Scope and limitations
This resource is a general starting point for ordinary low-voltage building installation work. Specialist, high-voltage, fire, hazardous-area and commissioning scopes need their own project controls.
Confirm applicable design documents, standards, licensed roles and testing requirements for the actual project before use.
Inspection steps in this starting template
- Scope and regulatory basis — Confirm circuits, areas, system boundaries, exclusions and jurisdiction.
Review approved scope, electrical drawings, schedules and state regulatory requirements.
- Personnel and approvals — Check responsible electrical contractor/worker and required licences or authorisations are identified.
Verify applicable jurisdiction licence/authorisation evidence and any network/inspection approval required for scope.
- Design and equipment submittal — Review drawings, circuit schedules, equipment ratings, protective devices and approved substitutions.
Check against approved design, specification, equipment schedules and coordination/interface documents.
- Incoming materials — Check cables, accessories, enclosures and equipment identity, ratings, condition and traceability.
Visual inspection; compare markings and delivery documents with approved schedule/submittal.
- Containment and supports — Inspect conduits, trays, trunking, supports, segregation, routes and penetrations.
Visual check and measure route/support details against drawings, specification, manufacturer instructions and fire/acoustic details where applicable.
- Concealed wiring — Check cable type/size/route, protection, separation, identification and support before concealment.
Visual inspection against approved circuit schedules and project requirements; photograph concealed work.
- Cable installation and termination — Inspect pulling, bend/routing condition, gland/termination, conductor identification and workmanship.
Visual inspection against manufacturer instructions and approved equipment/circuit details.
- Switchboards and equipment mounting — Check location, mounting, enclosure, access, identification and installed components.
Visual/measured inspection against approved schedules, drawings and manufacturer data.
- Earthing and bonding — Check earthing/bonding conductors, connections, continuity provisions and labels per design.
Visual verification and tests by appropriately licensed/authorised person using approved safe procedure and applicable standard.
- Electrical installation verification — Check required visual inspection and specified dead tests for completed installation.
Only responsible licensed/authorised electrical worker performs tests using their approved safe method; record actual values and instrument.
- Protective devices and settings — Verify selected protective device identity, rating and approved settings.
Compare installed item and settings with approved coordination/protection schedule; licensed worker verifies.
- Functional and polarity checks — Verify specified switching, polarity/circuit connection, phase sequence or functional operation as applicable.
Authorised electrical worker follows applicable adopted procedure and records results; only perform tests in safe state.
- RCD/protection functional testing — Where included, verify specified device operation and record test particulars.
Authorised person uses applicable adopted test method and specified criteria; distinguish commissioning verification from routine user pushbutton checks.
- Defects and retesting — Track nonconformances, corrective work and repeat verification.
Record affected circuit/equipment, defect, authorised repair, retest results and revised status.
- Pre-energisation readiness — Check covers, barriers, labels, test completion, approvals and interface prerequisites before energisation.
Documented walkdown by responsible electrical contractor; verify statutory/network approvals and isolation/energisation plan.
- Energisation and commissioning — Record controlled energisation and specified system function/commissioning checks.
Responsible authorised person records date, circuits/systems energised, checks and exceptions; follow approved switching arrangements.
- Certificates and handover — Verify required certificates, test reports, as-builts, schedules, product records and approvals.
Review jurisdictional certificate requirements and contract handover index.
How to complete the project fields
- Identify the actual work package and remove steps outside its scope.
- For each retained check, cite the current drawing, specification, product instruction or approved project document.
- Enter project acceptance requirements exactly from those sources and agree inspection responsibilities and release points.
- Keep measurements, observations, dates and signatures blank until checks are performed on site.
Source notes
The starting structure is a general planning aid. The links below explain topic context; they do not set universal project acceptance values.
- NSW Government, Service and Installation Rules (June 2025 issue surfaced in search; current issue must be checked)
Topic support that electrical installation work is tested by a person authorised to undertake the work before commissioning, with results documented/notified under NSW rules. This is NSW-specific and issue currency/adoption must be checked.
- SafeWork NSW, Schedule of test results form
Inspected as a reporting-field example for verification records; does not independently define current acceptance limits or prove NSW-wide contract applicability.
- Energy Safe Victoria, Certificates of Electrical Safety for consumers (reviewed September 2026)
Current Victoria regulator page inspected. Supports Victoria-specific testing/certificate boundaries only; it is not Australia-wide and supplies no electrical test acceptance thresholds.
- NSW Government, Service and Installation Rules current-edition page
Official page inspected for current issue identity; particular clause detail came from a search extract of the earlier June 2025 issue and has not been checked in the current PDF.
- Construction Quality Association, Guide: How to create an ITP
ITP structure and preparation method only; not technical electrical criteria.