Wet-area waterproofing · Free field record

Pre-Tiling Waterproofing Inspection Checklist

A before-covering check of the installed membrane, vulnerable details, documented cure conditions, specified tests, defects and handover evidence before tiling or screeding.

Excel provides separate project setup, field record and issue/handover sheets, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Ordinary indoor wet areas after membrane installation and before tile/screed concealment or downstream trade handover. Captures surface continuity, detail condition, product-specific readiness evidence and project-defined tests/release.

Outside this record: Installing the membrane, assessing substrate readiness, prescribing a flood test, certifying compliance, authorising tiling or approving defects. A test is included only when required by the approved project/system and must use its specified method and acceptance.

Blank record for ordinary indoor wet areas. Fill criteria from the approved project details and exact compatible system instructions, after confirming the applicable project compliance basis. Observations, test results and signatures stay blank until the work is checked. Recording installer work or site observations does not grant certification or contractual release authority.

Collect these project inputs first

Project compliance pathway and current adopted edition
Identify the project building class, jurisdiction, adopted edition, variations and approved compliance pathway; a published code edition does not establish applicability.
Exact membrane system and current TDS revision
Cure, recoat, over-tile and test windows differ across products and site conditions.
Membrane installation records and room map
Pre-cover inspection must trace each area and junction to actual application and repair evidence.
Project-specific test method and acceptance
A flood test is not universal; record duration and limits only if approved project evidence requires them.
Contractual notice and release role
Installer finish, site verification, independent certification and builder/client release are separate actions.

How to use the checklist

  1. Use this record only after the membrane application records are available and before tiles/screed hide the membrane.
  2. Inspect each room and vulnerable detail; compare against exact approved drawings and current system instructions; record defects, repairs and recheck evidence.
  3. Enter cure/overcoating requirements and any water test only from the exact current approved system/project documents. Do not treat dry-to-touch or a marketing claim as permission to cover.
  4. Record installer declaration, site verifier findings, any required certifier inspection and contractual release separately, with named roles and references.
  5. If any area is damaged, contaminated, incomplete or outside its documented window, keep its status Pending and obtain disposition before concealment.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

WT-01 · Installation traceability and completed extent

Confirm each room/zone proposed for tiling maps to membrane application records, selected product system, batch information and final-coat date where available.

How to check
Reconcile room map, installer log, labels and repair records; mark unrecorded or excluded areas clearly.
What defines acceptance
Every proposed cover area is traceable to the approved system and actual installation record; missing area/product/date evidence is resolved or explicitly dispositioned.
Project document to cite
Approved room schedule, membrane application record, current product submittal and batch evidence.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Construction Quality Association, Guide: How to create an ITP.

Blank record fields
  • Room / zone
  • Membrane / batch
  • Final coat date
  • Install record ref
  • Result, inspector and date; issue and recheck reference

WT-02 · Membrane surface and continuity

Inspect the exposed membrane for visible damage, pinholes, discontinuities, contamination, debonding or unfinished patches.

How to check
Walk all accessible surfaces under suitable light; map defects and take location-linked photographs; use only project/product-approved inspection method.
What defines acceptance
Surface is complete and free of unresolved visible defects against the project and exact system criteria; visual inspection alone is not represented as proof of watertightness.
Project document to cite
Approved project inspection criteria and current membrane TDS.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet.

Blank record fields
  • Defect / location
  • Extent / photo
  • Repair instruction
  • Recheck result
  • Result, inspector and date; issue and recheck reference

WT-03 · Junctions, penetrations and terminations

Inspect membrane continuity at wall/floor and wall/wall junctions, movement joints, drains, penetrations, waterstops, thresholds and terminations.

How to check
Check each detail against approved enlarged drawings and selected tape/sealant/membrane sequence; record inaccessible or damaged interfaces.
What defines acceptance
All required interfaces match approved details and current compatible system instructions; any omitted/inaccessible detail is resolved before concealment.
Project document to cite
Approved wet-area details, applicable code pathway and exact accessory/membrane TDS.

Topic references: ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing; ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Sika Australia, Sika SealTape F Product Data Sheet.

Blank record fields
  • Detail / location
  • System components
  • Continuity note
  • Photo / RFI ref
  • Result, inspector and date; issue and recheck reference

WT-04 · System-specific cure and covering readiness

Check whether the system-specific cure, environmental and overcoating/tiling conditions required by approved documents have been met.

