Structural steel · Free field record

Structural Steel Weld Visual Inspection Record

A weld-by-weld visual inspection form for joint identity, approved procedure references, observable surface condition, mapped repair and reinspection evidence.

Excel provides separate project setup, field record and issue/handover sheets, plus a repeatable weld inspection and repair log sheet, to keep project requirements, observations and follow-up separate. Word is editable; PDF is arranged for printing. These files are blank records, with no completed results.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Use this record for

Visual examination of accessible completed structural-steel welds at the project-defined inspection stage, including joint traceability, surface observations and disposition/reinspection links.

Outside this record: Welding procedure approval, welder qualification assessment, design of welds, acceptance limits not supplied by the project, NDT execution or interpretation, and certification of welding quality.

This is a blank visual inspection record, not an NDT report. Identify the specified visual examination method and project acceptance criteria before inspection; keep actual observations and results blank until the work is examined.

Collect these project inputs first

Current weld map and joint details
Defines unique weld IDs, joint locations, type and any drawing-specific detail needed for traceability.
Approved welding procedure and project welding specification
Supplies the applicable process/procedure and visual acceptance basis for the specific weld.
Project construction category and inspection plan
Identifies required inspection stages, responsible roles and any contractual notice or release point.
Specified NDT plan and reporting route
Separates visual inspection from any required ultrasonic, radiographic, magnetic-particle or penetrant examination.
Repair and reinspection procedure
Defines how a reported indication is dispositioned, repaired and linked to subsequent examination.

How to use the checklist

  1. Use one record for one identifiable weld or a project-defined weld lot with each included weld listed. Confirm shop/site location and current weld-map revision.
  2. Record joint identity, applicable drawing detail, WPS revision and personnel references required by the project before entering an observation.
  3. Inspect only at the stage and by the method specified by the project; record actual visible condition, access limitations and observation evidence.
  4. Enter the project clause or approved weld-acceptance document used. Do not copy a threshold from a different construction category or standard edition.
  5. If an indication or inaccessible area is found, describe it, map it to the weld and leave disposition pending until the assigned welding/engineering role directs action.
  6. Link repairs and reinspection to the original weld ID. Record NDT only as a separate report reference and do not use this form as a substitute for that report.

Checks and the records they need

Fill project criteria from approved documents before inspection. The fields below show what the downloaded form asks you to record; the web page does not save or approve site results.

Weld inspection and repair log for repeat entries

Use one line for each actual weld examination or repair/re-examination event. Keep the original weld ID constant across events and use the weld map and NCR/repair reference to preserve the sequence. Enter NDT only as a linked report reference.

Columns in the blank log
  • Inspection date / stage
  • Weld ID / drawing ref
  • Joint / location / side
  • WPS / revision
  • Actual visual observation
  • Project criterion / clause
  • Repair / NCR / recheck ref
  • NDT report ref if specified
  • Inspector / role / status

The files provide 6 blank entry rows. Continue on another blank copy as needed; the web page does not record site entries.

WVI-01 · Weld identity and examination boundary

Weld number, member marks, joint location, drawing/weld-map revision, shop or site stage, and the portion included in this examination.

How to check
Locate the joint physically and reconcile it to the current weld map and inspection request; record any inaccessible length or boundary.
What defines acceptance
The examined joint is uniquely traceable to the controlled drawing/weld map and stated examination extent; unidentified or inaccessible portions remain open.
Project document to cite
Approved drawing connection detail, weld map, inspection request and current revision register; cite drawing sheet, grid/member and weld mark.

If a discrepancy is found: Do not mark an unidentified or partly inaccessible weld complete; identify the affected portion and request the current weld map/access direction.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Weld ID / joint mark
  • Member / grid / location
  • Map and drawing revision
  • Examined portion / access limit
  • Result, inspector and date; issue and recheck reference

WVI-02 · Procedure and personnel traceability

Applicable WPS/process revision, joint/material scope references and welder identity where the project requires the link.

How to check
Compare the weld map and fabrication/site weld record to the controlled WPS register and required personnel records; do not assess qualification beyond supplied project evidence.
What defines acceptance
The references attached to the weld are the ones required by the approved project welding plan; any missing or mismatched document remains unresolved before disposition.
Project document to cite
Approved WPS register, project welding specification, weld log and project-required personnel/continuity record; cite exact entry and revision.

If a discrepancy is found: Keep a missing or mismatched procedure/personnel link open and refer it to the assigned welding quality role before disposition.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • WPS / revision / process
  • Material / thickness range source
  • Welder ID / project record
  • Mismatch / query ref
  • Result, inspector and date; issue and recheck reference

WVI-03 · Examination stage and method

Specified visual examination procedure, stage (before/during/after coating or other stated stage), access, lighting/cleanliness conditions where prescribed.

How to check
Confirm the method and stage against the approved ITP or inspection request; record the actual conditions relevant to visibility and any limitation.
What defines acceptance
The examination follows the specified method and timing; any unavailable surface or method deviation is identified and referred rather than implied complete.
Project document to cite
Project ITP, approved welding inspection procedure, inspection request and coating sequence documents; cite row, revision and stage.

If a discrepancy is found: Record the actual method, stage or access deviation and arrange the project-specified follow-up; do not infer that the required examination occurred.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Inspection method / procedure
  • Required stage / trigger
  • Observed access condition
  • Deviation / instruction ref
  • Result, inspector and date; issue and recheck reference

WVI-04 · Visible weld profile and surface condition

Actual visible profile, continuity, termination, surface discontinuities, spatter or arc strikes only where covered by project acceptance rules.

