Construction planning guide

Bored Pile Installation ITP: Sequence, Pile Log and Test Traceability

Organise bored-pile quality evidence around one unique pile ID. The plan, bore observations, reinforcement cage, concrete delivery, installation record and integrity/load-test reports should all resolve to that pile and the approved design.

Scope of this guide

The technical sequence is based on Main Roads Western Australia Specification 812, which is explicitly for non-displacement cast-in-situ bored reinforced concrete piles without permanent casing and excludes grouted piles. Use it only when the project adopts it. Other pile systems, casing arrangements, geotechnical design and project-specific acceptance criteria are outside this guide.

Confirm the pile system and source hierarchy

Before drafting rows, verify pile type, permanent or temporary casing, support fluid, project jurisdiction and the actual adopted specification. Specification 812 has a clear system boundary; it is not a generic bored-pile recipe. Check the project drawings, ground information, concrete/reinforcement requirements, testing schedule, contract amendments and precedence rules together.

For an adopted Specification 812 contract, clause 812.04 makes the installation plan a Hold Point and identifies proposed methods, materials, test frequencies, sequence, forms and contingency arrangements as submission content. The notice period and release role in that example belong to that contract only.

Plan for each pile before drilling starts

Create the pile register from the approved pile schedule. Give each pile a unique mark and carry it into setting-out, drilling, cleaning, cage placement, concrete, testing, nonconformance and as-built records.

Control stageSource-led plan entryRecord key
Prestart submissionPile method, equipment, materials, proposed forms, test and contingency plan required by the adopted contract.Pile ID range; procedure and revision; submission status; contract notice/release reference.
MaterialsApproved concrete, reinforcement, casing and drilling-fluid requirements from the project documents.Supplier/batch/cage/casing IDs; submittals; delivery dockets and inspection evidence.
Set-out and boringApproved set-out/design geometry, boring method and project-required support/ground observations.Pile ID; set-out evidence; date/time; actual depth/strata/support observations as defined in the form.
Bore inspectionProject-defined cleaning/inspection criteria and required reviewer before cage or concrete proceeds.Bore depth/diameter only where measured and required; base-cleaning evidence; inspection and release record.
Reinforcement and concreteApproved cage detail, spacers/cover requirements, placement sequence, mix and continuity controls.Cage ID; inspection; concrete dockets, batch/time and actual volume; sampling/test IDs.
Testing and handoverProject pile-testing scope, acceptance source, report route and as-built deliverables.Test IDs and reports; deviations; pile coordinates/levels; NCR disposition and closeout status.

Keep installation events in the same sequence as the pile log

The WA specification headings give a useful event sequence: set out; bore/excavate; clean and inspect the borehole; place reinforcement; concrete; casing extraction; cut-off; installation record; pile testing; as-built and handover. Translate those headings into project-specific rows and do not assume the WA control points apply elsewhere.

EventWhat the ITP should identifyWhat the contemporaneous log should capture
Set-outApproved pile schedule, coordinates/tolerances source, survey check and project release status.Pile mark, planned location and actual survey reference.
BoringApproved method, sequence, support-fluid requirements if applicable, and project escalation for changed ground or interruptions.Start/finish times if required, observed strata, tool/method, depth progress, fluid readings only as project-defined, interruption/deviation.
Clean and inspectThe project’s bore cleanliness/founding criteria and who reviews it before the next concealed step.Actual observations, measurements required by the project, inspection evidence, reviewer and formal release reference.
ReinforcementCurrent cage drawing, cage identity, spacers and placement requirements.Cage ID, installed position/depth and observations required by the project.
Concrete placementApproved mix, placement method, delivery/testing requirements and contingency controls.Docket/batch ID, arrival and placement times where required, actual quantities, sample IDs, observed interruption and disposition.
After placementCasing extraction/cut-off only where the system and project require them; project-defined pile tests and as-built data.Actual extraction/cut-off record, test report IDs, coordinates/levels, discrepancy/NCR and closeout decision.

Blank pile installation record structure

The specification includes an Annexure 812A Pile Installation Record. The field set below is a practical index to the event evidence, not a reproduction of that annexure or a substitute for the adopted project form.

Record groupBlank fields to complete
IdentificationProject / contract: ___ Pile ID: ___ Pile type: ___ Drawing / revision: ___ Adopted specification / revision / clause: ___
Set-outDesign coordinate / level reference: ___ Survey record ID: ___ Actual location evidence: ___
BoreDrilling method/equipment: ___ Start / finish: ___ Actual depth and observations required by project: ___ Ground change / interruption: ___
Bore acceptanceCleaning method / evidence: ___ Project criterion locator: ___ Inspection date / role: ___ Release reference if required: ___
CageCage mark / fabrication record: ___ Drawing revision: ___ Delivery ID: ___ Installation check and record: ___
ConcreteApproved mix reference: ___ Docket/batch IDs: ___ Placement start/finish: ___ Actual quantity if required: ___ Samples/tests: ___
TestingIntegrity / dynamic / static test type required by project: ___ Test provider/report ID: ___ Review/disposition reference: ___
CloseoutCut-off/as-built survey: ___ Deviation / NCR / query: ___ Authorised decision: ___ Recheck/closure evidence: ___ Open items: ___

Control technical limits instead of copying a reference project

Specification 812 includes project-specific materials, methods, Hold Points and pile-testing provisions. Do not carry its concrete provisions, notices, test frequency, geometry or release role into another job unless the contract adopts them. Even when adopted, check the current contract issue and annexures; a public PDF is evidence of that source, not evidence that it governs your project.

An ITP can prescribe how the project requires the actual bore and placement to be recorded. It cannot determine the founding stratum, approve a change in pile length, resolve an unexpected ground condition or certify capacity. Record the factual observation and route the decision to the authority named by the project.

Fictional workflow: keep a single-pile record complete

Fictional ID only. No actual bore condition, measurement, test result, acceptance or release is represented.

  1. Assign the fictional pile mark P-014 from the approved pile schedule and link its drawing revision.
  2. Complete a separate bore and cleaning event record before the cage is placed, retaining the project-defined inspection evidence.
  3. Link the cage fabrication mark and actual concrete delivery dockets to P-014 as placement occurs.
  4. Add the actual test report and as-built survey reference when received; list missing evidence as open.
  5. Record any change in pile depth or method as a query and retain the authorised written decision before closing the pile package.

Before issuing the plan

Sources and their limits

Public sources explain the planning topics below. Confirm their jurisdiction, contract context and applicable edition; use controlled project documents for the actual requirements.

Related resources

Continue with the related work

Choose the next resource for your task.

Prepare this work package

Map the selected system and controlled sources into the project form.

Record observations and follow-up

Keep actual event evidence, discrepancies and release decisions traceable.

Check related scopes

Use these resources for the stated interfaces, rather than assuming one baseline covers every system.

Browse guides by task · Browse field and quality records

Need this turned into a project-specific ITP?

Send the drawings, specifications, contract control-point requirements and required form. We prepare the scoped ITP and matching blank records, with source references and open confirmations.

USD 99 per defined work package · Excel, Word and PDF · Within 24 hours after payment and the required project files are complete.