SWB · Scoped work package

Switchboard Installation ITP Template

Board identity and receiving evidence, mounting, circuit interfaces, installation checks and links to licensed verification and connection decisions.

What this plan covers

Ordinary building low-voltage switchboard installation from approved design/submittal through verification and handover readiness. Covers only the identified project package and approved drawings. Excludes high voltage, hazardous areas, generation/storage/PV, fire alarm, security, communications/data, specialist controls and utility/network-owned works unless separately identified and supported by project-specific scope. No live-work guide is provided. Electrical work and tests belong to appropriately licensed/authorised personnel under applicable jurisdictional law; project values, legal Hold/Witness points and release authority are not supplied.

Original general planning baseline; Queensland regulator sources are topic examples only, not national law. The customer project must confirm local licensing, adopted requirements, inspection/certificate process, contract criteria, Hold/Witness points and connection authority. Enter actual test values only from approved project/jurisdiction sources. The template never authorises work on energised equipment or supply energisation.

Project-specific ITP drafting for this package

The paid plan can link receipt and identity, mounting, enclosure / entry treatment, circuit and protection-setting references, labels, licensed verification evidence and handover prerequisites to each board. It keeps verification, supply connection and energisation decisions with their authorised parties.

Useful files to provide

Example of an input still needed

For example: “The board schedule is present, but the approved protection study and network connection prerequisites are absent. Please provide the latest approved revisions and identify the authorised connection decision maker.”

A project-specific switchboard installation ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.

How the plan and blank records fit together

The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as Board ID / serial / supplier, Specified setting / unit / source locator, Actual connection decision / authorised party reference provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.

Define the package before tailoring it

Included work and boundaries
Identify included electrical systems, areas/circuits, exclusions and interfaces.
Jurisdiction and regulator
Identify current state/territory rules, licensing scope, adopted requirements and notification/certificate process.
Approved drawings and design documents
Identify revisions of layouts, single-lines, schedules, details and approved changes.
Verification and test criteria
Identify project method, acceptance, coverage and actual licensed tester/record from controlled sources.
Supply, builder and network interfaces
Identify upstream/downstream limits, alternate supplies, isolation control and separate network connection/energisation approvals.
Performing, review and release roles
Identify licensed contractor/workers and distinguish project review, regulator inspection, contractual H/W and network approval.

Inspection sequence and project requirements

This starting plan contains 8 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

SWB-01 · Board design, rating and interface release

Work stage
Board design, rating and interface release
Inspection / test
Confirm board scope, location, single-line diagram, supply boundary and approved technical submittals.
Method
Review approved board schedule, drawings, supply/network interface, fault-level/design inputs and assigned designer decisions; do not calculate or select ratings in this baseline.
Acceptance condition
Board identity, design basis, project interfaces and required approvals are traceable to current controlled documents before procurement or installation. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Network connection / energisation interface].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Switchboard design and interface register
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover; Network connection / energisation interface. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover; Network connection / energisation interface
Blank record fields
Board ID / supply boundary; Single-line / equipment schedule revision; Design rating / setting approval reference; Manufacturer / assembly evidence reference; Supply / metering interface owner; Unresolved design decision

SWB-02 · Receipt, identity and condition

Work stage
Receipt, identity and condition
Inspection / test
Inspect delivered switchboard and components against approved equipment schedule and supplier documents.
Method
Match board ID, assembly configuration, device schedule and certificates to approved submittal; inspect transport condition and record discrepancies for disposition.
Acceptance condition
Delivered assembly and evidence match approved schedule; damage or substitutions are accepted by assigned authority before installation. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Receipt, identity and condition inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover
Blank record fields
Board ID / serial / supplier; Assembly / device schedule revision; Approved submittal / supplier evidence; Transport condition / photo reference; Discrepancy / authorised disposition

SWB-03 · Room, plinth and mounting readiness

Work stage
Room, plinth and mounting readiness
Inspection / test
Inspect switchboard location, mounting surface, access and service entries before positioning.
Method
Compare room/location, support/plinth, access and entry points with approved drawings and coordination requirements; record unresolved builder/service interfaces.
Acceptance condition
Installation location and support/interface arrangements satisfy approved project documents and manufacturer requirements; no generic clearance values are supplied. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Room, plinth and mounting readiness inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover
Blank record fields
Board / room / location; Plinth / mounting detail revision; Access / entry criteria source; Actual observed or measured condition / unit; Builder interface / outstanding item

SWB-04 · Placement, enclosure and cable entries

Work stage
Placement, enclosure and cable entries
Inspection / test
Inspect installed board alignment, anchorage, enclosure integrity, entry treatment and identification before termination.
Method
Use approved installation instructions and drawings; inspect visible condition, board identity, entries, covers and labels; record deviations before energisation planning.
Acceptance condition
Assembly is installed to approved instructions/documents, remains intact and identifiable, and deviations are dispositioned. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Network connection / energisation interface].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Placement, enclosure and cable entries inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover; Network connection / energisation interface. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Certificates, test records and handover; Network connection / energisation interface
Blank record fields
Board ID / installed location; Mounting / anchorage detail; Enclosure / entry treatment evidence; Labels / covers / visible condition; Deviation / correction / recheck reference

