Scope of this guide
For minor cast-in-place concrete works such as kerb and gutter, crossings, footpaths, driveways and paving. The reference is ACT Government Specification SS06 Section 6, a jurisdiction-specific roadworks source. Its project values, tolerances, test frequencies and Hold Point apply only where adopted. Structural slabs, buildings and major concrete are outside scope.
Define segment limits and project controls
SS06 Section 6 separates earthworks, grading, subbase, formwork, finishing, joints, curing/protection, making good, conformance and testing. Use that as a source-specific workflow and break a long run into project-defined lots or pour segments with a consistent location key.
Before work, confirm approved cross-sections and levels, service and kerb interfaces, joint plan, concrete and reinforcement requirements, access controls, test plan and adopted inspection notices.
| Input | What the plan needs |
|---|---|
| Alignment and geometry | Approved line, levels, crossfall, transitions, crossing types, drainage interfaces and segment extents. |
| Ground and substrate | Subgrade and subbase source, preparation, test evidence, release status and locations. |
| Formwork and reinforcement | Form / slip-form method, reinforcement only where specified, cast-in items and associated evidence. |
| Concrete and finish | Specified mix, supply evidence, sampling/testing plan, finish type and curing/protection method. |
| Joints and interfaces | Approved joint drawing/schedule, existing structures, adjacent pavement and utility/kerb markers. |
| Conformance / closeout | Applicable criteria, test/report routing, defective-work process, reinstatement and as-built survey. |
Inspect in a sequence that preserves access
Keep pre-pour checks separate from finishing and final conformity. For each segment, record the drawing source and actual evidence while the feature can still be seen.
| Stage | Plan check and source locator | Record evidence |
|---|---|---|
| Set-out | Segment chainage/grid, line/level and cross-section from approved drawings. | Survey or set-out record, segment limits, any unresolved level/interface. |
| Subgrade and subbase | Project-defined preparation, material, testing and release requirements. | Test report and lot references, observed condition, level evidence, release reference where required. |
| Formwork and reinforcement | Profile, edge restraint, reinforcement/cast-ins where specified and approved detail. | Form/line/level check, reinforcement or embed record, photos before concealment if required. |
| Pre-pour readiness | Project-specified notice, cleanliness, joint materials, concrete supply and approved sequence. | Checklist/inspection record, required notices and response, mix and delivery plan, open items. |
| Placement and finish | Placement/compaction method, crossfall/profile, texture and edge treatment from contract. | Docket/sample references, event time, segment, observed finish, joint locations and any interruption. |
| Curing and protection | Specified curing method, duration and protection conditions. | Product/application or alternative method, time and area, damage/weather event, repair/recheck. |
| Final and making good | Levels, alignment, surface defects, interfaces, service reinstatement and required testing. | Survey/test records, defect/NCR, repair and recheck, as-built reference and authorised closeout. |
Blank kerb or footpath event record
Use a separate record for each work segment or a controlled form that preserves segment and pour identification. Leave results and signatures blank until the event.
| Field group | Blank fields |
|---|---|
| Control | Project: ___ Road / path / crossing: ___ Segment / lot: ___ Date / shift: ___ Record ID / revision: ___ |
| Geometry | Drawing / revision / section: ___ Chainage start/end: ___ Side / segment type: ___ Set-out record: ___ |
| Substrate | Subgrade/subbase source and lot: ___ Test report IDs: ___ Surface/level observation: ___ Release/query: ___ |
| Pre-pour | Forms/profile: ___ Reinforcement/embeds if specified: ___ Joint layout/material: ___ Inspection/notice reference: ___ |
| Concrete | Approved mix reference: ___ Docket/batch: ___ Sample/test IDs if required: ___ Placement start/finish: ___ |
| Finish and joints | Surface finish: ___ Joint type/location: ___ Measured values only where required: ___ Observation/photo: ___ |
| Curing / protection | Method/product: ___ Start/time/area: ___ Protection and damage observation: ___ Repair reference: ___ |
| Closeout | Survey/as-built: ___ NCR/defect: ___ Repair/recheck: ___ Outstanding test/record: ___ Authorised disposition: ___ |
Resolve missing project criteria before work
For a missing crossfall, joint, mix, frequency or release condition, cite the exact missing document and raise a project query before the affected work proceeds.
Fictional workflow: close one footpath segment
Fictional segment ID and records illustrate one footpath evidence trail.
- Set a fictional segment ID from the project chainage limits and approved cross-section.
- Link the actual substrate report and set-out record before creating the pre-pour event.
- Record forms, specified reinforcement and joint positions while visible; retain any required release record.
- Attach delivery and sample identifiers to the actual placement and finish record.
- Link curing/protection, survey, defects and authorised disposition before segment closeout.
Before issuing the plan
- Keep set-out, substrate, pre-pour, placement, joints, curing and final evidence traceable to a segment.
- Record the actual joint layout and interfaces.
- Record the adopted authority and revision beside the applicable geometry, testing and control requirements.
Sources and project references
- ACT Government Municipal Infrastructure Standard SS06 Footpaths and Minor Works
Section 6 Concrete Kerbs, Footpaths and Minor Works: clauses 6.01–6.15, especially scope, materials, earthworks, grading, subbase, formwork, finish, joints, curing, making good, conformance, test frequency and Schedule of Hold Points.
Official ACT engineering specification provides a detailed minor-concrete task sequence and record-worthy checks for kerbs, footpaths and related works.
Source reviewed: 2026-10-10
- NSW Government Quality Management Guidelines for Construction
Construction ITP, records, nonconformance and contract-specific review context.
Official government guidance reinforces project-based roles and record trails; not a concrete acceptance authority.
Source reviewed: 2026-10-10
Related resources
- Concrete ITP baseline and editor
- Concrete delivery record
- Concrete curing and protection record
- Roadworks project-specific drafting service
- ITP and ITR terminology
- Cross-package ITP register
- Nonconformance report
- Handover evidence index
- Asphalt Paving ITP and Daily Work Record: Mix, Delivery, Lots and Testing