What this plan covers
Reusable baseline for clearing/stripping interfaces, bulk excavation, site-won cut/fill movements, formation preparation and bulk closeout. Selected engineered fill placement/conditioning/compaction/testing is covered by the separate Selected Engineered Fill package. Excludes structural excavations, deep foundations, contaminated-land remediation, blasting, ground improvement, trench utility backfill and pavement-specific acceptance unless expressly included.
Free editable proposed work-package baseline. Source material is topic guidance, not an adopted project standard or acceptance requirement. Complete against contract, drawings, specifications, geotechnical documents, approved procedures, adopted standards and assigned roles. All actual measurements, tests, dates, dispositions and signatures remain blank until work is performed.
Project-specific ITP drafting for this package
A project ITP can distinguish stripping, bulk excavation, material identification and movement, formation preparation, survey checks and handover by zone. Selected engineered fill compaction stays in its separate package unless the customer expressly includes it; acceptance and testing requirements come from the job documents.
Useful files to provide
- Approved cut / fill drawings, boundaries, datum and survey control
- Geotechnical design basis and material reuse / disposal requirements
- Earthworks specification defining formation acceptance and any testing lots
- Staging, environmental / service constraints and assigned release roles
Example of an input still needed
For example: “The earthworks limits are shown, but there is no geotechnical disposition for unexpected founding material or approved reuse category. Please send the relevant report and decision path.”
A project-specific bulk earthworks ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.
How the plan and blank records fit together
The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as Work zone / chainage, Material description / source, As-built survey file / revision provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.
Define the package before tailoring it
- Work zones and boundaries
- Identify drawing references, start/end locations, interfaces and exclusions.
- Design and ground basis
- Identify approved drawings, geotechnical documents, controlled specifications and disposition roles.
- Material source and intended use
- Identify material designation, source, permitted use and required project approval evidence.
- Inspection, lotting and testing basis
- Copy the actual project method, acceptance source, lot basis, rate, location and reporting requirement.
- Roles and external control
- Identify performer/reviewer roles and actual contractual notice, H/W and release provisions.
- Survey / closeout evidence
- Identify datum, drawing criteria, survey responsibility and handover records.
Inspection sequence and project requirements
This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.
BEW-01 · Scope, design basis and work-front release
- Work stage
- Scope, design basis and work-front release
- Inspection / test
- Confirm the defined bulk cut/fill limits, interfaces, material destinations, geotechnical basis and document revisions before disturbing ground.
- Method
- Review contract scope, drawing register, geotechnical report, earthworks method, service/permit information and material-use plan; record unresolved conflicts for assigned decision.
- Acceptance condition
- Work limits and governing inputs are identifiable by revision; every material stream has a nominated destination/use or a recorded hold for project disposition. [Fill: Approved civil / services drawings and revisions] [Fill: Geotechnical design basis and disposition roles] [Fill: Material source, classification and use schedule] [Fill: Project earthworks specification and adopted standards]
- Timing / coverage
- Before mobilisation and when controlled scope or design documents change.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Bulk earthworks readiness register
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Approved civil / services drawings and revisions; Project earthworks specification and adopted standards; Geotechnical design basis and disposition roles; Material source, classification and use schedule; Performing, reviewing and contractual release roles; Project records and handover requirements. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Approved civil / services drawings and revisions; Project earthworks specification and adopted standards; Geotechnical design basis and disposition roles; Material source, classification and use schedule; Performing, reviewing and contractual release roles; Project records and handover requirements
- Blank record fields
- Work zone / chainage; Drawing / spec / report revisions; Open conflict / decision reference
BEW-02 · Survey control and bulk set-out
- Work stage
- Survey control and bulk set-out
- Inspection / test
- Check control marks and set-out for clearing, stripping, cut limits, fill extents and interfaces.
- Method
- Compare surveyor’s set-out record and visible marks with approved plans and project survey control; note datum and drawing items.
- Acceptance condition
- Set-out is traceable to approved coordinates/levels and current control; discrepancies or disturbed control are resolved before affected work. [Fill: Survey control, geometry and closeout requirements]
- Timing / coverage
- Before each new work zone and after disturbance or design change.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Bulk set-out check
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Approved civil / services drawings and revisions; Survey control, geometry and closeout requirements; Performing, reviewing and contractual release roles. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Approved civil / services drawings and revisions; Survey control, geometry and closeout requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Area / chainage; Control mark / datum; Design level / drawing locator; Set-out record reference
BEW-03 · Clearance, stripping and topsoil segregation
- Work stage
- Clearance, stripping and topsoil segregation
- Inspection / test
- Verify required clearances and confirm stripping limits and segregation of material intended for reuse.
- Method
- Review permits and service marks; observe clearing limits and compare stripped material handling with the project environmental and reuse plan.
