Scope of this guide
General construction document coordination guidance. Contract specifications, project quality procedures, safety documents and regulatory requirements determine mandatory formats, approval roles and content.
Compare purpose and user action
The documents answer different questions. The method statement sets out the proposed sequence, resources, interfaces, controls and execution approach for the activity. The ITP identifies how conformance will be inspected or tested, by whom, against which approved requirement and what evidence will be retained.
Neither document automatically approves the other. A method statement may be a referenced input to the ITP; the ITP can identify checks that must occur at stages in that method.
| Document | Primary question | Typical content | Approval/decision boundary |
|---|---|---|---|
| Method statement / work method | How will this work be executed? | Scope and sequence, interfaces, resources/equipment, work controls and linked procedures as required by the project | Acceptance/approval route is the one assigned by the contract or project procedure |
| Inspection and test plan | How will specified work requirements be verified and recorded? | Work stage, check/test, method, source criterion, role, timing/frequency if defined, control point and record | H/W and review/release effects follow the project’s defined authority and contract language |
| Risk assessment / safe work method | What hazards and safety controls apply? | Hazards, risk controls and required safe-work arrangements under the applicable system | Not replaced by either quality document |
Connect the documents with controlled references
Reference the approved method statement title, number and revision in the ITP where it informs the inspection sequence or method. In the method statement, identify the related ITP steps or inspection records where the project workflow needs the crew to stop, notify, inspect or retain evidence.
If the method changes, review whether the inspection sequence, access to inspect, test method, criteria source, control points or required evidence also change. Route both documents through the project’s revision and approval process.
Keep technical decisions in the right place
The ITP should point to the governing drawing, specification, adopted code pathway, approved product instruction or test method rather than copy uncontrolled excerpts. The method statement should not create new acceptance criteria or grant release authority unless the project documents assign it.
Neither is a substitute for engineering design, regulator/certifier decisions, permits, safety plans or completed inspection records. Link those documents where the project requires them.
Resolve coordination questions before work starts
When an ITP inspection cannot be performed at the stage proposed in the method, revise the sequence or arrange access before the work conceals the evidence. If documents conflict, raise a request for information through the project route and identify the affected activity. Do not proceed on an assumed interpretation where the contract requires a release.
Fictional example: coordinate before a concealed finish
Fictional teaching example only. A hypothetical contractor method proposes a sequence for an internal wet-area membrane, while the ITP contains a pre-cover inspection. This is not a real approved procedure or a universal hold point.
- The method statement identifies the surface preparation, product system and intended sequencing using the approved project details.
- The ITP row references the method revision and separately cites the project criteria and inspection evidence needed before covering.
- The supervisor checks whether the method leaves access for the inspection; if not, the sequence is clarified before starting.
- The ITP control type and release route are copied from the contract/project quality plan, not inferred from the example.
- A revision to the product or sequence is routed for review in both documents where it changes verification or acceptance.
Before issuing the plan
- Check which document the contract or client requires and its named revision/approval process.
- Use the method statement for execution sequence and the ITP for verification and records.
- Cross-reference document IDs and revisions where one informs the other.
- Check that the construction sequence preserves access for required inspections/tests.
- Keep safety analysis and permits linked but separately controlled.
- Raise unresolved conflicts before the affected work proceeds.
Sources and their limits
Public sources explain the planning topics below. Confirm their jurisdiction, contract context and applicable edition; use controlled project documents for the actual requirements.
- TfNSW Quality Management (Major Works) – QA
Clause 3.8.2 Inspection and Test Plans, especially required stages/frequency, method and criteria, nominated H/W points and time constraints, performing/reviewing roles, nonconformance next steps and lot close-out
Contract-specific example that ITPs sit within project quality planning and carry steps, methods, records and criteria. Does not establish a universal building ITP format.
Source reviewed: 2026-10-07
- TfNSW Guide to Quality Management System (Type 4), NQ4
Clause 8.1.2 Frequency of Testing and cross-reference to Q4 clauses 1.4 and 8.2.4.2
Public infrastructure example connecting ITP entries to specification requirements, testing frequency and review; frequency remains project/specification dependent.
Source reviewed: 2026-10-07
- Construction Quality Australia: Guide – How to Create an Inspection and Test Plan (ITP)
Public industry guide on work scope, requirements, responsibilities and review
Industry context for planning and review workflow; used as guidance, not as a governing project specification or approval.
Source reviewed: 2026-10-07