How to check
Observe and describe the actual condition at its location; compare each observation with the project-defined visual criteria and record dimensions only where the method requires them.
What defines acceptance
Each observation is assessed against the cited project criterion and is traceable to its location; blank criteria or unsupported assumptions remain pending.
Project document to cite
Project-adopted welding standard and project weld criteria, including construction category and relevant acceptance reference; cite exact adopted edition/clause from controlled documents.

If a discrepancy is found: Record the actual visible finding, location and evidence, leave acceptance/disposition pending, and refer it to the designated welding or engineering role.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Observation / location
  • Measured feature / unit if required
  • Acceptance source / clause
  • Status / photo ref
  • Result, inspector and date; issue and recheck reference

WVI-05 · Surface preparation and visible defects before concealment

Accessible weld surface and adjacent material condition at the project inspection stage, including any preparation needed for examination.

How to check
Verify the specified examination access and surface condition; identify coating, dirt or geometry that prevents the required observation.
What defines acceptance
The required surface is accessible and examined under the project method, or limitation is recorded for a defined follow-up; obscured weld is not marked visually accepted.
Project document to cite
Approved inspection procedure, coating sequence, weld map and inspection hold/witness schedule where contractually assigned; cite area and stage.

If a discrepancy is found: Record the obscured area and reason, identify the access or surface-preparation limitation, and arrange the project-specified follow-up examination.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Surface condition
  • Area not examined / reason
  • Required follow-up / role
  • Evidence photo / request ref
  • Result, inspector and date; issue and recheck reference

WVI-06 · Indication disposition and repair mapping

Reported indication description/location, project decision, repair instruction, material removed/deposited reference and repair-weld ID where required.

How to check
Raise or cross-reference the project NCR/repair instruction; preserve the original observation and link later work rather than overwrite it.
What defines acceptance
Each reported condition has an assigned disposition and a traceable repair/engineering instruction; this record does not determine structural acceptability or repair design.
Project document to cite
Project nonconformance procedure, approved repair/WPS instruction and engineering disposition; cite NCR number, weld location and revisions.

If a discrepancy is found: Preserve the original indication, NCR and repair instruction references with status pending until the assigned role documents the disposition and repair plan.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Original indication / location
  • NCR / disposition ref
  • Repair WPS / instruction ref
  • Repair weld / evidence ref
  • Result, inspector and date; issue and recheck reference

WVI-07 · Re-examination, linked NDT and closure

Actual visual reinspection event, specified NDT method/extent if any, original report reference, remaining issue and authorized closeout status.

How to check
Record the visual result for the actual reinspection; separately link NDT request/report and retain the original report and evaluator decision.
What defines acceptance
Reinspection and any project-required NDT are documented against the same weld identity and their own governing criteria; unresolved findings remain open for assigned disposition.
Project document to cite
Project ITP and NDT schedule, approved NDT procedure, original NDT report, NCR closeout and weld dossier index; cite report revision and weld coverage.

If a discrepancy is found: Record the actual re-examination outcome and separately link any required NDT report; keep closure open until each specified examination and assigned review is documented.

Topic references: Cavoren structural steel fabrication and erection baseline; Queensland Department of Transport and Main Roads, MRTS78 Fabrication of Structural Steelwork (November 2020 listing); Queensland Department of Transport and Main Roads, Amendment Register (May 2026); Standards Australia, Australian Standards supporting the steel sector; Steelwork Compliance Australia, compliance scheme overview.

Blank record fields
  • Reinspection date / method
  • Actual visual result / evidence
  • NDT report / extent / status
  • Closeout role / NCR ref
  • Result, inspector and date; issue and recheck reference

When a check cannot be closed

SituationWhat to record or resolve
Weld map ID is absent or multiple welds share an unclear markHold the record pending controlled identification; request the current weld map or an approved traceability correction.
Visible indication is observed but acceptance basis is unclearDescribe and locate the observation with evidence, retain pending status, and refer to the specified welding/engineering authority; do not call it acceptable by appearance.
Weld is partly obscured or inaccessibleRecord the portion and reason that could not be examined; request the project method or access decision and do not infer completion.
Repair has been madeLink the repair instruction/NCR and actual repair record to the same weld identity, then record the specified reinspection separately.
NDT is requiredRecord method, report number, weld coverage and status in the linked NDT record; preserve the original NDT report and its separate acceptance decision.

Weld examination and disposition handover

A completed visual record does not certify the weld or replace specified NDT, procedure qualification evidence, engineering disposition or contractual release. Keep each original examination and repair event traceable.

Record inspection handover status options in the blank record:

Record the assigned roles: Recorder / inspector name and role / date; Assigned technical or project decision role / date; Supplier / fabricator contact if clarification is needed; Related register, report, NCR or instruction reference.

Fictional traceability example — not a project acceptance or completed inspection

Fictional teaching example only. These are illustrative document references, not a real project, engineering values or completed inspection results.

Teaching-only identifiers: fictional drawing ST-00, member M-000, lot H-000 and record REF-000. No real project, supplier or result is represented.

Requirement to carry into the record
A traceability label is a link to be verified, not proof by itself. Compare the physical identity, controlled project requirement and original source record; use a clearly identified placeholder for any missing project criterion.
Illustrative reference
Fictional ST-00 / M-000 / H-000 / REF-000; replace with current project records.
What the site record should capture
Show how an item, joint, connection or member links to an approved project reference and evidence record. Keep actual observations, assessment, decision and signatures blank until inspection.

Source notes and limits

Continue the work sequence

This field record documents checks after they are carried out. An ITP sets the work sequence, project criteria, responsibilities and required records before the work starts.

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.