Wet-area waterproofing · Free field record

Waterproofing Substrate Readiness Checklist

A pre-membrane hold-and-record sheet for substrate condition, falls and drainage interfaces, defects, preparation and product-specific primer readiness.

Excel provides separate project setup, field record and issue/handover sheets, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Ordinary indoor wet-area wall and floor substrates immediately before primer or membrane installation. Focuses on handover from substrate/preparation work to the waterproofing installer.

Outside this record: Membrane coat inspection, pre-tiling release, structural design acceptance, concrete moisture design or substrate engineering assessment. No universal moisture percentage, surface profile, fall value, drying period or repair method is set here.

Blank record for ordinary indoor wet areas. Fill criteria from the approved project details and exact compatible system instructions, after confirming the applicable project compliance basis. Observations, test results and signatures stay blank until the work is checked. Recording installer work or site observations does not grant certification or contractual release authority.

Collect these project inputs first

Project jurisdiction, class and compliance pathway
Identify the project building class, jurisdiction, adopted edition, variations and approved compliance pathway; a published code edition does not establish applicability.
Substrate materials and construction records
Concrete, screeds, sheet flooring and wall linings have different system compatibility and preparation requirements.
Approved finish levels, falls and drainage details
Compare to issued drawings/criteria; this record does not invent the design values.
Membrane, primer and preparation products
Use exact manufacturer instructions for the selected substrate and system.
Required substrate condition tests and acceptance
Enter method/value only when required and defined by approved project/system evidence; otherwise raise a clarification.

How to use the checklist

  1. Inspect and record the actual substrate by room and surface before primer/membrane work begins.
  2. Record type, visible condition, defects, drainage/interface geometry and preparation status. Add measurements only against stated project criteria and approved method.
  3. Consult the exact selected membrane/primer instructions for substrate compatibility, dryness, preparation and primer; manufacturer values are product-specific.
  4. Mark unresolved cracks, contamination, movement, ponding, incompatible materials or missing acceptance criteria Pending; assign an action and recheck.
  5. This is a substrate handover record. The person checking does not gain design authority or certify the compliance pathway by signing it.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

WS-01 · Room, substrate and system match

Confirm the substrate inspection is for the correct room/surface and the substrate type is permitted by the approved membrane/primer system.

How to check
Compare room/element IDs, substrate build-up and product submittal/TDS; inspect accessible surface and record where condition changes.
What defines acceptance
Observed substrate type and condition align with approved drawings and selected system scope; unlisted substrate or undocumented build-up remains Pending.
Project document to cite
Approved room details, substrate submittal and current selected membrane/primer TDS.

Topic references: ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing; ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet.

Blank record fields
  • Room / surface
  • Substrate type
  • Membrane / primer
  • Drawing / submittal rev
  • Result, inspector and date; issue and recheck reference

WS-02 · Surface soundness and damage

Inspect for loose/friable areas, weak edges, spalls, cracks, holes, ridges or defects likely to disrupt preparation or membrane continuity.

How to check
Visual and tactile inspection; map each defect on room sketch/photo and record size/location only when measured using project method.
What defines acceptance
Surface is repaired/accepted to the cited project and system criteria; unresolved movement or structural defects are referred for design disposition, not hidden by coating.
Project document to cite
Approved substrate criteria, repair detail and selected system TDS.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Sika Australia, Sika SealTape F Product Data Sheet.

Blank record fields
  • Defect / location
  • Measured value
  • Disposition ref
  • Recheck photo
  • Result, inspector and date; issue and recheck reference

WS-03 · Cleanliness and contaminants

Check that dust, oil, grease, curing compounds, sealers, old adhesive/coatings, laitance and loose debris relevant to this substrate have been addressed.

How to check
Inspect after the specified mechanical/vacuum/cleaning preparation; record observed contaminants and completed method.
What defines acceptance
Prepared surface meets the exact system’s stated cleanliness condition; remaining contaminants are removed and rechecked before primer.
Project document to cite
Approved preparation method and current membrane/accessory TDS.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Sika Australia, Sika SealTape F Product Data Sheet.

Blank record fields
  • Contaminant / area
  • Prep method / date
  • Surface after prep
  • Photo ref
  • Result, inspector and date; issue and recheck reference

WS-04 · Moisture / dryness requirement

Determine whether the approved project or selected system requires a moisture/dryness test and whether the specified method and criterion are available.

