and obtain required survey, inspection, markup or disposition before handover.

Stormwater drainage handover

This record links observed installation and project evidence. It does not design drainage, establish lawful discharge, certify compliance or grant a contractual release.

Record inspection handover status options in the blank record:

Record the assigned roles: Installer / assigned trade role and date; Field inspector / role / date; Surveyor / as-built evidence role and reference; Authority / project release role and decision ref if applicable.

Fictional pit-to-outlet trace example — no result

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

Fictional line SW-000 from pit P-00 to outlet O-00, drawing DR-00 revision 0, datum DAT-00 and record REF-000. No real level, consent or test is represented.

Requirement to carry into the record
Trace the installed pit and line through actual surveyed references to the project-designated outlet; record a test only if required by project evidence.
Illustrative reference
Fictional IDs only; replace with approved project drawings and survey records.
What the site record should capture
Blank teaching example. Do not infer actual levels, discharge approval, test result or release from these placeholder identifiers.

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.