What this plan covers
Building automatic sprinkler distribution/range pipe installation only, based on an identified approved design and project-adopted system standard. Covers material/route/support/joint/penetration coordination and receipt/review of a project-required test report from the assigned testing/commissioning party. Excludes fire hydrants, hose reels, alarms/detection, pumpsets, special hazards, domestic-system design, head fit-off unless expressly shown, pressure/functional test instructions, commissioning execution and statutory certification.
This free editable file is a scoped starting baseline, with proposed checks and matching blank record forms. It is not adopted project criteria. A separate paid project-specific ITP and matching blank records are available for this sprinkler pipe installation package; customer-controlled documents may define work beyond this baseline. Confirm the actual scope, products, criteria, inspection roles and interfaces from approved project sources. Results and signatures remain blank until work is performed.
Project-specific ITP drafting for this package
A sprinkler-pipe ITP can link material traceability, route and support checks, joints, penetrations, head interfaces and receipt of project-required test / commissioning reports by system zone. It does not provide pressure-test instructions, carry out commissioning or certify statutory compliance.
Useful files to provide
- Approved sprinkler shop drawings, hydraulic design and zone / head schedules
- Project-adopted system standard, authority approvals and notice requirements
- Approved pipe, fitting, support and penetration product evidence
- Testing / commissioning report boundary and the party responsible for each certificate
Example of an input still needed
For example: “The sprinkler shop drawings are present, but the authority approval condition and adopted test-report format are missing. Please provide the approval and identify the testing / commissioning contractor.”
A project-specific sprinkler pipe installation ITP service prepares the plan and matching blank site records for this package. The listed inputs help scope the work; if an item is unavailable, it can be recorded as an open project decision rather than guessed.
How the plan and blank records fit together
The Excel, Word and PDF downloads each contain the plan and corresponding blank record forms. For this package, entries such as System / zone, Pipe route / drawing locator, Authority / approval document ref. provide examples of location, source / product and observation or traceability fields. They are fields in the downloadable package files, not separate online records; the browser editor edits the plan only.
Define the package before tailoring it
- Work areas and package boundary
- Identify room/zone/location limits, drawing references, interfaces and exclusions.
- Design and acceptance basis
- Identify project drawings, specifications, product/system selection and the person who resolves gaps.
- Materials and approved products
- Identify product/system approval, delivery traceability and applicable installation instructions.
- Inspection, verification and reporting basis
- Copy the project method, acceptance source, trigger/frequency, role and record requirement; do not infer values.
- Roles and external controls
- Identify performer/reviewer, contractual notices, Hold/Witness points and release authority from project records.
- Handover evidence
- Identify location/as-built, photo, certificate, defect/disposition and submission requirements.
Inspection sequence and project requirements
This starting plan contains 9 inspection steps. Proposed timing and roles need project confirmation; no contractual hold point or engineering acceptance value is assigned by this template. Actual results and signatures remain blank.
FIR-01 · Building class, sprinkler scope and approved design basis
- Work stage
- Building class, sprinkler scope and approved design basis
- Inspection / test
- Confirm building classification, protected area, system type, approved design source and adopted compliance pathway are documented.
- Method
- Review project approvals, fire services drawings, applicable NCC edition/state variation and specified sprinkler standard; log any scope or edition gap.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler package design-basis register
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- Building class / use locator; System / zone type; Approved design / adopted standard ref.; Authority / approval document ref.
FIR-02 · Approved pipe, fittings and material receipt
- Work stage
- Approved pipe, fittings and material receipt
- Inspection / test
- Check pipe/fittings and listed system components are approved and traceable to the specified sprinkler system.
- Method
- Review submittals, markings, delivery documents, material identity and condition against approved design/specification/manufacturer information.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler material receipt and traceability record
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- System / zone; Pipe / fitting / component; Approval / product ID; Batch / delivery docket ref.
FIR-03 · Pipe route, zone and coordination release
- Work stage
- Pipe route, zone and coordination release
- Inspection / test
- Verify sprinkler pipe route, branch/range identity and coordinated interfaces are released before installation.
- Method
- Compare the work front against current fire drawings and coordinated ceiling/structure/service details; record clashes for approved resolution.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler route and coordination record
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- System zone / floor; Pipe route / drawing locator; Other service / structure interface; Coordination decision ref.
FIR-04 · Supports, sleeves and penetration interfaces
- Work stage
- Supports, sleeves and penetration interfaces
- Inspection / test
- Check pipe supports and building penetrations are installed at shown locations and related fire/smoke protection interfaces are identified.
- Method
- Inspect against approved support/penetration details and record the responsible trade/evidence for reinstating affected fire-rated elements.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler support and penetration interface log
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- Floor / grid / zone; Support detail / locator; Opening / fire-rated element ref.; Assigned interface owner / evidence ref.
FIR-05 · Pipe fabrication, joining and installation
- Work stage
- Pipe fabrication, joining and installation
- Inspection / test
- Inspect installed distribution/range piping, joints and identification against approved drawings and specified joining method.
- Method
- Review work records and visible joints/route against manufacturer instructions, project method and approved fire design; capture deviations by location.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler pipe installation inspection record
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- System / zone; Pipe run / joint locator; Joining method / procedure ref.; Deviation / disposition ref.
