Structural Steel Erection ITP Template

Site receiving, supports, approved stability documents, member connections, survey evidence and handover.

What this plan covers

Project-specific baseline for site receipt, support interfaces, erection readiness, member placement, connections, geometry evidence and handover. It does not design lifting operations, temporary works, structural stability or determine tolerances, fastener values, weld acceptance or contractual release rights.

Free editable proposed work-package baseline; sources are topic guidance, not adopted project acceptance criteria. Complete against contract, drawings, specification, approved procedures, adopted standards and assigned roles.

Define the package before tailoring it

Site workfront / structure
Identify the building/structure area, grids, levels and lot or handover basis.
Included site operations
Select receiving, placement, bolting, site welding, survey, grout and handover activities.
Temporary works / stability responsibility
Identify the approved sequence and responsible designer/reviewer; the ITP does not engineer lifting or stability.
Follow-on trade and release interfaces
Identify who receives the completed frame, required survey/dossier and separate contractual release roles.

Inspection sequence and project requirements

This starting plan contains 8 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

ERE-01 · Erection package and workfront release inputs

Work stage
Erection package and workfront release inputs
Inspection / test
Confirm erection scope, received member schedule, interface boundaries and approved sequence documents are identified for the workfront.
Method
Review contract scope, erection drawings/revisions, member list, approved sequence/temporary stability documents and project inspection/control requirements before site assembly.
Acceptance condition
The workfront and member/connection references map to controlled approved documents; required technical approvals and assigned decision roles are identifiable before the relevant operation. Project acceptance basis to complete from the controlled source: [Fill: Approved structural and steelwork drawings / revisions], [Fill: Specified construction category and design basis], [Fill: Approved erection sequence / temporary stability documents].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Erection workfront and document register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Specified construction category and design basis; Fabrication, subcontractor and handover boundary; Approved erection sequence / temporary stability documents; Performing, reviewing, witness and release roles
Blank record fields
Building / grid / workfront / lot; Erection drawing / revision; Approved sequence / temporary stability doc ref.; Trade / designer / erector interface; Open decision / release record ref.

ERE-02 · Delivery receipt and member identity

Work stage
Delivery receipt and member identity
Inspection / test
Check delivered member marks, packing identity, traceability handover and visible transport condition before distribution to the workfront.
Method
Compare delivery docket and packing list with member marks and fabrication dossier; inspect for visible damage or identity gaps and link exceptions to the affected item.
Acceptance condition
The received member and evidence map to the dispatch records and project material register; damage, missing records or untraceable items are identified and dispositioned before use. Project acceptance basis to complete from the controlled source: [Fill: Steel grade, product and certification requirements], [Fill: Project record, submission and closeout requirements], [Fill: Fabrication, subcontractor and handover boundary].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Site steel receiving and discrepancy register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Steel grade, product and certification requirements; Project record, submission and closeout requirements; Fabrication, subcontractor and handover boundary; Performing, reviewing, witness and release roles
Blank record fields
Delivery / packing list ref.; Member / piece mark; Dossier / certificate / traceability ref.; Observed transport / storage condition; Damage / missing evidence / disposition ref.

ERE-03 · Base and anchor interface before steel placement

Work stage
Base and anchor interface before steel placement
Inspection / test
Verify the assigned interface evidence for support locations and anchors before steelwork is placed or the interface becomes inaccessible.
Method
Compare the concrete/anchor handover and survey record with the approved steel drawings and project-defined interface criteria; record point/location references and unresolved deviations.
Acceptance condition
The inspected support and anchor evidence is traceable to the drawing and assigned interface acceptance source; unresolved deviations have written direction from the project-designated decision role. Project acceptance basis to complete from the controlled source: [Fill: Anchor/holding-down bolt and base interface requirements], [Fill: Project geometry / survey tolerances and evidence].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Base / anchor interface and survey record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Anchor/holding-down bolt and base interface requirements; Project geometry / survey tolerances and evidence; Performing, reviewing, witness and release roles
Blank record fields
Grid / baseplate / support mark; Anchor group / identification; Drawing / survey / concrete handover ref.; Actual position / condition / unit; Deviation / designer disposition ref.

ERE-04 · Pre-erection temporary stability and readiness documents

Work stage
Pre-erection temporary stability and readiness documents
Inspection / test
Confirm the approved project erection and temporary stability documentation relevant to the next operation is available to the assigned team.
Method
Check controlled sequence, temporary works/bracing details and any required engineered approvals or release documents; verify revisions and workfront applicability. This check does not design or validate a lift.
Acceptance condition
The applicable approved documents and responsible roles are identified for the workfront before the operation; missing or conflicting requirements are referred through the project process. Project acceptance basis to complete from the controlled source: [Fill: Approved erection sequence / temporary stability documents].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Erection readiness and briefing reference
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved erection sequence / temporary stability documents; Performing, reviewing, witness and release roles; Fabrication, subcontractor and handover boundary
Blank record fields
Planned operation / workfront; Sequence / revision; Temporary stability document / approval ref.; Briefing / interface evidence ref.; Unresolved conflict / referral ref.

