Earthworks & excavation · Free field record

Compaction Test and Lot Traceability Record

A lot- and layer-based register for linking field density reports to their represented earthworks area, source material and project criteria, with a separate failure/retest trail.

Excel provides separate project setup, field record and issue/handover sheets, plus a repeatable density test lot, layer and failure/retest register sheet, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need your ITP prepared for this project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.

Use this record for

identification of earthworks compaction test lots, layers and test points; exact report transcription; project-criterion reference; and failure, retest and disposition linkage.

Outside this record: selecting test methods or rates, setting compaction targets, performing/certifying laboratory work, recalculating results without the adopted method, and automatic acceptance of a lot.

Blank field record. Enter actual measurements only from the issued field/laboratory report and retain its units and revision. No default pass status is supplied. A report result is evidence for the assigned project reviewer; it is not itself a lot certification or automatic acceptance.

Collect these project inputs first

Approved earthworks specification, drawings and lot definition
Defines material zones, layer identity, lot boundaries and applicable project acceptance criteria.
Project sampling/testing plan and adopted test method
Supplies actual method edition, frequency, location selection and report requirements.
Material source approval and reference laboratory data
Links the field result to the material/source and reference value used under the adopted method.
Issued field density reports and attachments
Provides actual result, units, test location, method and report revision for faithful transcription.
Failed-test and nonconformance procedure
Names the affected work, required investigation/retest and decision authority.

How to use the checklist

  1. Identify the project-defined lot and layer before assigning each test result.
  2. Record the physical test location and represented extent; preserve coordinates, offsets, depth and datum as reported.
  3. Copy each actual result, unit, method, report ID and revision exactly from the issued report.
  4. Record the project criterion and comparison separately; leave decision Pending until the assigned reviewer records a supported outcome.
  5. For failures, preserve the original result and add linked corrective action, retest and disposition entries; do not replace the first result.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

Density test lot, layer and failure/retest register for repeat entries

One row per actual test event. Keep original failure rows unchanged and link separate corrective work, retest report and disposition. Transcribe values and units only from issued reports. Status stays Pending until reviewed against the project criterion by the assigned role.

Columns in the blank log
  • Test date / time
  • Lot / boundary
  • Layer / placement date
  • Material / source
  • Test point / depth
  • Method / edition
  • Actual result / unit
  • Report / revision
  • Status / reviewer
  • NCR / retest / disposition

The files provide 10 blank entry rows. Continue on another blank copy as needed; the web page does not record site entries.

CTR-01 · Lot and represented work definition

Project lot ID and boundaries, material zone, placement date and governing lot definition.

How to check
Map each report to a unique project-defined lot and retain its limits; do not infer lot size or merge separate zones.
What defines acceptance
The represented work and lot boundaries are traceable to the approved project definition and match the report assignment.
Project document to cite
Project earthworks specification, lot plan, ITP and approved lot definition.

If a discrepancy is found: Unclear or overlapping lot identity remains Pending until reconciled with site and project test registers.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Lot ID / boundary ref
  • Lot definition source
  • Project test plan / revision
  • Result, inspector and date; issue and recheck reference

CTR-02 · Layer, placement and material/source identity

Layer number, placement date, location, material description/class and source or stockpile reference.

How to check
Match field test sheet to placement diary, delivery/source records and layer plan; distinguish source approval from in-place test evidence.
What defines acceptance
Each result identifies the layer and material/source represented under project records; no source class or thickness is assumed here.
Project document to cite
Approved materials register, source approval, placement diary and project layer plan.

If a discrepancy is found: Keep unmatched layer or material/source evidence open; obtain the correct contemporaneous placement and source records.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Layer / placement date
  • Material source / class
  • Placement diary ref
  • Result, inspector and date; issue and recheck reference

CTR-03 · Test point and method traceability

Test point coordinates/grid/offset, layer depth if reported, test date/time, test method and edition, performer and equipment/report IDs.

