FAB · Scoped work package

Structural Steel Fabrication ITP Template

Shop material traceability, processing, fit-up, welding, specified inspection, coating interfaces and dispatch dossier.

What this plan covers

Project-specific baseline for workshop processing, assembly, welding and inspection interfaces, subcontract coating, fabrication records and dispatch to site. It does not certify design, provide a WPS, determine weld/NDT acceptance values, select coatings or create inspection release rights.

Free editable proposed work-package baseline; sources are topic guidance, not adopted project acceptance criteria. Complete against contract, drawings, specification, approved procedures, adopted standards and assigned roles.

Define the package before tailoring it

Fabrication shop / suppliers
Identify the fabricator, processors, coating/NDT subcontractors and where each activity occurs.
Included fabrication processes
Select material processing, assembly, welding, specified NDT, coating, trial assembly and dispatch scope.
Project traceability and dossier basis
Enter required identification level, transfer controls and handover dossier structure from project documents.
Erection handover boundary
Identify the receiving erector, required member/connection evidence and interface records.

Inspection sequence and project requirements

This starting plan contains 10 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

FBR-01 · Package definition and submittal readiness

Work stage
Package definition and submittal readiness
Inspection / test
Confirm the fabrication lot, downstream erection interfaces and required submissions are defined before steel is released for production.
Method
Compare contract scope, drawing register, steel schedule, submittal register and supplier/subcontract interfaces; flag unresolved revisions or responsibility gaps.
Acceptance condition
The identified lot and interfaces map to the current controlled drawings and specified category; required submissions and unresolved decisions are visible before work proceeds. Project acceptance basis to complete from the controlled source: [Fill: Approved structural and steelwork drawings / revisions], [Fill: Specified construction category and design basis], [Fill: Fabrication, subcontractor and handover boundary].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Fabrication package and submittal register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Specified construction category and design basis; Fabrication, subcontractor and handover boundary; Performing, reviewing, witness and release roles; Project record, submission and closeout requirements
Blank record fields
Package / lot reference; Drawing and revision; Detailer / processor / coater / erector interface; Open decision / action reference

FBR-02 · Incoming steel and certificate traceability

Work stage
Incoming steel and certificate traceability
Inspection / test
Verify received steel identity and preserve the link from each project lot or member to its supplied compliance documents.
Method
Compare purchase/delivery documentation, physical marks or controlled transfer marks, member/heat references and certificates against the project material schedule; document breaks before processing.
Acceptance condition
The identified product agrees with the specified material record and its compliance documentation remains traceable through the project's required identification level; gaps are segregated and referred for written disposition. Project acceptance basis to complete from the controlled source: [Fill: Steel grade, product and certification requirements].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Incoming material and traceability register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Steel grade, product and certification requirements; Approved structural and steelwork drawings / revisions; Performing, reviewing, witness and release roles
Blank record fields
Member / piece mark; Heat / batch / source ID; Specified material designation; Certificate and source document ref.; Traceability gap / disposition ref.

FBR-03 · Detailing and approved shop information

Work stage
Detailing and approved shop information
Inspection / test
Check shop details used for manufacture against the controlled design information and record resolved design interfaces.
Method
Review shop drawing, member list, connection/bolt details and revision status against contract drawings and approved design responses; record specific discrepancy references.
Acceptance condition
Released shop information identifies the member and connection being made and has the review/approval status required by the contract; unresolved design changes are not silently incorporated. Project acceptance basis to complete from the controlled source: [Fill: Approved structural and steelwork drawings / revisions], [Fill: Specified construction category and design basis].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Shop drawing review and change register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Specified construction category and design basis; Performing, reviewing, witness and release roles
Blank record fields
Member / assembly mark; Shop drawing / revision / detail; Design drawing / revision / detail; RFI / design response / approval ref.

FBR-04 · Cutting, drilling and edge preparation

Work stage
Cutting, drilling and edge preparation
Inspection / test
Inspect processed components against their identified drawings and fabrication details before assembly obscures the features.
Method
Identify the member mark; compare cut, hole and edge-preparation features with the cited drawing/detail and approved fabrication information; note the actual inspection evidence and discrepancy location.
Acceptance condition
The inspected member and relevant features correspond to the controlled details and specified preparation; any deviation has a traceable approved disposition before incorporation. Project acceptance basis to complete from the controlled source: [Fill: Approved structural and steelwork drawings / revisions].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Fabrication processing and dimensional record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Specified construction category and design basis; Performing, reviewing, witness and release roles
Blank record fields
Member mark; Cut / hole / edge feature and drawing locator; Observed dimension / condition and unit; Measurement method / tool ref.; Deviation / disposition ref.

FBR-05 · Joint fit-up and assembly before welding

Work stage
Joint fit-up and assembly before welding
Inspection / test
Verify the identified joint preparation and fit-up against its weld detail before welding changes access to the joint.
Method
Locate the joint on the weld map and compare preparation, alignment, cleanliness, backing and fit-up features that the approved WPS and project detail require; record the observed feature, not a generic pass tick.
Acceptance condition
Joint identity, preparation and fit-up match the cited approved detail and applicable WPS requirements; unresolved departures are held for assigned disposition before welding. Project acceptance basis to complete from the controlled source: [Fill: Weld category, WPS, personnel evidence and acceptance].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Joint fit-up and weld map record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Weld category, WPS, personnel evidence and acceptance; Performing, reviewing, witness and release roles
Blank record fields
Weld ID / member and joint locator; Weld map / drawing revision; WPS reference / revision; Observed fit-up feature / condition; Deviation / disposition ref.

