TIL · Scoped work package

Free Tiling Work Package Inspection and Test Plan Template

Ordinary internal ceramic/porcelain wall and floor tiling within a building, including substrate/readiness handoff, set-out, adhesive fixing, grout, movement/junction interfaces and closeout. Waterproofing design/installation/certification, stone, external facades, pools, structural substrate repair, wet-area compliance pathway selection and project-specific numerical tolerances are excluded or treated as interfaces.

What this plan covers

Ordinary internal ceramic/porcelain wall and floor tiling within a building, including substrate/readiness handoff, set-out, adhesive fixing, grout, movement/junction interfaces and closeout. Waterproofing design/installation/certification, stone, external facades, pools, structural substrate repair, wet-area compliance pathway selection and project-specific numerical tolerances are excluded or treated as interfaces.

This free editable file is a scoped starting baseline, with proposed checks and matching blank record forms. It is not adopted project criteria. A separate paid project-specific ITP and matching blank records are available for this tiling package; customer-controlled documents may define work beyond this baseline. Confirm the actual scope, products, criteria, inspection roles and interfaces from approved project sources. Results and signatures remain blank until work is performed.

Project-specific ITP drafting for this package

A project tiling plan can map substrate readiness, set-out, product and batch checks, fixing, grout, movement joints, perimeter details and finish review to rooms and surfaces. Waterproofing remains an interface unless separately scoped; finish criteria and tolerances come from the project specification.

Useful files to provide

Example of an input still needed

For example: “The room finish schedule is attached, but the substrate release tolerance and wet-area interface owner are unclear. Please send the approved handover criteria and confirm who accepts the membrane before tiling.”

A project-specific internal wall and floor tiling ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.

How the plan and blank records fit together

The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as Room / zone / surface, Tile product / batch / size ref., Corner / floor junction ref. provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.

Define the package before tailoring it

Work areas and package boundary
Identify room/zone/location limits, drawing references, interfaces and exclusions.
Design and acceptance basis
Identify project drawings, specifications, product/system selection and the person who resolves gaps.
Materials and approved products
Identify product/system approval, delivery traceability and applicable installation instructions.
Inspection, verification and reporting basis
Copy the project method, acceptance source, trigger/frequency, role and record requirement; do not infer values.
Roles and external controls
Identify performer/reviewer, contractual notices, Hold/Witness points and release authority from project records.
Handover evidence
Identify location/as-built, photo, certificate, defect/disposition and submission requirements.

Inspection sequence and project requirements

This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.

TIL-01 · Scope, room schedule and tile-system release

Work stage
Scope, room schedule and tile-system release
Inspection / test
Confirm room/zone, wall/floor surfaces, tile selection, setting-out intent, substrate type, interfaces and governing schedule are defined.
Method
Cross-check current room finishes schedule, tile schedule, elevations, details, approved samples and project scope; raise conflicts before work.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Tiling zone release register
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Room / zone / surface; Tile product / batch / size ref.; Drawing / schedule revision; Open scope decision ref.

TIL-02 · Tile, adhesive, grout and accessory receipt

Work stage
Tile, adhesive, grout and accessory receipt
Inspection / test
Verify delivered products and accessories match approved selections and are traceable to the intended zone.
Method
Review approvals, packaging/labels, batch references, condition and supplier documentation against schedule and product instructions.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Tile and setting-material receipt record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Tile / adhesive / grout product; Batch / delivery docket ref.; Intended room / zone; Approval / substitution ref.

TIL-03 · Substrate readiness and trade handover

Work stage
Substrate readiness and trade handover
Inspection / test
Inspect the released substrate for identity, condition, cleanliness, support and project-defined readiness before tiling.
Method
Review substrate handover and relevant drawings/product instructions; document visible defects, contamination, movement or moisture evidence only where project documents require it.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Substrate readiness and handover record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Wall / floor / substrate type; Room / zone; Preceding trade release ref.; Defect / disposition ref.

TIL-04 · Layout, datum and edge/junction set-out

Work stage
Layout, datum and edge/junction set-out
Inspection / test
Check the approved tile layout, datum, cuts, thresholds, openings and junction details are transferred to the work area.
Method
Compare dry layout or marked set-out with controlled elevations, tile schedule and approved samples; record requested design decisions.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Tile set-out check record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Room / elevation / zone; Datum / control line ref.; Approved layout / drawing ref.; Set-out decision ref.

TIL-05 · Tile cutting, drilling and edge preparation

Work stage
Tile cutting, drilling and edge preparation
Inspection / test
Verify cuts, openings and edge treatments are coordinated with fixtures, trims and adjacent finishes.
Method
Inspect representative work locations against coordinated service/architectural details and tile product requirements; record chips or damage for disposition.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Tile cut and penetration coordination record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Tile / room / opening locator; Coordinated detail ref.; Service / fixture interface; Damage / decision ref.

TIL-06 · Floor tile bedding, falls and surface geometry

Work stage
Floor tile bedding, falls and surface geometry
Inspection / test
Check floor tile installation against the project layout and the specifically adopted substrate, fall, drainage and finish criteria.
Method
Inspect the floor zone and drainage interfaces using the method and criteria named in project documents; record location-specific observations and readings if required.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Floor tiling inspection record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Floor zone / grid; Waste / threshold locator; Geometry / fall source locator; Observation / photo ref.

TIL-07 · Wall tile fixing, junctions and alignment

Work stage
Wall tile fixing, junctions and alignment
Inspection / test
Check wall tile rows, corners, junctions, trims, penetrations and interface details as work progresses.
Method
Compare installation with approved elevations/details, selected system instructions and project appearance criteria; record specific locations.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Wall tiling inspection record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Wall / room / elevation; Course / datum locator; Corner / floor junction ref.; Alignment / interface decision ref.

TIL-08 · Grout, movement joints and finish protection

Work stage
Grout, movement joints and finish protection
Inspection / test
Verify grout and designated movement/interface joints are completed to the specified system and other-trade boundary.
Method
Review joint schedule and product instructions; inspect joint locations, material identity, finish and protection before handover.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Jointing and finish protection record
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Room / surface; Joint type / locator; Grout / sealant product; Protection / release status ref.

TIL-09 · Defects, cleaning and tiling handover

Work stage
Defects, cleaning and tiling handover
Inspection / test
Close the tiling scope by linking defects/dispositions, cleaning/protection status, product records and the package handover index.
Method
Reconcile room-by-room records with outstanding items and required client/project closeout documents; leave unresolved items open.
Acceptance condition
Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
Timing / coverage
At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
Responsible role
Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
Control / release arrangement
Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
Record
Tiling closeout and handover index
Project document reference
For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
Project inputs to resolve
Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
Blank record fields
Room / area; Defect / disposition ref.; Product / batch records ref.; Submission / recipient ref.

Source notes

Connect the plan to field evidence

Prepare this package and its inspection records · Choose a scoped trade template

Need your internal wall and floor tiling ITP prepared for this project?

Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.

USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.

Browser editor

Loading the editable internal wall and floor tiling plan. Download a file above if the editor is unavailable.