How to check
Link field sheet and report to the exact test point; transcribe method/edition and reported location without changing units or assigning a nearby location by assumption.
What defines acceptance
The actual test is traceable to a point, date, method and report, and any project-required performer/equipment evidence is linked.
Project document to cite
Adopted project testing plan, method reference, original field sheet and issued report.

If a discrepancy is found: Query missing or conflicting test identity before comparing the result to a project criterion.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Test point / depth
  • Method / edition
  • Field sheet / report ref
  • Result, inspector and date; issue and recheck reference

CTR-04 · Issued result transcription and criterion reference

Actual reported value(s), units, method fields, report revision and separate project criterion source/clause.

How to check
Copy values verbatim from the issued report; record criterion and source separately and preserve amended reports alongside original.
What defines acceptance
Transcription matches the report. The project criterion is explicit and applicable to that lot/material/method; no universal percentage, test rate or limit is provided.
Project document to cite
Original report and revision, project specification and adopted test method/criterion.

If a discrepancy is found: Leave decision Pending if report or criterion cannot be matched; refer to assigned technical reviewer.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Report / revision
  • Actual result / unit
  • Project criterion / clause
  • Result, inspector and date; issue and recheck reference

CTR-05 · Failure, retest and disposition register

Original failing/anomalous result, affected area, NCR/action, corrective work, separate retest evidence and written decision.

How to check
Retain chronological linked entries; record new retest as a new event and cross-reference the initial result rather than overwriting it.
What defines acceptance
Each issue has an identifiable affected extent and evidence trail; only the project-assigned role records disposition/closure.
Project document to cite
Project NCR and retest procedure, original/retest reports and written disposition.

If a discrepancy is found: Keep affected lot status open until the specified retest/review and documented project disposition are available.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Original test ID
  • NCR / corrective action
  • Retest report / disposition
  • Result, inspector and date; issue and recheck reference

CTR-06 · Lot review status and evidence handover

Reviewer role, project comparison, outstanding tests/documents, linked reports and record transfer reference.

How to check
Reconcile the test register against all required project results for the lot and submit to the named reviewer; do not self-populate Pass.
What defines acceptance
Status reflects explicit evidence and assigned review. Blank or missing results are Pending; recording a report does not certify or accept the lot.
Project document to cite
Approved ITP, project lot acceptance process and assigned review/record handover requirements.

If a discrepancy is found: Do not mark the lot passed by default; identify missing evidence and obtain recorded project decision.

Topic references: Cavoren earthworks baseline; Queensland Department of Transport and Main Roads, MRTS04 General Earthworks (March 2025); Hutchies 010 Groundworks Report (public Word example).

Blank record fields
  • Reviewer role / date
  • Review outcome
  • Open item / handover ref
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
Test report is missing a location, lot/layer link, method, unit or report revision.Keep result unassigned/Pending and reconcile with the original request, field sheet and laboratory before use.
Reported result is outside the cited criterion or marked invalid/anomalous.Preserve the original report, identify affected work, raise/link project nonconformance and obtain the required written disposition.
Retest is requested after corrective work.Create a new event row with its own test date, location, method and report; cross-reference the original failing result and affected extent.
A lot needs a pass decision but no reviewer or project criterion is named.Leave status Pending and request the contract/project-assigned reviewer and exact approved acceptance reference.

Compaction evidence handover

This register links actual reports to defined work and records review status. It does not set a test frequency or compaction criterion, certify field/laboratory work, or automatically pass/accept a lot.

Record lot review status options in the blank record:

Record the assigned roles: Field tester / laboratory / report references; Recorder / lot register revision / date; Assigned project reviewer role / written outcome / date; Open failure / NCR / corrective work / retest references; Evidence recipient / handover date.

Fictional lot-to-report trace — no result shown

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

Illustrative lot L-00, layer LY-00, test point TP-00, report R-00. No measured value, unit or status is represented.

Requirement to carry into the record
Retain a distinct row for each actual report and link any failure to a later correction, retest and written disposition.
Illustrative reference
Fictional identifiers only; no implied test method or acceptance outcome.
What the site record should capture
No result, criterion, date, signature or pass status is prefilled.

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need your ITP prepared for this project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.