How to check
Review the exact product TDS and project specification; if testing is specified, record test location, method, instrument and actual value without substituting another method.
What defines acceptance
Test result meets only the cited applicable criterion. If no applicable method/value or system requirement is identified, record the gap and obtain direction; no generic moisture limit is implied.
Project document to cite
Project specification and current local membrane/primer TDS, including test method and stated substrate scope.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet.

Blank record fields
  • Test / location
  • Method / instrument
  • Actual value / unit
  • Criterion source
  • Result, inspector and date; issue and recheck reference

WS-05 · Falls, levels and drainage readiness

Check floor levels/falls, local ponding and waste/flange location against the approved detail before membrane work.

How to check
Use the project’s stated measurement method and reference points; map actual readings and drain/threshold interface. Do not infer required falls from another building class or pathway.
What defines acceptance
Observed conditions satisfy the cited approved project details and applicable code pathway; discrepancy, ponding or missing datum is referred before covering.
Project document to cite
Approved architectural/wet-area and drainage drawings; applicable adopted code clauses and project criteria.

Topic references: ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing; ABCB, Waterproofing in houses.

Blank record fields
  • Point / datum
  • Actual level / fall / unit
  • Drain / threshold ID
  • Drawing / action ref
  • Result, inspector and date; issue and recheck reference

WS-06 · Joints, penetrations and repair preparation

Identify movement joints, cracks, wall/floor changes, penetrations and prior repairs that require system-specific treatment before membrane installation.

How to check
Walk the surface and compare each detail to approved drawings and current system accessory instructions; photograph and map omitted details.
What defines acceptance
Required detail and repair method are approved, accessible and ready for application; unresolved movement/design questions or incompatible repairs remain open.
Project document to cite
Approved wet-area details and exact membrane/accessory TDS.

Topic references: ABCB, NCC 2022 Housing Provisions, Part 10.2 Wet area waterproofing; ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Sika Australia, Sika SealTape F Product Data Sheet.

Blank record fields
  • Detail / location
  • Approved treatment
  • Repair evidence
  • Open RFI
  • Result, inspector and date; issue and recheck reference

WS-07 · Preparation, primer and handover readiness

Confirm specified preparation is complete and the approved primer/product, surface condition, environmental checks and handover are ready for the next operation.

How to check
Compare actual prepared surface and planned primer with exact system instructions; record applicable weather/temperature check only where project/TDS requires it.
What defines acceptance
No unresolved defect or missing system/project criterion remains; ready status is recorded by the assigned role. This entry is not formal client release unless project says so.
Project document to cite
Project ITP/work method, current selected primer/membrane TDS and subcontract handover requirement.

Topic references: ARDEX Australia, WPM 155 Rapid Plus Technical Data Sheet; Construction Quality Association, Guide: How to create an ITP.

Blank record fields
  • Prep record
  • Primer / batch
  • Required readings
  • Handover / date
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
Substrate type or build-up is not shown in approved documents.Record the observed construction and obtain design/project confirmation of suitability before applying a system.
Substrate has contamination, loose material, sharp edges, cracks, laitance or previous coatings.Record locations and disposition; use only the approved preparation/repair method for that substrate and system, then document recheck.
Moisture condition is required but no applicable method/limit is available.Leave the criterion unresolved and ask the project/system authority for the test method, threshold and decision role; do not copy a value from another manufacturer.
Falls or drainage geometry differs from approved details or is unclear.Record measured location and drawing reference; request instruction before membrane covers the surface.

Substrate handover before membrane

“Ready” records this site handover only; it does not approve substrate design or confirm code compliance. The waterproofing installer and any appointed verifier record their own roles. Missing suitability or acceptance criteria stay open.

Pre-installation handover status options in the blank record:

Record the assigned roles: Substrate installer / role / date; Waterproofing installer receiver / date; Site verifier / role / date; Instruction authority / reference.

Teaching example — substrate clarification

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

Fictional training scenario only. Example room B-02 and ticket RFI-WP-014 are invented; no substrate has actually been inspected.

Requirement to carry into the record
Illustrative requirement: the substrate type and falls must match the approved room detail and the selected system must permit that substrate. The example intentionally supplies no moisture limit, repair threshold or measured result.
Illustrative reference
Illustrative only: fictional A-204 Rev B plus fictitious clarification RFI-WP-014; replace with project documents.
What the site record should capture
Record the room/surface, actual substrate, exact drawing and system instruction, observed condition, missing criterion and person assigned to resolve it.

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.