- Acceptance condition
- Clearance is current for the work front; disturbance stays within approved limits; reusable topsoil and other materials are identified and kept separate as specified. [Fill: Service clearance and permit process] [Fill: Material source, classification and use schedule] [Fill: Project earthworks specification and adopted standards]
- Timing / coverage
- Before ground penetration; inspect each stripping area before bulk excavation or stockpiling.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Clearance and stripping record
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Service clearance and permit process; Approved civil / services drawings and revisions; Material source, classification and use schedule; Project earthworks specification and adopted standards; Project records and handover requirements. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Service clearance and permit process; Approved civil / services drawings and revisions; Material source, classification and use schedule; Project earthworks specification and adopted standards; Project records and handover requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Permit / service clearance ref.; Area / drawing item; Stripped material / destination; Stockpile ID / photo ref.
BEW-04 · Bulk excavation and cut to design formation
- Work stage
- Bulk excavation and cut to design formation
- Inspection / test
- Check cut limits, exposed conditions, water management and progressive excavation geometry.
- Method
- Observe excavation against drawings and approved method; record changed ground, unexpected services, water or instability for the assigned project disposition.
- Acceptance condition
- Excavation stays within the approved footprint and documented geometry; unexpected conditions and departures receive written disposition before covering or building on them. [Fill: Approved civil / services drawings and revisions] [Fill: Geotechnical design basis and disposition roles] [Fill: Survey control, geometry and closeout requirements]
- Timing / coverage
- As each excavation area or material condition is exposed, before concealment or dependent work.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Bulk excavation observation
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Approved civil / services drawings and revisions; Geotechnical design basis and disposition roles; Survey control, geometry and closeout requirements; Service clearance and permit process; Performing, reviewing and contractual release roles. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Approved civil / services drawings and revisions; Geotechnical design basis and disposition roles; Survey control, geometry and closeout requirements; Service clearance and permit process; Performing, reviewing and contractual release roles
- Blank record fields
- Area / chainage; Cut level / drawing reference; Observed material / water / anomaly; Instruction / disposition ref.
BEW-05 · Unsuitable or unexpected ground disposition
- Work stage
- Unsuitable or unexpected ground disposition
- Inspection / test
- Identify material or ground conditions that do not match the documented design/material basis and trace the decision before removal or reuse.
- Method
- Mark the affected location and volume/extent where directed; notify the assigned geotechnical/design role and record written classification, treatment or destination instruction.
- Acceptance condition
- Affected material is segregated pending written project disposition; removal, treatment or reuse follows that instruction and is traceable to location and quantity basis. [Fill: Geotechnical design basis and disposition roles] [Fill: Material source, classification and use schedule] [Fill: Project records and handover requirements]
- Timing / coverage
- Whenever changed or potentially unsuitable conditions are exposed and before the affected material is reused or concealed.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Changed-ground / material disposition register
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Geotechnical design basis and disposition roles; Material source, classification and use schedule; Performing, reviewing and contractual release roles; Project records and handover requirements. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Geotechnical design basis and disposition roles; Material source, classification and use schedule; Performing, reviewing and contractual release roles; Project records and handover requirements
- Blank record fields
- Location / limits; Observed condition; Written disposition ref.; Approved treatment / destination
BEW-06 · Cut/fill material movement and stockpile control
- Work stage
- Cut/fill material movement and stockpile control
- Inspection / test
- Trace excavated material to the approved reuse area, stockpile or disposal destination and keep distinct streams identifiable.
- Method
- Review load/shift records and observe stockpile or placement identification against the approved material-use plan and environmental controls.
- Acceptance condition
- Material identity and destination remain traceable; material is not transferred into a different use zone without project approval; stockpiles are managed to the project requirements. [Fill: Material source, classification and use schedule] [Fill: Project earthworks specification and adopted standards]
- Timing / coverage
- For each identified material stream, stockpile establishment and change of destination.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Earthworks material movement register
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Material source, classification and use schedule; Project earthworks specification and adopted standards; Project records and handover requirements. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Material source, classification and use schedule; Project earthworks specification and adopted standards; Project records and handover requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Material description / source; Quantity / load reference; Reuse area / stockpile / disposal ref.; Use approval / instruction ref.
BEW-07 · Cut/fill interface and transition preparation
- Work stage
- Cut/fill interface and transition preparation
- Inspection / test
- Inspect interfaces where excavation transitions to fill or where the project identifies a treatment detail.
- Method
- Compare the exposed interface and preparation record with the approved detail and geotechnical instruction; identify location and evidence before the next layer.
- Acceptance condition
- Interface treatment matches the specific drawing/detail or written disposition; unresolved soft spots, steps or changed conditions remain open until disposition. [Fill: Approved civil / services drawings and revisions] [Fill: Geotechnical design basis and disposition roles]
- Timing / coverage
- At each designed or instructed transition before it is covered by subsequent work.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Cut/fill interface record
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Approved civil / services drawings and revisions; Geotechnical design basis and disposition roles; Survey control, geometry and closeout requirements; Performing, reviewing and contractual release roles. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Approved civil / services drawings and revisions; Geotechnical design basis and disposition roles; Survey control, geometry and closeout requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Interface / drawing locator; Observed preparation; Disposition / treatment ref.; Photo / survey ref.
BEW-08 · Bulk formation trim, drainage and protection
- Work stage
- Bulk formation trim, drainage and protection
- Inspection / test
- Check completed bulk formation shape, surface condition, drainage and protection before handover to the next trade.