FBR-06 · Welding process and weld identity

Work stage
Welding process and weld identity
Inspection / test
Maintain a traceable record connecting each performed weld to its joint, applicable procedure and production evidence.
Method
Review the weld map and production record for the actual joint ID, procedure reference, responsible welder/operator evidence required by the project, date/shift, consumable/control records where specified, and any repair link.
Acceptance condition
Every recorded weld can be traced to its identified joint and applicable approved process evidence; required records are present and discrepancies or repairs remain linked to the original weld identity. Project acceptance basis to complete from the controlled source: [Fill: Weld category, WPS, personnel evidence and acceptance].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Weld production and repair register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Weld category, WPS, personnel evidence and acceptance; Performing, reviewing, witness and release roles; Project record, submission and closeout requirements
Blank record fields
Weld ID / member / location; WPS / revision; Welder / operator evidence ref.; Date / production record ref.; Repair / reinspection ref.

FBR-07 · Completed weld inspection and specified NDT

Work stage
Completed weld inspection and specified NDT
Inspection / test
Record visual inspection and only project-specified NDT against the identified weld and acceptance source.
Method
Identify the weld on the weld map; compare observable weld features with the cited criteria; link any NDT request, report, method, extent and result to that same joint. Preserve the original report.
Acceptance condition
The inspection record and any required report identify the weld, method and controlling acceptance reference; required evidence is complete and nonconformances have an assigned disposition and recheck trail. Project acceptance basis to complete from the controlled source: [Fill: Weld category, WPS, personnel evidence and acceptance], [Fill: Specified NDT method, extent, timing and acceptance].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Weld inspection and NDT report index
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Weld category, WPS, personnel evidence and acceptance; Specified NDT method, extent, timing and acceptance; Performing, reviewing, witness and release roles; Project record, submission and closeout requirements
Blank record fields
Weld ID / member / location; Acceptance source / clause; Visual observation / disposition; NDT method / report / result ref.; NCR / repair / recheck ref.

FBR-08 · Trial assembly / fabrication geometry

Work stage
Trial assembly / fabrication geometry
Inspection / test
Where required by the project, verify assembly interfaces and measured geometry against identified drawings before disassembly or shipment.
Method
Record assembly marks and measurement locations; compare actual measured features with the project-nominated drawing dimensions/tolerances and identify instrument/report references.
Acceptance condition
The assembly, measurement location and actual observations are traceable to the controlled acceptance source; results outside or without a source are referred for project disposition. Project acceptance basis to complete from the controlled source: [Fill: Project geometry / survey tolerances and evidence].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Trial assembly and dimensional survey record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Project geometry / survey tolerances and evidence; Performing, reviewing, witness and release roles
Blank record fields
Assembly / member marks; Measurement point / drawing locator; Observed dimension / unit; Drawing / tolerance source; Survey / instrument / report ref.

FBR-09 · Surface preparation, coating and repair interface

Work stage
Surface preparation, coating and repair interface
Inspection / test
Verify specified surface treatment evidence and retain identification through subcontract processing and return to the fabricator.
Method
Compare the coating work order and member marks with specified system documents; review preparation/application/environmental readings and repair records only where required by the project; link subcontract report to each lot/member.
Acceptance condition
The delivered coating evidence identifies the specified system, inspected lot/member and source criteria; incomplete, damaged or discrepant areas have traceable project disposition and repair evidence. Project acceptance basis to complete from the controlled source: [Fill: Specified coating system, preparation, inspection and repair].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Surface treatment and coating traceability record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Specified coating system, preparation, inspection and repair; Approved structural and steelwork drawings / revisions; Fabrication, subcontractor and handover boundary; Performing, reviewing, witness and release roles; Project record, submission and closeout requirements
Blank record fields
Member / lot mark; Specified coating system / source; Subcontractor / process record ref.; Observed inspection / reading / unit if specified; Damage / repair / reinspection ref.

FBR-10 · Fabrication dossier and dispatch release interface

Work stage
Fabrication dossier and dispatch release interface
Inspection / test
Compile the required manufacturing evidence and maintain the link from shop lot/member marks to packing and receiving records.
Method
Reconcile material certificates, traceability, shop drawing revisions, weld map and inspection reports, coating evidence, NCR dispositions and member/packing list against project dossier requirements.
Acceptance condition
The required dossier index identifies the supplied member/lot and controlled documents; open exceptions and delivery/erection handover items are clearly listed for assigned project review. Project acceptance basis to complete from the controlled source: [Fill: Project record, submission and closeout requirements], [Fill: Fabrication, subcontractor and handover boundary], [Fill: Approved structural and steelwork drawings / revisions].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Fabrication dossier index and dispatch register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Project record, submission and closeout requirements; Fabrication, subcontractor and handover boundary; Performing, reviewing, witness and release roles; Approved structural and steelwork drawings / revisions
Blank record fields
Fabrication lot / packing list; Member marks / quantity basis; Dossier index / revision; Open NCR / concession / missing evidence ref.; Transport / receiving interface ref.

Source notes

Connect the plan to field evidence

How to write a structural steel ITP · Compare the broader structural steel scope · Site erection plan

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Browser editor

Loading the editable steel fabrication plan. Download a file above if the editor is unavailable.