SWB-05 · Incoming/outgoing connections and earthing

Work stage
Incoming/outgoing connections and earthing
Inspection / test
Check documented completion of identified incoming/outgoing terminations, protective conductors and bonding interfaces.
Method
Assigned electrical worker verifies against approved single-line, schedules, connection details and supplier instructions; record circuit/device identity and required torque/tool evidence only if specified.
Acceptance condition
Connections and earthing/bonding are complete to controlling sources; no torque, conductor size or setting is inferred by this template. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Network connection / energisation interface].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Incoming/outgoing connections and earthing inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Isolation and alternate supply arrangements; Certificates, test records and handover; Network connection / energisation interface. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Isolation and alternate supply arrangements; Certificates, test records and handover; Network connection / energisation interface
Blank record fields
Board / terminal / circuit ID; Cable / conductor identification; Connection / bonding detail revision; Supplier torque / tool evidence if required; Observed completion / defect; Separate verification evidence reference

SWB-06 · Protection devices and settings

Work stage
Protection devices and settings
Inspection / test
Verify protective device identity, labels and settings documentation against approved design/schedules before functional verification.
Method
Compare installed device references and recorded settings to approved coordination/design documents; any change is referred to responsible designer and recorded.
Acceptance condition
Installed devices and settings evidence match approved design documents; no protective setting or performance threshold is supplied. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Project verification and test criteria].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Protection devices and settings inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Certificates, test records and handover. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Certificates, test records and handover
Blank record fields
Board / device / circuit identity; Approved protection study / schedule revision; Specified setting / unit / source locator; Actual recorded setting / unit / evidence; Label / device match; Design change / authorised decision reference

SWB-07 · Verification, functional checks and test evidence

Work stage
Verification, functional checks and test evidence
Inspection / test
Review required switchboard tests and functional/sequence evidence for identified board and circuits.
Method
Assigned licensed electrical worker performs required verification under applicable sources; record scope, method, device IDs, instruments and actual results. This is not an instruction for live testing.
Acceptance condition
Required examination and test evidence meets jurisdictional and project acceptance sources; defects, exclusions and retests are traceable. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Project verification and test criteria].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Verification, functional checks and test evidence inspection record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Isolation and alternate supply arrangements; Certificates, test records and handover. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Isolation and alternate supply arrangements; Certificates, test records and handover
Blank record fields
Board / circuit / function; Verification scope and exclusions; Approved method / criterion / source; Instrument / original report reference; Actual result / unit; Failure / correction / retest link; Licensed verification role / evidence

SWB-08 · Pre-energisation readiness and network interface

Work stage
Pre-energisation readiness and network interface
Inspection / test
Confirm installation test/certificate package and outstanding defects are ready for the distinct energisation and supply-connection process.
Method
Review test record, certificate, approved as-builts, outstanding-work register, isolation/source plan and network operator/retailer prerequisites; identify who controls each release.
Acceptance condition
Contractor completion and required certificates are documented; contractual acceptance, statutory inspection and network/supply connection approvals are separately obtained from their authorised parties. This check does not authorise energisation. Project source: [Fill: Approved electrical drawings and revisions]; [Fill: Project specification and adopted standards]; [Fill: Jurisdiction and regulator basis]. Supporting controlled inputs: [Fill: Approved equipment and product evidence]; [Fill: Project verification and test criteria]; [Fill: Network connection / energisation interface].
Timing / coverage
Proposed: Check the identified circuit, board or work lot before concealment or the next activity removes access; project coverage and timing must be confirmed.
Responsible role
Proposed: Assigned appropriately licensed electrical contractor/worker performs and records electrical work and tests within their authority. Other review roles act only within documented jurisdictional or contractual authority. Project role basis: [Fill: Licensed roles, reviews and release authority]
Control / release arrangement
Proposed: Contractor check only. Confirm any statutory inspection, contractual Hold/Witness point, notice and release authority from jurisdiction and contract; none is assigned by this template. Project basis: [Fill: Licensed roles, reviews and release authority]; [Fill: Jurisdiction and regulator basis]
Record
Switchboard pre-energisation readiness and connection interface record
Project document reference
Enter the controlling document number, revision and exact clause, drawing detail, circuit schedule entry or instruction for this step. Resolve: Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Isolation and alternate supply arrangements; Certificates, test records and handover; Network connection / energisation interface. Topic-source links do not establish project adoption.
Project inputs to resolve
Jurisdiction and regulator basis; Approved electrical drawings and revisions; Project specification and adopted standards; Electrical work scope and boundaries; Approved equipment and product evidence; Licensed roles, reviews and release authority; Project verification and test criteria; Isolation and alternate supply arrangements; Certificates, test records and handover; Network connection / energisation interface
Blank record fields
Board / installation boundary; Verification report / unresolved defects; Jurisdiction certificate / issuer; Required independent inspection evidence; Contractual review / disposition reference; Network / metering / connection prerequisite; Source / isolation plan reference; Actual connection decision / authorised party reference

Source notes

Connect the plan to field evidence

How to write an ITP from project documents · Compare the broader electrical installation scope

Need your switchboard installation ITP prepared for this project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.

Browser editor

Loading the editable switchboard installation plan. Download a file above if the editor is unavailable.