- Method
- Walk the defined area; compare visible geometry and surface/drainage arrangements with project drawings and inspect for damage or water accumulation.
- Acceptance condition
- Formation matches the nominated project detail and documented tolerances; damage or water effects are recorded and corrected by an approved disposition before handover. [Fill: Approved civil / services drawings and revisions] [Fill: Survey control, geometry and closeout requirements] [Fill: Project earthworks specification and adopted standards]
- Timing / coverage
- Each completed formation area at handover and after damage or remedial work.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Formation inspection and handover record
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Approved civil / services drawings and revisions; Survey control, geometry and closeout requirements; Project earthworks specification and adopted standards; Project records and handover requirements. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Approved civil / services drawings and revisions; Survey control, geometry and closeout requirements; Project earthworks specification and adopted standards; Project records and handover requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Area / chainage; Drawing / level criterion locator; Surface / drainage observation; Receiving trade / date reference
BEW-09 · As-built survey and bulk earthworks closeout
- Work stage
- As-built survey and bulk earthworks closeout
- Inspection / test
- Reconcile completed extents and levels with required as-built evidence, open dispositions and handover records.
- Method
- Review survey files, material movement/disposition records, field observations, approved rework evidence and outstanding items against the project closeout list.
- Acceptance condition
- Required records identify the completed zone and current revision; specified survey deliverables are submitted; open departures have a documented owner and disposition. [Fill: Survey control, geometry and closeout requirements] [Fill: Project records and handover requirements]
- Timing / coverage
- At completion of each bulk earthworks zone before closeout or dependent handover.
- Responsible role
- Proposed: assigned earthworks supervisor / quality role performs and records; project-assigned reviewer acts only within documented authority. Confirm project roles: [Fill: Performing, reviewing and contractual release roles].
- Control / release arrangement
- Proposed internal readiness check. Confirm any contractual Hold/Witness point, notice, evidence and release authority from project documents; none is assigned by this baseline.
- Record
- Bulk earthworks closeout index
- Project document reference
- Identify the exact project document, revision and clause/drawing item for: Survey control, geometry and closeout requirements; Project records and handover requirements; Performing, reviewing and contractual release roles. Include applicable annexures and written dispositions; record a precise missing-input prompt if the project source is unavailable. Topic sources do not establish project adoption.
- Project inputs to resolve
- Survey control, geometry and closeout requirements; Project records and handover requirements; Performing, reviewing and contractual release roles
- Blank record fields
- Zone / drawing reference; As-built survey file / revision; Open NCR / disposition ref.; Submission / handover ref.
Source notes
- Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025)
Inspected topic example for Queensland road and bridge earthworks only. Supports identification of process topics, documentary controls, materials, geometry, excavation, fill, compaction, backfill and the fact that lot/test rules are specified. Its technical values, tests, frequencies, lot sizes, control points and roles are not defaults; use only if the project contract adopts this edition and applicable annexures.
Inspected official PDF and local searchable extract industry-library/text/tmr-mrts04.txt. Topic locators: 1.1-1.2 scope (printed specification pp. 1-2); 5.2-5.6 procedures, testing/lotting (printed pp. 15-19); 6 geometry (printed pp. 19-20); 8 topsoil (printed pp. 22-24); 9 unsuitable material (printed pp. 25-26); 13 excavation (printed pp. 34-38); 14 Earth Fill (printed pp. 38-47); 15 Compaction (printed pp. 48-53); 19 Backfill (printed pp. 67-74).
- Hutchinson Builders, Safety & Quality Planning: 010 Groundworks ITP and Report (EXAMPLE)
Builder example marked EXAMPLE; used only to check broad staging and useful lot/report fields. Many acceptance/frequency/role cells are blank. It does not set universal criteria, regulatory steps or release authority. Original DOCX files are not redistributed.
Official downloads page lists 010 Groundworks ITP and 010 Groundworks Report; both DOCX files downloaded and text-extracted 2026-10-07 from the linked Toolbox files. ITP table rows 3-11 cover bulk set-out, fill source, excavation, fill operations, bottom/surface preparation, compaction/soil-strength records and final inspection; rows 12-25 cover detailed earthworks, trench/pit bottoms, bedding/blinding, backfill, regulatory records and closeout. Matching report table rows 2-4 capture lot/location/open-close/comments/signature; rows 8-32 carry process, specification, acceptance, pass/fail, CAR, initials and date.
- Construction Quality Australia, How to create an Inspection and Test Plan
Method structure only: sequence checkable activities and specify method, acceptance source, trigger/frequency, responsibility, control and records. Does not substantiate earthworks technical limits or project requirements.
Official industry guide, sections 1-4, previously inspected and summarized in skills/au-construction-itp/references/template-writing-guide.md.
Connect the plan to field evidence
- Construction Nonconformance Report and Corrective Action Record
- Construction ITP Inspection and Quality Records Register
- Subgrade and formation inspection
- Compaction test and retest traceability
- Trench bedding and backfill inspection
How to write an ITP from project documents · Compare the broader earthworks & excavation scope
Need your bulk earthworks ITP prepared for this project?
Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.
USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.