ERE-05 · Member placement, orientation and temporary restraint

Work stage
Member placement, orientation and temporary restraint
Inspection / test
Inspect installed member identity, location/orientation and documented temporary restraint state against the approved erection information.
Method
Identify member and grid/location; compare orientation and connection interface with the erection drawing; record observed restraint/bracing evidence against the project sequence. Do not infer structural stability from visual appearance.
Acceptance condition
Member identity, position and required temporary restraint evidence correspond to the current approved erection documents; any difference or incomplete restraint is escalated to the assigned technical authority. Project acceptance basis to complete from the controlled source: [Fill: Approved structural and steelwork drawings / revisions], [Fill: Approved erection sequence / temporary stability documents].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Member placement and temporary restraint record
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Approved structural and steelwork drawings / revisions; Approved erection sequence / temporary stability documents; Performing, reviewing, witness and release roles
Blank record fields
Member mark; Grid / level / connection locator; Erection drawing / revision; Temporary restraint / brace ref. and observed state; Deviation / technical direction ref.

ERE-06 · Bolted connection assembly and specified verification

Work stage
Bolted connection assembly and specified verification
Inspection / test
Trace each identified bolted connection to the supplied assembly and project-specified installation/verification evidence.
Method
Identify the connection and fastener lot; compare assembly/installation records with approved connection detail and nominated procedure; record only measurements, tool checks or verification required by project documents.
Acceptance condition
The connection record identifies its project fastener source, installation procedure and required verification evidence; any missing evidence or deviation has a recorded project disposition and recheck. Project acceptance basis to complete from the controlled source: [Fill: Structural fastener system and verification requirements].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Bolted connection installation and verification log
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Structural fastener system and verification requirements; Approved structural and steelwork drawings / revisions; Performing, reviewing, witness and release roles; Project record, submission and closeout requirements
Blank record fields
Connection / grid / member marks; Fastener assembly / lot / certificate ref.; Approved installation procedure ref.; Actual specified verification / unit / tool ref.; Deviation / recheck / disposition ref.

ERE-07 · Site welded connections and inspection evidence

Work stage
Site welded connections and inspection evidence
Inspection / test
Where site welding is included, preserve a separate trace from connection identity to approved site procedure, production records and specified inspection reports.
Method
Locate weld by connection/member marks; verify the controlled site WPS and required personnel/process records; connect visual/NDT evidence and repair records to the same weld ID.
Acceptance condition
The site weld has traceable approved procedure and project-required inspection evidence; required repairs/retests and technical dispositions remain linked to the original weld and connection. Project acceptance basis to complete from the controlled source: [Fill: Site welding scope and project welding regime], [Fill: Weld category, WPS, personnel evidence and acceptance], [Fill: Specified NDT method, extent, timing and acceptance].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Site weld map and inspection / NDT index
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Site welding scope and project welding regime; Weld category, WPS, personnel evidence and acceptance; Specified NDT method, extent, timing and acceptance; Approved structural and steelwork drawings / revisions; Performing, reviewing, witness and release roles
Blank record fields
Weld ID / connection / location; Site WPS / revision; Production / operator evidence ref.; Visual / NDT report and result ref.; Repair / recheck / disposition ref.

ERE-08 · Geometry, connection completion and handover

Work stage
Geometry, connection completion and handover
Inspection / test
Record final project-specified survey/connection evidence and compile unresolved items before handing the frame to follow-on trades.
Method
Compare measured locations and completed connection evidence with identified acceptance sources; reconcile open NCRs, grout/baseplate records where included, as-built changes and required dossier items.
Acceptance condition
The final record links actual observations and reports to member/grid/connection identifiers and project criteria; unresolved items and required releases remain visible for the assigned decision-maker and follow-on trade. Project acceptance basis to complete from the controlled source: [Fill: Project geometry / survey tolerances and evidence], [Fill: Specified grout / baseplate interface scope], [Fill: Project record, submission and closeout requirements], [Fill: Approved structural and steelwork drawings / revisions].
Timing / coverage
Proposed: At the identified activity / item / lot before the next step that would obscure or change the evidence; confirm project-defined coverage and timing.
Responsible role
Proposed: Assigned fabricator / erector quality role performs and records; project-assigned reviewer acts only within documented authority. Project role basis: [Fill: Performing, reviewing, witness and release roles]
Control / release arrangement
Proposed: Internal readiness check only. Confirm any contractual Hold/Witness point, notice recipient, evidence and release authority from the project; none is assigned here. Project notice / release basis: [Fill: Performing, reviewing, witness and release roles]
Record
Steelwork completion, survey and handover register
Project document reference
Enter the governing document, revision and clause, drawing detail or register entry for this check.
Project inputs to resolve
Project geometry / survey tolerances and evidence; Specified grout / baseplate interface scope; Approved structural and steelwork drawings / revisions; Project record, submission and closeout requirements; Performing, reviewing, witness and release roles
Blank record fields
Building / grid / level / member IDs; As-built / survey report and actual value / unit; Connection completion evidence ref.; Grout / base interface report ref., if applicable; NCR / release / handover outstanding item ref.

Source notes

Connect the plan to field evidence

How to write a structural steel ITP · Compare the broader structural steel scope · Shop fabrication plan

Need an ITP prepared for your project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after the required project files are complete.

Browser editor

Loading the editable steel erection plan. Download a file above if the editor is unavailable.