FIR-06 · Concealment readiness and protection
- Work stage
- Concealment readiness and protection
- Inspection / test
- Before concealment, reconcile installed pipe evidence, access and unresolved interface items for the identified zone.
- Method
- Review photographs/inspection evidence, ceiling coordination and project-defined notice/release process; do not mark a contractual hold point unless sourced.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler concealment readiness record
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- Ceiling / riser zone; Photo / check record ref.; Valve / access provision ref.; Project release / notice evidence ref.
FIR-07 · Pipe integrity test report interface
- Work stage
- Pipe integrity test report interface
- Inspection / test
- Identify required pressure/integrity tests from the project and receive records from the assigned qualified/testing party.
- Method
- Check submitted report references the system/zone, approved method and criteria source, equipment/results where required, defects, retests and responsible signatories.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler pipe test report receipt log
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- System / zone; Project test method / clause; Report / date locator; Leak / repair / retest disposition ref.
FIR-08 · Testing/commissioning evidence and interface status
- Work stage
- Testing/commissioning evidence and interface status
- Inspection / test
- Track the separate testing/commissioning dossier and status of valves, heads, alarms, pumps and authority interfaces without claiming their completion.
- Method
- Review only project-required records from assigned parties; identify excluded systems and unresolved prerequisites in the handover index.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Sprinkler test and commissioning interface register
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- System / zone; Test / commissioning report ref.; Assigned responsible party; Outstanding interface / approval ref.
FIR-09 · As-built, defect closeout and fire package handover
- Work stage
- As-built, defect closeout and fire package handover
- Inspection / test
- Index installed pipe scope, approved changes, inspection/test reports, open defects and required submission recipients.
- Method
- Reconcile evidence against contract and authority submission requirements; retain open items until assigned resolution is documented.
- Acceptance condition
- Project source and approved installation details identify the applicable scope, requirements and evidence for this location; record any gap or variance for assigned disposition. [Fill: Assigned performer, reviewer and external control roles] [Fill: Project inspection/testing plan and acceptance basis] [Fill: Project records and handover submission rules]
- Timing / coverage
- At the work stage identified by the project inspection plan; repeat when the applicable location, installation condition or controlled source changes. [Fill: Project inspection/testing plan and acceptance basis]
- Responsible role
- Proposed: assigned trade supervisor / quality role records the check; review and external sign-off remain with project-assigned persons acting within documented authority. [Fill: Assigned performer, reviewer and external control roles]
- Control / release arrangement
- Proposed internal readiness prompt only. Verify contractual notice, Hold/Witness point, release evidence and authority in project documents; this template assigns none. [Fill: Assigned performer, reviewer and external control roles]
- Record
- Fire sprinkler pipe closeout and handover index
- Project document reference
- For this row, record the exact project document/revision/clause, drawing/sheet/detail or product instruction supporting: Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules. Identify missing or conflicting sources for disposition. Topic references do not establish project adoption.
- Project inputs to resolve
- Assigned performer, reviewer and external control roles; Project inspection/testing plan and acceptance basis; Project records and handover submission rules
- Blank record fields
- Areas / systems covered; As-built drawing ref.; Defect / disposition index; Package submission / recipient ref.
Source notes
- training.gov.au, CPCPFS3044 Install distribution and range pipes
Installation workflow topics only. This broad pipe unit also covers other extinguishing agents; this package narrows its application to building automatic sprinkler piping and supplies no project criteria.
Official current unit PDF inspected directly (4 pages; generated 24 Dec 2024): identify requirements from job plans/specs/standards/manufacturer/jurisdiction sources; set out supports, install to design, mechanical joints, alteration isolation/drain-down and reinstate for water tightness; complete documentation.
- ABCB, NCC 2022 Volume One Specification 17 Fire sprinkler systems
Prompts identification of project building class, adopted system standard and applicable state variation. NCC 2022 is not presumed current/adopted for every project.
Official NCC page inspected: applicable sprinkler design/install standards vary by building classification/system, state variations apply and multiple AS/FPAA pathways exist.
- training.gov.au, CPCPFS4027 Commission fire sprinkler systems
Used solely to shape the commissioning report interface. This work package does not assign or teach commissioning/testing authority.
Official unit page reviewed for separation of approved design requirements, component/location/pipework inspection, specified pressure/functional testing and records.
- Construction Quality Australia, How to create an Inspection and Test Plan (ITP)
Structure and record-design guidance only. It does not create project criteria, jurisdictional rules or control points.
Public industry guide; sections on sequencing activities, method, acceptance source, responsibility, control points and records. Reviewed 2026-10-07.
Connect the plan to field evidence
- Construction Nonconformance Report and Corrective Action Record
- Construction ITP Inspection and Quality Records Register
Prepare this package and its inspection records · Choose a scoped trade template
Need your sprinkler pipe installation ITP prepared for this project?
Send your drawings, specifications and contractor requirements. Receive a project-specific ITP and matching blank site records in Excel, Word and PDF.
USD 99 per defined work package · Within 24 hours after payment and the required project files are complete.