Scope and limitations
Internal wet-area checks may cover substrate readiness, falls and junctions, membrane application, curing and inspection before covering.
Use the specified proprietary system instructions, approved details and project specification. Requirements differ by system and jurisdiction.
Inspection steps in this starting template
- Scope and compliance basis — Confirm rooms, wet-area types, system limits and interfaces included.
Review approved scope, room schedule, drawings and jurisdiction/compliance pathway.
- Product/system approval — Check specified membrane, primer, bond breaker, reinforcement and accessories are the approved compatible system.
Compare submittals, product labels and current manufacturer data to approved product schedule.
- Delivery and storage — Check delivered product identity, batch, shelf life and storage condition.
Inspect packaging/labels and compare to approved submittal and current manufacturer storage instructions.
- Substrate readiness — Inspect substrate type, soundness, cleanliness, dryness/condition and surface preparation before priming.
Visual inspection; check moisture/condition using method and limit in project/manufacturer documents; record defects and remedial preparation.
- Falls and drainage — Check floor falls, floor waste position, drainage path and any step-down/threshold details before membrane.
Measure levels/falls against approved drawings and jurisdiction/code pathway; confirm waste is secure and interface detail identified.
- Junctions and movement joints — Inspect wall-floor junctions, internal corners, changes of plane, construction/movement joints and bond-breaker detail.
Visual check against approved detail and system instructions; record each junction type and treatment.
- Penetrations and outlets — Check pipe penetrations, floor wastes, puddle flanges and fixtures interfaces are stable and treated.
Visual inspection and compare dimensions/details to approved drawings and system instructions.
- Primer and preparation coat — Verify primer selection, mixing (if applicable), application and drying/overcoat readiness.
Observe product/batch and application; record ambient/substrate conditions where required by data sheet.
- Membrane first coat — Inspect coverage, continuity, corners, upturns and specified reinforcement at first application.
Visual inspection while accessible; measure wet/dry thickness or consumption only by manufacturer/project-prescribed method.
- Membrane subsequent coat(s) — Check subsequent coats, direction/overlap and cure/recoat interval.
Visual check; record coat time and conditions against product instructions.
- Upturns and terminations — Inspect membrane height/extents, edges, doorway/threshold termination, hob and bath/shower details.
Measure only against project detail and applicable pathway; visually inspect terminations and continuity.
- Curing and protection — Confirm cure before traffic, flood test or follow-on trade; inspect protection method.
Check elapsed time and conditions against manufacturer instructions; inspect protection and trade interface.
- Specified water test — Where required, inspect test setup and result before finishes/concealment.
Use only project-approved test method, boundaries, duration and limits; document start/end, observed leakage and result.
- Pre-cover inspection — Final inspection before screed, tile, lining or other concealment.
Walk down complete system; verify all prior issues closed and photograph critical concealed interfaces.
- Tiling/screed interface — Check membrane protection and any screed/adhesive interface details before finishes.
Review approved detail and manufacturer compatibility; inspect that membrane is not damaged and required protection/separation is installed.
- Defects, repairs and retest — Track damage, pinholes, delamination or failed test; inspect repair.
Record defect location, approved repair method, product/batch, reinspection and retest where required.
- Completion and handover — Check required certificates, warranties, product/batch traceability, photos and maintenance information.
Review handover schedule and project-required documents.
How to complete the project fields
- Identify the actual work package and remove steps outside its scope.
- For each retained check, cite the current drawing, specification, product instruction or approved project document.
- Enter project acceptance requirements exactly from those sources and agree inspection responsibilities and release points.
- Keep measurements, observations, dates and signatures blank until checks are performed on site.
Source notes
The starting structure is a general planning aid. The links below explain topic context; they do not set universal project acceptance values.
- ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing
Inspected online topic support for housing wet areas, systems/materials, substrate, falls and construction details. Apply only after confirming building class, state adoption/variations and compliance pathway; not a universal commercial-building rule.
- ABCB, NCC 2022 referenced documents
Inspected for NCC reference status/editions and relevant clause pointers; does not provide the full standards or make them applicable to every project.
- ABCB, Waterproofing in houses
Method/topic guidance confirming NCC housing wet-area scope and alternative compliance pathways; not a project specification.
- Construction Quality Association, Guide: How to create an ITP
ITP structure and preparation method only; not technical waterproofing acceptance criteria.
- Sika Australia, Sikalastic-1K Product Data Sheet
Public Australian manufacturer product page and linked PDS content inspected. This is one product example supporting the topics substrate, application and cure; it supplies no criteria for another system and does not establish project approval.