How to check
Compare final-coat time and recorded site conditions to the exact current local TDS and project specification; record any conditions the source requires.
What defines acceptance
Document that the cited product and governing project conditions are met. Resolve conflicting instructions through project document precedence and written clarification; do not silently select the stricter value. No cure or waiting period is supplied by this form.
Project document to cite
Exact approved membrane TDS revision, application log and project specification.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet.

Blank record fields
  • Final coat time
  • Site conditions
  • TDS revision
  • Reviewer / evidence
  • Result, inspector and date; issue and recheck reference

WT-05 · Specified water or other performance test

Confirm whether a test is required and, only when specified, record the actual approved test setup, observations and outcome.

How to check
Review contract/specification/system instruction for method, area, isolation, duration, acceptable level/condition and witness; attach test record. If none applies, mark N/A with source/reason.
What defines acceptance
Test requirement and acceptance are traceable to this project/system. No generic flood-test duration, depth, pass rule or permission to test is implied; a missing criterion remains Pending.
Project document to cite
Project specification/ITP and current system instructions; named approved test procedure.

Topic references: ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing; ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Construction Quality Association, Guide: How to create an ITP.

Blank record fields
  • Test / N/A basis
  • Method / criteria ref
  • Actual observation
  • Witness / report ref
  • Result, inspector and date; issue and recheck reference

WT-06 · Repairs, reinspection and protection

Confirm all recorded defects have an approved repair, reinspection evidence and protection/interface plan for follow-on trades.

How to check
Revisit mapped locations after repair; compare repair materials and sequence to compatible system instructions; record how membrane will be protected from damage.
What defines acceptance
Repair and recheck evidence is closed or remains explicitly open; follow-on work has agreed protection/interface measures before covering.
Project document to cite
Approved repair disposition, current system TDS and project follow-on trade method.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Sika Australia, Sika SealTape F Product Data Sheet.

Blank record fields
  • Issue / repair ref
  • Repair product / date
  • Recheck / inspector
  • Protection plan
  • Result, inspector and date; issue and recheck reference

WT-07 · Installer, site verifier and formal release record

Record installer completion, independent/site verifier observation, any appointed certifier decision and contractual release/witness outcome as separate items.

How to check
Check project ITP/contract for notice, hold, witness and release authority; record actual person/role, scope, date, response and document reference.
What defines acceptance
No party’s observation is attributed to another. Tiling/screeding follows the actual project release conditions; blank or pending formal approval is not inferred from an installer signature.
Project document to cite
Contract, project ITP, appointment/authority records, inspection report and any issued certificate/release.

Topic references: Construction Quality Association, Guide: How to create an ITP; ABCB, Editions of the National Construction Code.

Blank record fields
  • Event / scope
  • Person / role
  • Notice / outcome
  • Release / certificate ref
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
No project document states whether a water test is required.Do not assume a universal flood test; confirm the requirement, method, limit, duration, safe setup and responsible witness with the project authority.
Manufacturer cure/tiling guidance differs from the programme or another document.Record both references and request a documented project resolution; do not select the shorter time by assumption.
Membrane is damaged, dirty, visibly discontinuous or has unsealed penetrations/details.Map the location, record repair instruction and evidence, and inspect/recheck before covering.
Installer says the area is complete but no separate formal release is recorded.Record installer completion as such; leave contractual or regulatory release Pending until the appointed authority records its decision.

Pre-covering status

A site observation or installer statement does not authorise tiling. Select the first status only when the applicable project release evidence is recorded; it still does not constitute engineering approval or statutory certification.

Pre-covering / next-trade status options in the blank record:

Record the assigned roles: Installer declaration / role / date; Site verifier / role / date; Certifier only if appointed/required / reference; Contract release authority / reference.

Teaching example — pre-cover evidence check

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

Fictional training scenario only. Example room B-02, batch EXAMPLE-LOT-7 and photo reference TRAINING-PH-03 are invented identifiers. This is a prompt illustration, not a completed inspection.

Requirement to carry into the record
Illustrative requirement: compare the final membrane and drain/junction details with the current approved room detail and exact selected product instructions before concealment. Any cure or test requirement must be sourced from those documents; this example intentionally gives no period or result.
Illustrative reference
Illustrative only: fictitious WA-DTL-07 Rev C; actual criteria and revision must be entered from the live project file.
What the site record should capture
Is this specific room and membrane area traceable? Which details were observed? What current source controls cover readiness? Are any test, repair, witness or formal release records still Pending?

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.