EAR · Free editable resource

Earthworks inspection and test plan template

Excavation, founding, fill placement, compaction testing, trench backfill and final survey.

Scope and limitations

Earthworks may include clearing, excavation, founding inspection, fill placement, compaction testing, trench backfill and survey records.

Confirm material, lot definition, test method, frequency and acceptance criteria against the project specification and geotechnical requirements.

Inspection steps in this starting template

  • Planning and geotechnical basis — Confirm earthworks zones, cut/fill limits, geotechnical design, material classes, lot/testing rules and service constraints.

    Review current drawings, geotechnical report, specification, survey control, services information and approved work method.

  • Survey control and set-out — Verify survey control, limits, formation levels and service/set-out references before disturbance.

    Check control marks and survey set-out against approved drawings and survey plan.

  • Service clearance and permits — Confirm service searches, locating, permits and protection/diversion arrangements for the planned excavation.

    Review current service plans and clearance permits; record field locating/marking and required authority releases.

  • Clearing and topsoil stripping — Check clearing boundaries, topsoil/vegetation stripping, salvage and stockpile locations.

    Observe limits and compare stripped material handling with environmental and earthworks requirements.

  • Unsuitable material and groundwater — Identify soft, wet, contaminated or otherwise unsuitable material and unexpected groundwater during excavation.

    Visual inspection and geotechnical review where required; record extent, photographs, removal and replacement instructions.

  • Excavation dimensions and formation — Check excavation limits, lines, levels, stability and formation against drawings/geotechnical requirements.

    Measure/survey formation and inspect condition; involve geotechnical engineer where specified.

  • Fill source and material approval — Verify source, classification, sampling and approval for each proposed fill material.

    Review source approval and lab classification/test certificates; reconcile delivered material with approved source/material ID.

  • Subgrade preparation and proof condition — Check exposed subgrade is trimmed, drained and free from unacceptable disturbance before placing fill or pavement layers.

    Visual walkover and specified proof roll or geotechnical inspection; record soft spots and remediation.

  • Fill placement layer controls — Check placed material type, placement area, loose layer thickness and segregation before compaction.

    Observe placement; measure layer thickness and compare material and equipment/work method with approved trial or specification.

  • Moisture conditioning and compaction — Verify moisture conditioning and compaction method are appropriate to approved material and project requirement.

    Observe water addition/aeration and compaction passes/equipment; record method where required by project.

  • In-situ density and material testing — Arrange specified field/lab testing and link each result to the correct lot, layer, location and material.

    Use project-nominated methods and qualified/lab personnel; map test locations and compare results with exact project limits.

  • Nonconformance, rework and retest — Track failed tests, unsuitable areas and corrective work through acceptable retest or written disposition.

    Review test/NCR records, identify affected lot and layer, verify rework boundaries and retest.

  • Trench backfill and reinstatement — Check bedding, haunch/side support, pipe protection and backfill material/layers for trench works.

    Inspect before concealment and record material, layer placement, specified compaction tests and surface reinstatement.

  • Drainage, erosion and water management — Check temporary drainage, dewatering, erosion/sediment controls and protection of completed formation/fill.

    Inspect controls before and during work and after rainfall/change events against approved environmental/site plans.

  • Final levels, geometry and closeout — Survey completed surfaces, batters, slopes, formation and interfaces; compile material, lot and test records.

    Survey/measure against final design and compare register for all lots, nonconformances and geotechnical releases.

How to complete the project fields

  1. Identify the actual work package and remove steps outside its scope.
  2. For each retained check, cite the current drawing, specification, product instruction or approved project document.
  3. Enter project acceptance requirements exactly from those sources and agree inspection responsibilities and release points.
  4. Keep measurements, observations, dates and signatures blank until checks are performed on site.

Source notes

The starting structure is a general planning aid. The links below explain topic context; they do not set universal project acceptance values.

Continue with the related work

Choose the next resource for your task.

Prepare this plan

Keep the work package, inspection sequence and record under the same project references.

Define criteria and control points

Resolve the project requirement, notice and release arrangements before site checks.

Capture and close out the evidence

These blank records support the relevant work stages; complete actual results on site.

Browse guides by task · Browse field and quality records

Browser editor

Loading the editable Earthworks & excavation plan… If the editor does not load, download a file above.

  • Planning and geotechnical basis — Confirm earthworks zones, cut/fill limits, geotechnical design, material classes, lot/testing rules and service constraints.

    Review current drawings, geotechnical report, specification, survey control, services information and approved work method.

  • Survey control and set-out — Verify survey control, limits, formation levels and service/set-out references before disturbance.

    Check control marks and survey set-out against approved drawings and survey plan.

  • Service clearance and permits — Confirm service searches, locating, permits and protection/diversion arrangements for the planned excavation.

    Review current service plans and clearance permits; record field locating/marking and required authority releases.

  • Clearing and topsoil stripping — Check clearing boundaries, topsoil/vegetation stripping, salvage and stockpile locations.

    Observe limits and compare stripped material handling with environmental and earthworks requirements.

  • Unsuitable material and groundwater — Identify soft, wet, contaminated or otherwise unsuitable material and unexpected groundwater during excavation.

    Visual inspection and geotechnical review where required; record extent, photographs, removal and replacement instructions.

  • Excavation dimensions and formation — Check excavation limits, lines, levels, stability and formation against drawings/geotechnical requirements.

    Measure/survey formation and inspect condition; involve geotechnical engineer where specified.

  • Fill source and material approval — Verify source, classification, sampling and approval for each proposed fill material.

    Review source approval and lab classification/test certificates; reconcile delivered material with approved source/material ID.

  • Subgrade preparation and proof condition — Check exposed subgrade is trimmed, drained and free from unacceptable disturbance before placing fill or pavement layers.

    Visual walkover and specified proof roll or geotechnical inspection; record soft spots and remediation.

  • Fill placement layer controls — Check placed material type, placement area, loose layer thickness and segregation before compaction.

    Observe placement; measure layer thickness and compare material and equipment/work method with approved trial or specification.

  • Moisture conditioning and compaction — Verify moisture conditioning and compaction method are appropriate to approved material and project requirement.

    Observe water addition/aeration and compaction passes/equipment; record method where required by project.

  • In-situ density and material testing — Arrange specified field/lab testing and link each result to the correct lot, layer, location and material.

    Use project-nominated methods and qualified/lab personnel; map test locations and compare results with exact project limits.

  • Nonconformance, rework and retest — Track failed tests, unsuitable areas and corrective work through acceptable retest or written disposition.

    Review test/NCR records, identify affected lot and layer, verify rework boundaries and retest.

  • Trench backfill and reinstatement — Check bedding, haunch/side support, pipe protection and backfill material/layers for trench works.

    Inspect before concealment and record material, layer placement, specified compaction tests and surface reinstatement.

  • Drainage, erosion and water management — Check temporary drainage, dewatering, erosion/sediment controls and protection of completed formation/fill.

    Inspect controls before and during work and after rainfall/change events against approved environmental/site plans.

  • Final levels, geometry and closeout — Survey completed surfaces, batters, slopes, formation and interfaces; compile material, lot and test records.

    Survey/measure against final design and compare register for all lots, nonconformances and geotechnical releases.